Origins
The drawing horse ould becarried behind the coach in a covered stable waggon. In this way a single Horse would be enabled to perform the journey from Airdrie to Causewayend with a Passenger Carriage once a day, and allowing for spare Horses, five opportunities per day could be given at the expense of maintaining six Horses, with the means of conveying from 130 to 140 Passengers each way daily.Slamannan Railway Prospectus, October 1835, quoted in Martin
The Company is authorised
The company was incorporated on 3 July 1835 with a share capital of £86,000 and loan capital of £20,000. The proprietors had presented the Bill to Parliament with the minimum of publicity, and no subscription list had been prepared. Thomas Grahame had said that "The scheme is so obviously advantageous that the subscriptions would be easily filled up." The Act specified that work on construction could not start until the estimated cost of construction was fully subscribed, and this forced a delay until mid-1836, and first contracts were not let until October. John Benjamin Macneill (later to be called "the Father of the Irish railway system") was appointed principal engineer and Thomas Telford Mitchell was Resident Engineer.Whishaw; he spells Macneill "M'Neill", the common orthography for "Mac" surnames at the time. At the Annual General Meeting in February 1838 it was reported that one of the two construction contractors had failed to achieve the required output, and part of his contract was taken over by the Company directly; however a year later it was stated that both contractors had failed to achieve the required progress, and moreover that almost the whole of the subscribed capital had been expended. A further Act of Parliament was obtained in July 1839, authorising total share capital of £140,000 and the usual additional one-third of the value in borrowings.''The Railway Chronicle'', 20 May 1848, quoted in ''Robertson'' The construction process had been painful, the company "suffered during construction from 'considerable difficulty' in obtaining land, procrastinating contractors, high material costs, and problems of money raising in the deepening depression of the late 1830s"''Reports of the Committee of Management of the Slamannan Railway'', 8 February 1838 and 7 February 1837, quoted in Robertson The engineer Macneill reported to the committee of management that the nearby Wishaw and Coltness Railway had experienced difficulties with horse haulage by independent operators, referring to "the great confusion which always takes place on railways where a great number of horses are employed by persons of different interests". Prompted by Macneill, the thoughts of the Committee turned to locomotive haulage, and to the possibility of a through passenger service between Glasgow and Edinburgh. This would require the co-operation of three other railways—theOpening at last
Eventually the contractors' difficulties were overcome, and on 30 July 1840 the Directors, some shareholders, Directors of the Union Canal, and some engineers made a special journey throughout from the Garnkirk and Glasgow Railway's Townhead depot to Edinburgh over the G&GR, M&KR, BRly, the Slamannan line itself, and after transferring to a boat, the Union Canal. The railway part of this journey took 95 minutes to "Causeyend" (Causeway End) and "By one of the swift passage boats the party were conveyed from Causeyend to Edinburgh in two hours and a half—the whole journey from Glasgow to Edinburgh being thus performed in four hours with the utmost ease and pleasure."''Glasgow Herald'', 3 August 1840, quoted in ''Martin'' The Directors of the Union Canal had subscribed some of the Slamannan capital and its parliamentary costs, and evidently saw collaboration with the Slamannan as being the future. They were evidently persuaded by this demonstration run, for on 4 August they ordered a larger passenger boat for the new intercity trade. The arrival in "Edinburgh" was of course at the canal's basin at Port Hopetoun, some distance from the city centre. On 5 August 1840 the line opened, with a daily passenger train each way.Operation
Passenger
At first, the passenger trade seemed to boom, with the daily train leaving Townhead at 10:15 a.m. and the westbound journey starting by boat at 7:00 a.m. An omnibus ran from the centre of Edinburgh to connect, departing at 6:45 a.m. Fares were 7s 6d (first class and cabin on the boat), and 5s (second class and steerage). The journey took something over four hours, comparable with the stagecoach transit; a throughout boat trip over the Union Canal and the Forth and Clyde Canal continued in operation for the time being, taking 7½ hours. By October the Union Canal had procured a second boat and there were now two railway-and-canal journeys each way daily. This was now the principal means of travel between the two great cities, involving a canal boat trip, the transit of three rope-worked inclines over four railway companies, and a railway running on stone block sleepers and, west of Arbuckle, finding a path among horse-drawn coal trains. It was not long before a businessman started to operate a coach direct from Princes Street in Edinburgh to Causewayend, cutting 45 minutes off the journey (at a premium price) and of course by-passing the canal transit altogether. This proved popular, and the G&GR (apparently the driving force in this joint operation) encouraged the