Suki Kinari Hydropower Project
   HOME

TheInfoList



OR:

SK Hydro also known as Suki Kinari HPP, is a
run-of-the-river Run-of-river hydroelectricity (ROR) or run-of-the-river hydroelectricity is a type of hydroelectric generation plant whereby little or no water storage is provided. Run-of-the-river power plants may have no water storage at all or a limited amou ...
hydropower project located on the
Kunhar River The Kunhar River () or River Kunhar, is a long river, located primarily in the Khyber Pakhtunkhwa province, northern Pakistan. It is in the Indus River watershed basin. Origin and route Kunhar is the main river in the Naran Valley. It orig ...
at
Balakot Tehsil Balakot Tehsil () is an administrative subdivision (tehsil) of Mansehra District in the Khyber-Pakhtunkhwa province of Pakistan Balakot is the main city of this. It was one of the towns that was devastated in the 2005 Kashmir earthquake with aroun ...
in District Mansehra,
Khyber Pakhtunkhwa Khyber Pakhtunkhwa (; ; , ; abbr. KP or KPK), formerly known as the North West Frontier Province (NWFP), is a Administrative units of Pakistan, province of Pakistan. Located in the Northern Pakistan, northwestern region of the country, Khyber ...
, which has an installed generation capacity of 884 MW. The project's deal was finalized in 2014, with the financial closure occurring in January 2017. The project is sponsored by Chinese state-owned company
Gezhouba Group China Gezhouba Group Company Limited () is a Chinese construction and engineering company based in Wuhan, Hubei. As of 2014, the company is the 33rd largest contractor by revenue in the world. The major shareholder of the company (40.8%) is stat ...
, and is being constructed as part of the
China–Pakistan Economic Corridor China–Pakistan Economic Corridor (CPEC; zh, c=中巴经济走廊, p=Zhōng bā jīngjì zǒuláng; ) is a 3,000 km Chinese infrastructure network project currently under construction in Pakistan. This sea-and-land-based corridor aims to ...
's "Early Harvest" projects. The project was successfully commissioned on September 13, 2024.


Background

The project was first envisaged in 1960, and feasibility studies have been carried out by German GTZ,
Quebec Quebec is Canada's List of Canadian provinces and territories by area, largest province by area. Located in Central Canada, the province shares borders with the provinces of Ontario to the west, Newfoundland and Labrador to the northeast, ...
based Montreal Engineering and recent detailed design and engineering study was performed by
Mott MacDonald The Mott MacDonald Group is a management, engineering and development consultancy headquartered in the United Kingdom. It employs over 19,000 staff in 150 countries. Mott MacDonald is one of the largest employee-owned companies in the world. ...
of England. The Private Power and Infrastructure Board of Pakistan identified a number of sites in the country that were deemed attractive for their hydropower potential. In March 2005, PPIB publicly advertised seven hydropower sites for implementation in the private sector pursuant to the Policy for Power Generation Projects 2002. SK Hydro Consortium, having the requisite technical and financial strength, submitted its bid for the Suki Kinari Hydropower project. The consortium was prequalified, and a Letter of Interest (LOI) for conducting a feasibility study of the project was issued to SK Hydro on 15 November 2005. The government of the province of Khyber Pakhtunkhwa, Pakistan, announced on August 24, 2016, that it has signed an agreement with SK Hydro Private Ltd. and Industrial and Commercial Bank of China to develop and construct the dam.


Project details

The dam will be constructed as a 54.5 meter high and 336 meter wide concrete gravity dam with 2 gated spillways. Four 221 MW turbines are to be installed as part of the project, and will generate 884 MW of electricity in total. Construction of the dam will result in the formation of a 3.1 kilometer long reservoir with a capacity of 9 million cubic meters of water. It will not cause large scale displacement of populations as no villages or towns will be inundated by the resulting dam's reservoir, although a four kilometer section of the Kaghan-Naran highway will have to be diverted as a result of construction works and the resulting reservoir. Accompanying transmission lines will be constructed by Pakistan's National Transmission and Dispatch Company, and is not considered complementary to the project, but is to be constructed separately from the dam itself. The project was successfully commissioned on September 13, 2024.


Financing and tariff

The project is being built on a "Build, Own, Operate and Transfer" basis in accordance with Government of Pakistan's Policy for Power Generation Projects 2002. The dam is being developed by Pakistan'
SK Hydro
group and China's
Gezhouba Group China Gezhouba Group Company Limited () is a Chinese construction and engineering company based in Wuhan, Hubei. As of 2014, the company is the 33rd largest contractor by revenue in the world. The major shareholder of the company (40.8%) is stat ...
. In April 2015, an agreement for 75% of financing costs was signed by the developers and the
Exim Bank of China Exim is a mail transfer agent (MTA) used on Unix-like operating systems. Exim is a free software distributed under the terms of the GNU General Public License, and it aims to be a general and flexible mailer with extensive facilities for checkin ...
and
Industrial and Commercial Bank of China The Industrial and Commercial Bank of China (ICBC; zh, 中国工商银行) is a Chinese partially state-owned multinational banking and financial services corporation headquartered in Beijing, China. It is the largest of the " big four" banks ...
. The project achieved financial close on December 31, 2016. The projected cost for the project was initially projected to be $1.314 billion, but as a result of devaluation of the Pakistani Rupee, the cost is now estimated to be $1.8 billion. The Government of Pakistan has agreed to purchase electricity fro
SK Hydro
at a cost of 8.8415 US cents per kilowatt-hour for the 30 years on the cost-plus basis.


References

{{stack, {{Portal, Pakistan, Water, Renewable energy Hydroelectric power stations in Pakistan Mansehra District China–Pakistan Economic Corridor Dams in Pakistan Dams under construction Concrete-face rock-fill dams Dams in the Indus River basin 2017 establishments in Pakistan