Viking Link is a 1,400 MW
HVDC A high-voltage direct current (HVDC) electric power transmission system uses direct current (DC) for electric power transmission, in contrast with the more common alternating current (AC) transmission systems. Most HVDC links use voltages betwe ...
submarine power cable A submarine power cable is a transmission cable for carrying electric power below the surface of the water.National Grid plc National Grid plc is a British multinational electricity and gas utility company headquartered in London, England. Its principal activities are in the United Kingdom, where it owns and operates electricity and natural gas transmission networks ...
and Danish
Energinet Energinet is the Danish national transmission system operator for electricity and natural gas. It is an independent public enterprise owned by the Danish state under the Ministry of Climate and Energy. Energinet has some 1150 employees, ...
.


Route

The cable runs between
Bicker Fen Bicker is a village in the Borough of Boston, Lincolnshire, England. The population of the village was 941 at the 2011 census. It is situated approximately west-south-west from Boston, and on the A52 road. History The medieval estuary, Bi ...
in
Lincolnshire Lincolnshire (), abbreviated ''Lincs'', is a Ceremonial counties of England, ceremonial county in the East Midlands and Yorkshire and the Humber regions of England. It is bordered by the East Riding of Yorkshire across the Humber estuary to th ...
, UK, and Revsing in southern
Jutland Jutland (; , ''Jyske Halvø'' or ''Cimbriske Halvø''; , ''Kimbrische Halbinsel'' or ''Jütische Halbinsel'') is a peninsula of Northern Europe that forms the continental portion of Denmark and part of northern Germany (Schleswig-Holstein). It ...
, Denmark. The cable has a total length of , of which is undersea, passing through Danish, German, Dutch and British waters. It crosses the long
NorNed NorNed is a long high-voltage direct current submarine power cable between Feda, Norway and the seaport of Eemshaven in the Netherlands, which interconnects both countries' electrical grids. It was once the longest submarine power cable in the ...
submarine power cable.


Specification

The interconnector is capable of transmitting up to 1,400 MW at 525  kV, resulting in an annual transmission capacity of 12.3 TWh. The actual cable is made of copper, steel, paper and plastic and weighs about 40 kg per metre. It is similar in capacity and length to the UK–Norway
North Sea Link The North Sea Link is a 1,400MW high-voltage direct current submarine power cable between Norway and the United Kingdom. At it was the longest subsea interconnector in the world when it became operational on 1 October 2021. Route The cable ru ...
.


Project history

In November 2015 Viking Link was put on the EU "Projects of Common Interest" list, along with the
COBRAcable COBRAcable (''COpenhagen-BRussels-Amsterdam cable'') is a ±320 kV, 700 MW High-voltage direct current, HVDC submarine power cable pair between Eemshaven, the Netherlands and Endrup near Esbjerg, Denmark. The cable is jointly owned by E ...
between Jutland and the Netherlands, and the Krieger offshore wind turbine cable to Germany. In January 2017 Viking Link announced a €1.3 billion tender for seven contracts that detail all aspects of constructing and later maintaining both the land and sea components of the link. In March 2017
Fugro Fugro NV is a Dutch Multinational corporation, multinational public company headquartered in Leidschendam, Netherlands. The company is primarily a service company focused on geotechnical, survey and geoscience services, and is listed on Euron ...
announced the completion of their contract to survey the seabed for the subsea section of the interconnector. According to some experts including National Grid's head of strategy the UK's decision to leave the EU can negatively influence the effort to link the UK power grid with the continent and may put planned interconnectors such as Viking Link on hold. In reaction to the Brexit referendum Viking Link stated that the plans to build and operate the interconnector remain unchanged and that they consider the project unlikely to be influenced since it has a strong business case, while National Grid claims that leaving the internal energy market would jeopardize interconnector projects such as Viking Link. In July 2019 Viking Link announced three contracts totaling €1.1 billion, one with
Siemens Energy Siemens Energy AG is a German publicly-traded energy corporation formed through the spin-off of the former Gas and Power division of Siemens, and it includes full ownership of Siemens Gamesa. Christian Bruch is the CEO, and the former CEO of S ...
for the two onshore substations and two for the manufacture and laying of the undersea cables to be done by Prysmian Powerlink S.r.l. and
NKT The New Kadampa Tradition – International Kadampa Buddhist Union (NKT—IKBU) is a global Buddhist new religious movement founded by Kelsang Gyatso in England in 1991. In 2003 the words "International Kadampa Buddhist Union" (IKBU) were a ...
HV Cables AB. Construction work was scheduled to start mid-2020 and expected to be complete by end 2023. In November 2019, it was announced that preparation work had started on the beach in Denmark. In December 2019, contracts were awarded for the UK onshore construction works. In July 2020, Viking Link announced that work had started on the 475 mile (765 km) interconnector. Construction commenced with the building of an access road at Bicker Fen. In February 2021,
Balfour Beatty Balfour Beatty plc () is an international infrastructure group based in the United Kingdom with capabilities in construction services, support services and infrastructure investments. A constituent of the FTSE 250 Index, the company is active ac ...
started drilling work for the project. Land cables and submarine cables were installed between 2020 and 2023. In 2023 the cable laying contractor Prysmian announced that the land cables and 870 km of the 1250 km dual subsea cable had been laid with the remaining 380 km subsea cable to be laid between April and July 2023. The undersea section of the link was completed in July 2023. In August 2023 the cable including its terminations, land and subsea joints completed final electric testing at 735 kV, i.e. 40% above its nominal operating voltage. A new 400kV supporting power line in Denmark to increase internal transmission capacity (and reduce overhead power lines from 324 km to 145 km) was delayed until late 2025. Commissioning of the subsea cable started during November and December 2023 and commercial operation commenced on 29 December 2023. However, capacity was limited to 800 MW until the associated grid is completed in Denmark around 2025. From 14 January 2024 the Danish transmission system operator ''Energinet'' implemented changes that allow Viking Link to transmit at its full capacity under certain circumstances. As such, from 15 to 19 January where the Dutch-Danish
COBRAcable COBRAcable (''COpenhagen-BRussels-Amsterdam cable'') is a ±320 kV, 700 MW High-voltage direct current, HVDC submarine power cable pair between Eemshaven, the Netherlands and Endrup near Esbjerg, Denmark. The cable is jointly owned by E ...
was undergoing maintenance, Viking Link was able to transmit at its full capacity. In February 2024 the cable suffered an outage after a minor fire in a switching station in Revsing, Denmark. From its commencement of commercial operation on 29 December 2023 until the end of Q1 2024 Viking Link transmitted 1733 GWh, for a
capacity factor The net capacity factor is the unitless ratio of actual electrical energy output over a given period of time to the theoretical maximum electrical energy output over that period. The theoretical maximum energy output of a given installation is def ...
of 55%. The transmission was from Denmark to the UK 80% of the time.


