The Simcoe Street tunnel is located between Front Street and Bremner Blvd. in
Toronto
Toronto ( , locally pronounced or ) is the List of the largest municipalities in Canada by population, most populous city in Canada. It is the capital city of the Provinces and territories of Canada, Canadian province of Ontario. With a p ...
, Ontario, Canada. This tunnel is situated in a densely urban site below the
SkyWalk
The SkyWalk is an approximately 160 metre enclosed walkway connecting Union Station to the CN Tower and the Rogers Centre (SkyDome) in Toronto, Ontario, Canada. Part of Toronto's PATH network, the SkyWalk passes above the York Street ' s ...
and in close proximity to Toronto Union Station and the
InterContinental Toronto Centre hotel. The tunnel roof structure is designed to carry all 16 pre-existing railway tracks. The ground structure provides one vehicle lane north bound and two lanes south bound, one bicycle lane and one extra wide pedestrian sidewalk on each side of the tunnel.
The Simcoe Street tunnel was officially opened on September 22, 2009 by Councillor
Adam Vaughan.
Construction
Construction of the tunnel began in late 2006 and was carried out in stages. Thin soil cover prohibited the use of bored tunnel and hacked tunnel methods. For each stage the substructure was first constructed within the excavated trenches to the underside of the temporary trestles.
A key component in building the tunnel was the readily available supply of precast deck segments nearby. The project required 1.6 kilometres of girders so Soncin, who was contracted by Fairmont Developments to construct the extension of Simcoe Street, built a precast facility on site. A total of 153 girders were produced in three months. Fifty-one girders were post tensioned and 102 girders were normally reinforced.
Design and construction of the tunnel posed significant challenges as the
Union Station
A union station, union terminal, joint station, or joint-use station is a railway station at which the tracks and facilities are shared by two or more separate railway company, railway companies, allowing passengers to connect conveniently bet ...
corridor has the highest train volume for a single terminus location in North America.
It was necessary to maintain the normal operation schedule of the railway corridor during construction. In order to not cause any disruption to the operation of 16 tracks, construction was scheduled during train work blocks.
Morrison Hershfield the project managers, designers, contract administrators and site engineers, worked with the railway companies including
Via Rail
Via Rail Canada Inc. (), operating as Via Rail or Via (stylized as VIA Rail), is a Canadian Crown corporation that operates intercity passenger rail service in Canada.
As of December 2023, Via Rail operates 406 trains per week across eight ...
,
Canadian National Railway
The Canadian National Railway Company () is a Canadian Class I freight railway headquartered in Montreal, Quebec, which serves Canada and the Midwestern and Southern United States.
CN is Canada's largest railway, in terms of both revenue a ...
,
Amtrak
The National Railroad Passenger Corporation, Trade name, doing business as Amtrak (; ), is the national Passenger train, passenger railroad company of the United States. It operates intercity rail service in 46 of the 48 contiguous United Stat ...
and
GO Transit
GO Transit is a regional public transit system serving the Greater Golden Horseshoe region of Ontario, Canada. With its hub at Union Station in Toronto, GO Transit's green-and-white trains and buses serve a population of more than seven mil ...
to ensure the services of 177 daily scheduled trains that passed over the tunnel were maintained. Some trains were temporarily rerouted to adjacent tracks.
Environmental and social impacts
To help protect the environment during construction of the tunnel a Quality Management Plan was set in place. This plan ensured all waste materials were disposed of according to government regulations. Disposal techniques were also monitored for compliance.
By not affecting the existing rail service of the 177 trains per day using the corridor, a risk of loss of ridership was removed that could have occurred in relation to potential delays. Long and short distance travellers were continuously able to get to their destinations as planned, which helped to avoid an increase in the use of personal vehicles.
A lasting environmental impact after construction is the improved access to the
Lake Ontario
Lake Ontario is one of the five Great Lakes of North America. It is bounded on the north, west, and southwest by the Canadian province of Ontario, and on the south and east by the U.S. state of New York (state), New York. The Canada–United Sta ...
waterfront within the City of Toronto. The original rail corridor was a major physical barrier between the downtown and the lakefront where continuous residential, recreational and business developments are occurring.
The tunnel reduces the length of vehicular travel time and associated carbon emissions, and the new ease of access promotes carbon-free travel, i.e., bicycling and walking.
Former Mayor of Toronto,
David Miller was quoted saying “The Simcoe Street underpass will improve downtown traffic flow and help provide important services to future development on the lands south of Union Station. But most importantly, the project will improve access to our waterfront for all Torontonians."
According to the city report published in 2014, the underpass was flooded 5 times between 2010 and 2013.
See also
*
Lower Simcoe Street underpass murals
*
Toronto Waterfront
The Toronto waterfront is the lakeshore of Lake Ontario in the city of Toronto, Toronto, Ontario, Canada. It spans 46 kilometres between the mouth of Etobicoke Creek in the west and the Rouge River (Ontario), Rouge River in the east.
History
L ...
References
{{coord, 43, 38, 37, N, 79, 23, 04.5, W, region:CA-ON_type:landmark, display=title
Buildings and structures in Toronto
Geography of Toronto
Road tunnels in Ontario
Transport in Toronto