development of the stagecoach connection: the stagecoach operator would offer a fare reduction in return for being the favoured connection at the Edinburgh end. The Union Canal had provided considerable financial support to the Slamannan company in its early days and it was now being squeezed out. Reliability of the westbound canal trip seems to have been poor, and on 5 November 1841, the Slamannan board decided that the westbound train would leave at the advertised time whether or not the connecting boat had arrived. As this made the boat-and-railway journey practically impossible, the G&GR stopped selling through tickets for that journey, and the poor Union Canal had to try to reinvigorate its intercity business over the Forth and Clyde Canal instead. Nonetheless the railway transit was also under threat, and a fare reduction in December 1841 did little to stave off the approaching doom: on 21 February 1842 theMineral and goods
By contrast the mineral traffic was disappointing at the beginning; of course it relied on as-yet unproven pits in the area being developed. Moreover, all the trade to Edinburgh involved a transshipment to the canal at Causewayend. There was practically no goods (non-mineral) traffic. Thus in 1841 mineral receipts were £1,271 (from 26,776 tons) compared with £6,174 from passengers. The mineral tonnage climbed steadily, rising to 74,130 tons in 1845, still woefully weak.RobertsonLocomotives
At first the Company operated two locomotives on passenger duties; it seems that until March 1842 one of them worked exclusively below the Ballochney's inclines, to and from Townhead. In this period there was one goods engine operating, although the sparse traffic levels led to only one engine at a time being required for duty from 1842. The locomotive stock included ''Borealis'' from the Rowan Company and two Fairbairn locomotives, ''Thistle'' and ''Rose''.After the opening of the Edinburgh and Glasgow Railway
The Slamannan Railway had been built with high hopes of revolutionising transport between Glasgow and Edinburgh, as well as gaining access to rich new mineral fields. It was disappointed in both respects, and the opening of the Edinburgh and Glasgow Railway (E&GR) in 1842 seemed to be a hammer blow to the Slamannan company, with their primitive sleeper block railway and a suddenly out-of-date track gauge.David Turnock, ''The Historical Geography of Scotland Since 1707'', Cambridge University Press, Cambridge, 1982, Although the line gave access for the first time to isolated moorland communities, the traffic brought little money in.John Thomas revised J S Paterson, ''A Regional History of the Railways of Great Britain: Volume 6, Scotland, the Lowlands and the Borders'', David and Charles, Newton Abbot, 1984, In the best ways of management, the directors saw this as an opportunity: if they could connect to the E&GR with its more efficient connections to Edinburgh and elsewhere, they could enhance the traffic they carried. At Causewayend they were close to the E&GR and a connecting line there was the solution.Slamannan Junction Railway
Attempted take over and change of gauge
The Edinburgh and Glasgow Railway started negotiations in 1844 to take over the various Monkland coal railways; and at the same time they applied for permission to change to the gauge of the track to standard.David Ross, ''The North British Railway: A History'', Stenlake Publishing Limited, Catrine, 2014, However, in May 1846, the Edinburgh and Glasgow Railway was refused permission to amalgamate and it decide to withdraw on 31 December 1846. TheAmalgamation to form the Monkland Railways and after
On 14 August 1848 the Slamannan Railway merged with the Monkland and Kirkintilloch Railway and the Ballochney Railway to become theEngineering
The track gauge originally adopted was 4 ft 6 in, to conform to the gauge of the adjoining railways. A single line was laid with space for subsequent doubling. Rails of 50 lb per yard with a parallel single-headed profile were used. Stone blocks were used for sleepers although some timber sleepers were used also. There was an area of very poor ground at Arden Moss, where longitudinal timber bearers on cross-timbers were used in effect forming floating rafts:The line at the western end passes over a flow-moss from 30 to 40 feet deep, for a distance of 2 miles. Here the rails had to be literally floated on rafts of timber, and continued floating for some time after the trade had commenced, until at length, by continued pouring in of hard material—such as gravel, stones, &c.—this part of the road is now comparatively firm and solid. It had, however, for some months after the trains commenced to run, a very singular, and to many, an alarming appearance,—the engines and carriages, as they went along, causing a deflection of the platforms or rafts, of from 2 to 3 feet, which gradually rose to their proper level behind the train, exactly like a sluggish wave, as soon as the whole had passed over.''The Topographic, Statistical and Historical Gazetteer of Scotland'', volume second, A Fullarton & Co, Edinburgh, 1847The inclined plane at Causewayend was 800 yards (732 m) long. Murdoch, Aitken & Co supplied a 50-horsepower (37 kW) stationary engine, and Thomas Nicholson of Dundee provided the rope and "a cask of patent oil". A canal basin and wharves were provided at Causewayend, paid for jointly by the Slamannan company and the Union Canal.
