Over Budget
   HOME

TheInfoList



OR:

A cost overrun, also known as a cost increase or budget overrun, involves unexpected incurred
cost Cost is the value of money that has been used up to produce something or deliver a service, and hence is not available for use anymore. In business, the cost may be one of acquisition, in which case the amount of money expended to acquire it i ...
s. When these costs are in excess of budgeted amounts due to a
value engineering Value engineering (VE) is a systematic analysis of the functions of various components and materials to lower the cost of goods, products and services with a tolerable loss of performance or functionality. Value, as defined, is the ratio of func ...
underestimation of the actual cost during budgeting, they are known by these terms. Cost overruns are common in
infrastructure Infrastructure is the set of facilities and systems that serve a country, city, or other area, and encompasses the services and facilities necessary for its economy, households and firms to function. Infrastructure is composed of public and pri ...
,
building A building or edifice is an enclosed Structure#Load-bearing, structure with a roof, walls and window, windows, usually standing permanently in one place, such as a house or factory. Buildings come in a variety of sizes, shapes, and functions, a ...
, and
technology Technology is the application of Conceptual model, conceptual knowledge to achieve practical goals, especially in a reproducible way. The word ''technology'' can also mean the products resulting from such efforts, including both tangible too ...
projects. For IT projects, a 2004 industry study by the Standish Group found an average cost overrun of 43 percent; 71 percent of projects came in over budget, exceeded time estimates, and had estimated too narrow a
scope Scope or scopes may refer to: People with the surname * Jamie Scope (born 1986), English footballer * John T. Scopes (1900–1970), central figure in the Scopes Trial regarding the teaching of evolution Arts, media, and entertainment * CinemaS ...
; and total waste was estimated at $55 billion per year in the US alone. Many major construction projects have incurred cost overruns; cost estimates used to decide whether important transportation infrastructure should be built can mislead grossly and systematically. Cost overrun is distinguished from
cost escalation Cost escalation can be defined as changes in the cost or price of specific goods or services in a given economy over a period. This is similar to the concepts of inflation and deflation except that escalation is specific to an item or class of items ...
, which is an ''anticipated'' growth in a budgeted cost due to factors such as inflation.


Causes

Recent works by Ahiaga-Dagbui and Smith suggests an alternative to what is traditionally seen as an overrun in the construction field. They attempt to make a distinction between the often conflated causes of construction cost underestimation and eventual cost overruns. Critical to their argument is the point of reference for measuring cost overruns. Whereas some measure the size of cost overruns as the difference between cost at the time of decision to build and final completion costs, others measure the size of overruns as the difference between cost at contract award and final completion cost. This leads to a wide range in the size of overruns reported in different studies. Four types of
explanation An explanation is a set of statements usually constructed to describe a set of facts that clarifies the causes, context, and consequences of those facts. It may establish rules or laws, and clarifies the existing rules or laws in relation ...
for cost overrun exist:
technical Technical may refer to: * Technical (vehicle), an improvised fighting vehicle * Technical area, an area which a manager, other coaching personnel, and substitutes are allowed to occupy during a football match * Technical advisor, a person who ...
,
psychological Psychology is the scientific study of mind and behavior. Its subject matter includes the behavior of humans and nonhumans, both consciousness, conscious and Unconscious mind, unconscious phenomena, and mental processes such as thoughts, feel ...
,
political Politics () is the set of activities that are associated with decision-making, making decisions in social group, groups, or other forms of power (social and political), power relations among individuals, such as the distribution of Social sta ...
-
economic An economy is an area of the Production (economics), production, Distribution (economics), distribution and trade, as well as Consumption (economics), consumption of Goods (economics), goods and Service (economics), services. In general, it is ...
,
value engineering Value engineering (VE) is a systematic analysis of the functions of various components and materials to lower the cost of goods, products and services with a tolerable loss of performance or functionality. Value, as defined, is the ratio of func ...
. Technical explanations account for cost overrun in terms of imperfect
forecasting Forecasting is the process of making predictions based on past and present data. Later these can be compared with what actually happens. For example, a company might Estimation, estimate their revenue in the next year, then compare it against the ...
techniques, inadequate data, etc. Psychological explanations account for overrun in terms of
optimism bias Optimism bias or optimistic bias is a cognitive bias that causes someone to believe that they themselves are less likely to experience a negative event. It is also known as unrealistic optimism or comparative optimism. It is common and transcends ...
with forecasters.
Scope creep Scope creep (also called requirement creep, or kitchen sink syndrome) in project management is continuous or uncontrolled growth in a project's scope, generally experienced after the project begins. This can occur when the scope of a project i ...
, where the requirements or targets rises during the project, is common. Finally, political-economic explanations see overrun as the result of
strategic misrepresentation The planning fallacy is a phenomenon in which predictions about how much time will be needed to complete a future task display an optimism bias and underestimate the time needed. This phenomenon sometimes occurs regardless of the individual's knowl ...
of scope or budgets. Historically, political explanations for cost overrun have been seen to be the most dominant. In the USA, the architectural firm Home Architects has attributed this to a human trait they call "Psychology of Construction Cost Denial", regarding the cost inflation of custom homes. A less explored possible cause of cost overruns on construction project is the
escalation of commitment Escalation of commitment is a human behavior pattern in which an individual or group facing increasingly negative outcomes from a decision, action, or investment nevertheless continue the behavior instead of altering course. The actor maintains ...
to a course of action. This theory, grounded in social psychology and organisation behaviour, suggests the tendency of people and organisations to become locked-in and entrapped in a particular course of action and thereby 'throw good money after bad' to make the venture succeed. This defies conventional rationality behind subjective expected utility theory. Ahiaga-Dagbui and Smith explore the effects of
escalation of commitment Escalation of commitment is a human behavior pattern in which an individual or group facing increasingly negative outcomes from a decision, action, or investment nevertheless continue the behavior instead of altering course. The actor maintains ...
on project delivery in construction using the case of the
Scottish Parliament The Scottish Parliament ( ; ) is the Devolution in the United Kingdom, devolved, unicameral legislature of Scotland. It is located in the Holyrood, Edinburgh, Holyrood area of Edinburgh, and is frequently referred to by the metonym 'Holyrood'. ...
project. Also, a recent study has suggested that principles of chaos theory can be employed to understand how cost overruns emerge in
megaprojects A megaproject is an extremely large-scale construction and investment project. A more general definition is "Megaprojects are temporary endeavours (i.e. projects) characterised by: large investment commitment, vast complexity (especially in org ...
. This paper seeks to reclassify megaprojects as chaotic systems that are nonlinear and therefore difficult to predict. Using cases of cost overruns in oil and gas megaprojects, this study makes strong argument that chaos theory can indeed be a silver bullet in finding solutions to the recurring problem of cost overruns in megaprojects. A newly discovered possible cause of cost overruns is
value engineering Value engineering (VE) is a systematic analysis of the functions of various components and materials to lower the cost of goods, products and services with a tolerable loss of performance or functionality. Value, as defined, is the ratio of func ...
, and an approach to correct value engineering cost overruns known as value-driven-design.


