Misicuni Dam
   HOME

TheInfoList



OR:

The Misicuni Multiplepurpose Project, better known as the Misicuni Dam, is a
concrete-face rock-fill dam A dam is a barrier that stops or restricts the flow of surface water or underground streams. Reservoirs created by dams not only suppress floods but also provide water for activities such as irrigation, drinking water, human consumption, Indust ...
constructed on the Misicuni River about northwest of the city of
Cochabamba Cochabamba (; ) is a city and municipality in central Bolivia in a valley in the Andes mountain range. It is the capital (political), capital of the Cochabamba Department and the list of cities in Bolivia, fourth largest city in Bolivia, with ...
,
Bolivia Bolivia, officially the Plurinational State of Bolivia, is a landlocked country located in central South America. The country features diverse geography, including vast Amazonian plains, tropical lowlands, mountains, the Gran Chaco Province, w ...
. The dam will divert water from the Misicuni River to the Cochabamba Valley for several purposes to include providing water for
irrigation Irrigation (also referred to as watering of plants) is the practice of applying controlled amounts of water to land to help grow crops, landscape plants, and lawns. Irrigation has been a key aspect of agriculture for over 5,000 years and has bee ...
and
municipal water Water supply is the provision of water by public utilities, commercial organisations, community endeavors or by individuals, usually via a system of pumps and pipes. Public water supply systems are crucial to properly functioning societies. Thes ...
uses. In addition, the dam has an associated 120 MW
hydroelectric Hydroelectricity, or hydroelectric power, is Electricity generation, electricity generated from hydropower (water power). Hydropower supplies 15% of the world's electricity, almost 4,210 TWh in 2023, which is more than all other Renewable energ ...
power station, powered by 3 turbines 40 MW each. Construction on the dam began in June 2009 but was halted in November 2013 due to contract disputes. The company finished the construction and is started the operations in September 2017.


Characteristics and costs

The project has three components: * Phase I includes an already completed 20 km tunnel with the capacity to provide 2 cubic meters per second of drinking water and 1 cubic meter per second for irrigation to Cochabamba and the surrounding areas. Its cost was US$84 million. * Phase II includes a 120-meter-high
concrete-face rock-fill dam A dam is a barrier that stops or restricts the flow of surface water or underground streams. Reservoirs created by dams not only suppress floods but also provide water for activities such as irrigation, drinking water, human consumption, Indust ...
with a 460-hectare reservoir with a storage capacity of 154 million cubic meters, as well as pipelines, pumping stations, a water treatment plant and an irrigation network to irrigate 4,000 hectares (under construction as of 2013). Its cost was also estimated at US$84 million, * Phase III includes a hydropower plant with an installed capacity of 120 MW at an estimated cost of US$200 million (under construction since April 2010). Water will be diverted from the reservoir through a long
penstock A penstock is a sluice or gate or intake structure that controls water flow, or an enclosed pipe that delivers water to hydro turbines and sewerage systems. The term is of Scots origin, and was inherited from the earlier technology of mill pond ...
to the plant. The dam will be the highest and largest dam in Bolivia. Misicuni project director Ramiro Saniz said in 2009 that the water from the Misicuni river is not sufficient to fill the reservoir and that other sources are needed.


Background and construction progress

The public company in charge of developing the project is Proyecto Misicuni, an entity created by law in 1987. The contractor for the US$90 million dam component is the ''Consorcio Hidroelectrico Misicuni'' (CHM). The Misicuni consortium, led with 51 percent ownership by Grandi Lavori Fincosit S.p.A. of Italy, was the sole bidder for the project. Bidding was limited to Italian companies and CHM was the only company to submit a bid. The consortium also includes Bolivian, Colombian and Venezuelan firms. The dam component was originally expected to be completed in 2014. However, in November 2013 the contract was canceled amid delays because CHM "failed to pay for pension funds, health insurances and other labour benefits and to contract key technical personnel."


Benefits

The tunnel provides 4.5-7.5 million cubic meters of water per year to Cochabamba since 2005, depending on whether the flow of the river is low or high and supplying about 10 percent of the city's drinking water. Once the dam will be completed, the amount of drinking water available will increase tenfold to 63 million cubic meters per year.


Environmental and social impact

1365 people live in the reservoir area that will be flooded and will be relocated. The
Tunari National Park Tunari National Park is a national park located in the Cochabamba Department, Bolivia Bolivia, officially the Plurinational State of Bolivia, is a landlocked country located in central South America. The country features diverse geography ...
will also be affected.


Financing

The dam is partially financed by the Italian government through a 25 million Euro loan and the
Development Bank of Latin America and the Caribbean Development or developing may refer to: Arts *Development (music), the process by which thematic material is reshaped * Photographic development *Filmmaking, development phase, including finance and budgeting *Development hell, when a projec ...
(CAF). Total funding from Italy for Phased II and III is USD 93 million. Bolivia will have to pay back the loan over in 20 years with a 0.10% interest rate. The construction of the penstock, hydropower plant and power transmission line is funded by a US$101 million loan from the
Inter-American Development Bank The Inter-American Development Bank (IDB or IADB) is an international development finance institution headquartered in Washington, D.C., United States of America. It serves as one of the leading sources of development financing for the countri ...
approved in 2009. These works were expected to be completed by 2015, but were only 30 percent completed as of April 2013.


Climate


References

{{GeoGroupTemplate Dams in Bolivia Buildings and structures in Cochabamba Department Concrete-face rock-fill dams Hydroelectric power stations in Bolivia Interbasin transfer