MeyGen (full name MeyGen tidal energy project) is a
tidal stream energy
A tidal stream generator, often referred to as a tidal energy converter (TEC), is a machine that extracts energy from moving masses of water, in particular tides, although the term is often used in reference to machines designed to extract energy ...
plant in the north of Scotland. The project is located in the
Pentland Firth
The Pentland Firth (, meaning the Orcadian Strait) is a strait which separates the Orkney Islands from Caithness in the north of Scotland. Despite the name, it is not a firth.
Etymology
The name is presumed to be a corruption of the Old Nors ...
, specifically the Inner Sound between the
Island of Stroma
Stroma is an uninhabited island in the Pentland Firth, between Orkney and the mainland of Scotland. It forms part of the Civil parishes in Scotland, civil parish of Canisbay in Caithness, in the council area of Highland (council area), Highla ...
and the Scottish mainland.
It is currently being constructed in a phased manner.
The first phase of the project uses four 1.5MW turbines with rotors which were installed submerged on the
seabed
The seabed (also known as the seafloor, sea floor, ocean floor, and ocean bottom) is the bottom of the ocean. All floors of the ocean are known as seabeds.
The structure of the seabed of the global ocean is governed by plate tectonics. Most of ...
in winter 2016/17.
Meygen has been claimed to be the "world's largest tidal stream power project". There are plans for up to 400MW to be installed at the site.
The project is owned and run by
SAE Renewables (formerly called SIMEC Atlantis Energy, and prior to 2017 Atlantis Resources), although previously it was owned and run by Tidal Power Scotland Limited and
Scottish Enterprise
Scottish Enterprise () is a non-departmental public body of the Scottish Government which encourages economic development, Business, enterprise, innovation, international and investment agency, investment in business. The body covers the eastern ...
.
The high speed of currents in the area, reaching up to , made the chosen site in the
Pentland Firth
The Pentland Firth (, meaning the Orcadian Strait) is a strait which separates the Orkney Islands from Caithness in the north of Scotland. Despite the name, it is not a firth.
Etymology
The name is presumed to be a corruption of the Old Nors ...
well suited to this type of energy generation.
History
In October 2010, the newly named "MeyGen" tidal project from the nearby
Castle of Mey and "Gen" for generation was created by a consortium of
Atlantis Resources Limited and
Morgan Stanley
Morgan Stanley is an American multinational investment bank and financial services company headquartered at 1585 Broadway in Midtown Manhattan, New York City. With offices in 42 countries and more than 80,000 employees, the firm's clients in ...
and received operational lease from the
Crown Estate
The Crown Estate is a collection of lands and holdings in the United Kingdom belonging to the British monarch as a corporation sole, making it "the sovereign's public estate", which is neither government property nor part of the monarch's priva ...
to a 400MW project for 25years. In 2011 Norwegian partners
Statkraft
Statkraft AS is a hydropower
Hydropower (from Ancient Greek -, "water"), also known as water power or water energy, is the use of falling or fast-running water to Electricity generation, produce electricity or to power machines. This is ac ...
pulled out of the project.
A consent was granted in 2013, under Section 36 of the
Electricity Act, to construct up to 61 two- or three-bladed turbines with a total installed capacity of 86 MW.
This was subject to construction in a phased manner so that potential environmental impacts could be understood. Each turbine was limited to 16–20 m in rotor diameter, rated at 1.0–2.4 MW, and connected to the grid by 6.6 kV cables.
Marine Scotland
The Scottish Government, Scottish Government's Marine Directorate () is a Directorates of the Scottish Government, directorate of the Scottish Government responsible for managing Scottish seas, Scotland's seas and freshwater fish, freshwater f ...
granted the project a license in January 2014. This initially only lasted until the end of 2020, but was extended in July 2016 to cover the period until 1 January 2041 or 25 years after completion of phase 1a.
Construction work on the project started in January 2015, building an access road towards the sea where the onshore power conversion building would be located.