Economic impact

The cable will increase the UK's electricity interconnection level (transmission capacity relative to production capacity) from its comparatively low rate of 6% in 2014.COM/2015/082 final: "Achieving the 10% electricity interconnection target
TextPDF
page 2-5. ''
European Commission The European Commission (EC) is the primary Executive (government), executive arm of the European Union (EU). It operates as a cabinet government, with a number of European Commissioner, members of the Commission (directorial system, informall ...
'', 25 February 2015
ArchiveMirror
/ref> The Viking Link connects the UK to the west Denmark bidding area (DK1) of
Nord Pool Spot Nord Pool AS is a pan-European power exchange. Nord Pool has its main office in Oslo and further offices in Stockholm, Helsinki, Tallinn and London London is the Capital city, capital and List of urban areas in the United Kingdom, lar ...
. An analysis in 2016 showed a DKK 5.6 billion overall benefit for the society using Viking Link, and a DKK 20 billion benefit for heat pumps in district heating. Combining the two yields a benefit of DKK 22.8 billion. By 2022 prices in Denmark were projected to rise by 15 DKK/MWh, and fall in England. The investment was estimated at 13.4 billion DKK. By the first quarter of 2024 Viking Link had earned ca 20 million Euro, to be evenly split between National Grid plc and Energinet.


See also

*
Electricity sector in Denmark Denmark's western electrical grid is part of the Synchronous grid of Continental Europe whereas the eastern part is connected to the Synchronous grid of Northern Europe via Sweden. In 2022, Denmark produced 35 Terawatt-hours (TWh) of electric ...
*
Electricity sector in the United Kingdom The National Grid covers most of mainland Great Britain and several of the surrounding islands, and there are interconnectors to Northern Ireland and to other European countries. Power is supplied to consumers at 230 volts AC with a frequen ...
*
Energy in Denmark Denmark has considerable sources of oil and natural gas in the North Sea and ranked as number 32 in the world among net exporters of Petroleum, crude oil in 2008. Denmark expects to be self-sufficient with oil until 2050.
*
Energy in the United Kingdom Total energy consumption in the United Kingdom was 142.0million tonnes of oil equivalent (1,651TWh) in 2019. In 2014, the UK had an energy consumption ''per capita'' of 2.78tonnes of oil equivalent (32.3MWh) compared to a world average of 1 ...
*
List of high-voltage transmission links in Denmark List of high-voltage transmission links in Denmark including some under construction or proposed. International links In addition to the above named, submarine interconnectors Denmark has 400 kV, 220 kV and 150 kV AC transmiss ...
*
List of high-voltage transmission links in the United Kingdom The following is a list of high-voltage transmission links in the United Kingdom, including some under construction or proposed. The rise of UK interconnection The main direction of interconnector flows is into the UK electricity market. Duri ...
*
Triton Knoll Triton Knoll Wind Farm is an 857 MW round 2 offshore wind farm off the coast of Lincolnshire, in the North Sea, England. RWE Npower Renewables were awarded the lease to the development area in 2003. The offshore elements of the wind farm of ...
, an 857 MW offshore wind farm under construction, also with an onshore cable linking to Bicker Fen


References


External links

* {{Official website, viking-link.com
Project route in England

Map with power line and substation
Electric power infrastructure in Denmark Electric power infrastructure in England Electrical interconnectors in the North Sea Electrical interconnectors to and from Great Britain Electrical interconnectors to and from the Synchronous Grid of Continental Europe HVDC transmission lines Denmark–United Kingdom relations 2023 establishments in Denmark 2023 establishments in the United Kingdom