The route
The North British Railway and later
The attraction to the North British Railway of purchasing the Monkland lines was access to pits and iron works on the network, and in effect the Slamannan became a mineral branch line. The passenger service continued, no longer aspiring to be other than purely local, with (in 1895) an unbalanced service of three and four trains between Coatbridge and Manuel, taking about an hour for the journey.''Bradshaw's General Steam Navigation and Railway Guide'', 12th mo, (December) 1895, reprinted by Middleton Press, Midhurst, 2011, In 1922 the service was pretty well the same.''Bradshaw's General Railway and Steam Navigation Guide'', 7th mo, (July) 1922, reprinted by Guild Publishing, London, 1985 The coal extraction on the Slamannan's line declined in the twentieth century, and in 1930 the passenger service was discontinued, and the route was severed in the centre, becoming a branch from Manuel to Avonbridge at the east end, and from Airdrie to Slamannan at the west end. These lines too closed down and by 1964 everything had closed. Paradoxically open cast mining has become widespread in the area around Arbuckle and the western extremity of the line, obliterating its course. The remainder of the route is relatively intact, crossing unpromising moorland which has seen little development.Topography
The western extremity of the Slamannan Railway was Arbuckle. Taking that as a starting point, locations on the route are located as follows: * Arbuckle station; opened 31 August 1840; closed 3 October 1862; * Whiterigg station; opened 3 October 1862; closed 1 May 1930: * Arden station; opened 31 December 1840; closed 1 May 1930; * Longriggend (earlier the location was spelt Langrigend); passenger station opened November 1862; closed 1 May 1930; * ''Limerigg Junction'': Limerigg Branch diverged to the south; coal pits; * ''North Monkland Junction'': North Monkland Railway converges from the north; opened 1878; * Slamannan station; opened 5 August 1840; closed 1 May 1930; numerous pits served by tramways on south side of the line * ''Strathavon Junction''; branch to Jawcraig pit opened 1847, converged on north side; later much extended when the pits multiplied; also known as the Strathavon Valley Branch; * Glenellrig station; opened in the late 1840s and closed 1 January 1850; * Avonbridge station; opened 5 August 1840; closed 1 May 1930; apparently on the east side of the level crossing at first, moved later to the west side * Blackstone station; opened January 1863; later Blackstone Junction, then Blackston Junction; closed 1 May 1930; branch opened 1855, diverging to the south to Bathgate; * Bowhouse station; opened late 1840s; closed 1 May 1930; Bowhouse Branch from Roughrigg Colliery opened 1868 converged from west; several mineral branches later extended the line; * ''Causewayend incline''; * ''Causewayend Junction''; the Slamannan and Borrowstounness Railway diverged to the south, and the Slamannan Junction Railway diverged to the north. The Almond Iron Works was also located at this point later, with extensive sidings on the north side of the line; * Causewayend Wharf on the Union Canal; Causewayend passenger station opened 5 August 1840; closed 1 May 1930; The Causewayend passenger station was later built on the east side of the canal, on the Slamannan and Borrowstounness Railway route to Bo'ness.Notes
References
Sources
* * * * * *Further reading
* {{Historical Scottish railway companies North British Railway Closed railway lines in Scotland Early Scottish railway companies Mining railways Pre-grouping British railway companies Railway companies established in 1835 Railway lines opened in 1840 Railway companies disestablished in 1848 Standard gauge railways in Scotland 4 ft 6 in gauge railways in Scotland 1835 establishments in Scotland 1848 disestablishments in Scotland Railway inclines in the United Kingdom