In November 2016, the first turbine (TTG1) was installed, and in December it was announced that it had begun full power operations. TTG1 was supplied by
Andritz Hydro Hammerfest, and was joined by three further AR1500 turbines developed by Atlantis Resources with design support from
Lockheed Martin
The Lockheed Martin Corporation is an American Arms industry, defense and aerospace manufacturer with worldwide interests. It was formed by the merger of Lockheed Corporation with Martin Marietta on March 15, 1995. It is headquartered in North ...
. All four turbines were installed by February 2017, with the marine works undertaken by James Fisher Marine Services (previously Mojo Maritime). Phase 1 (formerly called Phase 1a) began operations in April 2018.
Some elements of the project were constructed outside the licensed area; however, after statutory consultation, Marine Scotland varied the license in September 2017 to extend the consented site area. It was considered there were no additional impacts and that asking for full removal may have had adverse impacts.
Phase 1b was initially planned to add a further 4 MW comprising two AR2000 turbines, with another 73.5 MW in Phase 1c.
Phase 1b was then revised to installing four turbines, bringing the total to eight. This required the Section 36 consent to be varied, to allow the additional two turbines above the six permitted in Phase 1. However, this phase did not proceed.
In July 2022, MeyGen plc was awarded a contract to supply 28 MW of electricity to the
GB grid in the
Contracts for difference (CfD) Allocation Round 4 (AR4), which will be used to support the construction of Phase 2 which is now due to be commissioned in 2027.
Four further contracts totalling 21.94 MW were awarded in the CfD AR5 auction in September 2023. An application was then submitted to vary the license conditions, to permit a smaller number of larger turbines to be used. These would be up to 24 m in diameter. The application would also remove the limit on the rated power per turbine, and increase the maximum voltage of the underwater cables to 33 kV.
, the plan is to install the next 28 MW of turbines as Phase 2 to be commissioned by 2027, and a further 22 MW as Phase 3 by 2028.
Phase 2 is planned to consist of a further 10 turbines.
In September 2024, the MeyGen project was awarded a further 9 MW in the CfD AR6 auction, to be delivered in 2028/29.
The site has the potential for a further 312 MW to be deployed beyond that, subject to expanding the consent.
This would amount to 398 MW in total.
By 2018 the four turbines had produced 8 GWh. In 2019, they produced 13.8 GWh. Total cumulative production was 51 GWh by March 2023.
The project received £1.5million Scottish Government grant from the
Saltire Tidal Energy Challenge Fund in 2020, to develop a sub-sea hub to connect multiple turbines.
[
]
Project description
Phase 1 of the project comprises four 1.5 MW turbines, three
Andritz Hydro Hammerfest AH1000 MK1 and one
Atlantis Resources AR1500 developed in conjunction with
Lockheed Martin
The Lockheed Martin Corporation is an American Arms industry, defense and aerospace manufacturer with worldwide interests. It was formed by the merger of Lockheed Corporation with Martin Marietta on March 15, 1995. It is headquartered in North ...
.
These are all three-bladed horizontal-axis turbines with an 18 m rotor diameter, that reach the 1.5 MW rated power at a current speed of 3 m/s. They are mounted on three-legged gravity foundations that sit on the seabed, each weighing around 350 tonnes with six 200-tonne ballast blocks.
The turbines in phase 1 are connected to the onshore power conversion centre at Ness of Quoys by an individual cable per turbine. These are laid on the seabed, with landfall by 550-metre-long
horizontal directionally drilled conduits, installed in July 2015. The cables were installed by James Fisher Marine Services by November 2015, with a total length of 11 km. This used the
DP vessel ''Siem Daya 1'', and was completed over a 2½-day
neap tide window.
The onshore power conversion equipment was supplied by
ABB.
References
{{stack, {{Portal, Scotland, Water, Renewable energy
Tidal power stations in Scotland