Prevention and mitigation

In response to problem of cost overruns on major projects, the UK Government set up a Major Projects Authority to provide
project assurance Project assurance or programme assurance is a discipline that seeks to provide an independent and objective oversight of the likely future performance of major projects for those responsible for sanctioning, financing or insuring such undertakings. ...
to HM Treasury and other Government departments undertaking major projects. Independent review of the financial effectiveness of project assurance in reducing cost overruns found the project assurance process to be effective in reducing cost overruns and recommended an expansion of the process to cover most of the Government's project portfolio. Project assurance is now also being used by private sector companies undertaking major projects.


Describing

Cost overrun can be described in multiple ways. * As a percentage of the total expenditure * As a total percentage including and above the original budget * As a percentage of the cost overruns to original budget For example, consider a bridge with a construction budget of $100 million where the actual cost was $150 million. This scenario could be truthfully represented by the following statement * The cost overruns constituted 33% of the total expense. * The budget for the bridge increased to 150%. * The cost overruns exceeded the original budget by 50%. The final example is the most commonly used as it specifically describes the cost overruns exclusively whereas the other two describe the overrun as an aspect of the total expense. In any case care should be taken to accurately describe what is meant by the chosen percentage so as to avoid ambiguity.


List of projects with large cost overruns


Australia

*
Sydney Opera House The Sydney Opera House is a multi-venue Performing arts center, performing arts centre in Sydney, New South Wales, Australia. Located on the foreshore of Sydney Harbour, it is widely regarded as one of the world's most famous and distinctive b ...
was completed ten years late and more than fourteen times over budget.


Canada

*
Canadian Firearms Registry The Canadian Firearms Registry () is the gun registry of Canada, requiring the registration of all restricted and prohibited firearms in the country. It is managed by the Canadian Firearms Program of the Royal Canadian Mounted Police (RCMP) as ...
, initially projected to cost Canadian taxpayers $CAN 2 million, ended up being 1,000 times over budget at $CAN 2 billion *
Trans Mountain pipeline The Trans Mountain Pipeline System, or simply the Trans Mountain Pipeline (TMPL), is a multiple product pipeline system which carries crude and refined products from Edmonton, Alberta, to the coast of British Columbia, Canada. The corporation ...
expansion comes in 70 per cent higher than expected. Trans Mountain Corporation announced the projected cost of the pipeline expansion has soared from its earlier estimate of $12.6 billion to $21.4 billion.


