Prerequisite for Valid Time Standards
*The task is performed by an average worker *The worker's pace represents standard performance *The worker uses the standard method *The task is performed on a standard work unitCalculating the Standard Time
The standard time (Ts) is calculated from multiplying the observed time (To) by the performance rating (R) and the personal need, fatigue and unavoidable delays (PFD): Ts = To*R*(1+PFD)Usages for Standard Time
*Estimate the quantity of the production *Determine workforce size and equipment requirement *Compare alternative methods *Evaluate worker's performance *Plan and schedule production and estimate co.Further reading
*''Work Systems: The Methods, Measurement & Management of Work'' by Mikell P. Groover, Prentice-Hall (2006) *''Work Measurement and Methods Improvement'' by Lawrence S. Aft, Wiley (2000) {{DEFAULTSORT:Standard Time In Manufacturing Industrial engineering