United Kingdom

*The
NHS The National Health Service (NHS) is the term for the publicly funded health care, publicly funded healthcare systems of the United Kingdom: the National Health Service (England), NHS Scotland, NHS Wales, and Health and Social Care (Northern ...
patient records system, implemented as part of the
National Programme for IT The NHS Connecting for Health (CFH) agency was part of the UK Department of Health and was formed on 1 April 2005, having replaced the former NHS Information Authority. It was part of the Department of Health Informatics Directorate, with the ro ...
, was originally estimated to cost £6.4bn and eventually abandoned before completion after £10bn were spent. It was described as "one of the worst and most expensive contracting fiascos in the history of the public sector". *
Scottish Parliament Building The Scottish Parliament Building (; ) is the home of the Scottish Parliament at Holyrood, Edinburgh, Holyrood, within the World Heritage Site, UNESCO World Heritage Site in central Edinburgh. Construction of the building commenced in June 1999 ...
, originally "expected to take two years and cost £40 million" but "took five years and cost £400 million". *
Edinburgh Trams Edinburgh Trams is a tramway in Edinburgh, Scotland, operated by Edinburgh Trams Ltd. It is an line between Newhaven, Edinburgh, Newhaven and Edinburgh Airport, with 23 tram stops, stops. A modern tram network for Edinburgh was proposed by ...


United States

* The
Big Dig The Big Dig was a megaproject in Boston that rerouted the then elevated Central Artery of Interstate 93 that cut across Boston into the O'Neill Tunnel and built the Ted Williams Tunnel to extend Massachusetts Turnpike, Interstate 90 to Logan I ...
, a multi-billion dollar highway reconstruction in Boston, was delivered nine years late with a cost overrun of 190% adjusted for inflation. * The
Boeing Dreamliner The Boeing 787 Dreamliner is an American wide-body airliner developed and manufactured by Boeing Commercial Airplanes. After dropping its unconventional Sonic Cruiser project, Boeing announced the conventional 7E7 on January 29, 2003, whi ...
programme, announced in 2003, was supposed to cost $6 billion and see the plane take to the air in 2008. The final bill was closer to $32 billion; and the plane arrived three years late.


Germany

*
Berlin Brandenburg Airport Berlin Brandenburg Airport () () is an international airport in Schönefeld, just south of the Germany, German capital and state of Berlin, in the state of Brandenburg. Named after the former Mayor of West Berlin, West Berlin mayor and Chance ...
: 1 billion euro → 6 billion euro *
Elbe Philharmonic Hall The Elbphilharmonie (; "Elbe Philharmonic Hall"), popularly nicknamed Elphi, is a concert hall in the HafenCity quarter of Hamburg, Germany, on the Grasbrook peninsula of the Elbe River. The new construction resembles a hoisted sail, water wave ...
in Hamburg: 77 million euro → 789 million euro * Landesarchiv Nordrhein-Westfalen in Duisburg: 30 million euro → 195 million euro *
Staatsoper Unter den Linden The Staatsoper Unter den Linden ( State Opera under the Lime Trees), also known as the Berlin State Opera (), is a listed building on Unter den Linden boulevard in the historic center of Berlin, Germany. The opera house was built by order of Pr ...
: 240 million euro → 400 million euro


Finland

* Olkiluoto Nuclear Power Plant Unit 3: 3 billion euro → 8.5 billion euro (as of 2017, project still ongoing) *Helsinki Western Metro Extension: 400 million euro → 1.19 billion euro (September 2017)


Russia

*
2014 Winter Olympics The 2014 Winter Olympics, officially called the XXII Olympic Winter Games () and commonly known as Sochi 2014 (), were an international winter multi-sport event that was held from 7 to 23 February 2014 in Sochi, Russia. Opening ro ...
in
Sochi Sochi ( rus, Сочи, p=ˈsotɕɪ, a=Ru-Сочи.ogg, from  – ''seaside'') is the largest Resort town, resort city in Russia. The city is situated on the Sochi (river), Sochi River, along the Black Sea in the North Caucasus of Souther ...
: US$12 billion → US$51 billion *
Krestovsky Stadium Krestovsky Stadium, known as Gazprom Arena for sponsorship reasons (), is a retractable roof stadium with a retractable pitch in the western portion of Krestovsky Island in Saint Petersburg, Russia, which serves as home for FC Zenit Saint Peter ...
in
St Petersburg Saint Petersburg, formerly known as Petrograd and later Leningrad, is the List of cities and towns in Russia by population, second-largest city in Russia after Moscow. It is situated on the Neva, River Neva, at the head of the Gulf of Finland ...
= 548%


See also

* * * * * * * * * * *


References


External links


The RISKS digest
(focuses on failed and overran IT projects) {{DEFAULTSORT:Cost Overrun Costs