Design
The plant was composed of two units capable of generating 790 MWe each. During normal operation, output varied between 350 and 750 MWe; theHistory
Commissioning
The plant's two identical units went into initial operation in 1971.Early failures
The plant's turbine-generators suffered two early failures before 1975. Both of these failures resulted in failures of the turbine-generators, and both failures occurred during unseasonably cold weather. The cold weather proved to be the essential clue. One of the joint owners (LADWP) was assigned to determine the cause of these failures, through use of computer simulations. The power station and its connected 500 kV transmission systems (one to California, the other to Nevada) were subjected to extensive simulations, which ultimately led to identification of the root cause of the failures. When initially installed, the then-new concept of "series compensation" (sets of capacitors connected in series at the sending- and receiving-ends of the transmission lines) were installed, with the expectation that this "series compensation" would reduce or even eliminate the losses inherent with long distance power transmission lines. What was not then known, but was later identified during the simulations, which were performed in the System Development Division of LADWP, was the series resistance of the ACSR transmission lines, when under near freezing conditions, combined with the "series compensation", which was designed to counteract the series impedance of the lines, could, under certain conditions of generation and load, and low ambient temperatures, place an effective negative impedance on the generators, thereby causing a mechanical response by the turbine-generators that resulted in their destruction. This behavior had not been anticipated, and as it had not been anticipated, it could hardly have been simulated prior to the installation and commissioning of the power station. In general, such simulations focused on steady-state system behavior, not subsystem transient behavior. These two failures caused a renewed interest in "dynamic" simulation. Only "static" (that is, steady-state) simulation had been done previously. General Electric, the manufacturer of the turbine-generators, refused to repair or replace subsequent damage—after all it had already replaced two failed turbine-generators due to reasons which were then unknown, and were subsequently proved not to be its fault—so new operational procedures were implemented to prevent subsequent failures. These procedures were successful, and there were no more turbine-generator failures. But, these new procedures would not address what later happened, due to other causes, including improper operation of the steam generator's "reheat" system, which is a usual, and necessary part of a "compound" turbine-generator system (a high-pressure 3600 rpm turbine section compounded with a lower-pressure 1800 rpm turbine section, both of which were supplied by the same steam generator, but using separate reheat "loops").1985 pipe failure disaster
At 3:25 pm on June 9, 1985, a hot reheat line, carrying steam at , burst open. The reheat line circulates exhaust steam from the high pressure turbine back through the boiler stack, where it is reheated before entering the low pressure turbine. A steam cloud blew down a door leading to the control room of the station, fatally scalding six workers: Michael Bowman, John Dolan, Ernest Hernandez, Terry Leroy, Danny Norman, and Howard Turner. Ten others were injured. A preliminary report cited a faulty weld as the immediate cause. Approximately 35 employees were on-site at the time; of those, 20 were in the control room. The station was out of service for six months while all the steam piping was replaced. A report on the accident was completed in May 1991, but was not released until Christmas Day because of Edison's objections that it would compromise civil suits. Although several factors contributed to the pipe's failure, the report said Edison's actions—or lack of actions—were "primary and critical factors in causing the accident": * Edison knowingly operated the system at temperatures above design specification for long periods of time, and operators were unable to control the temperatures within the system as a result of a "design flaw." * Even so, the pipe, part of a steam reheat system, was not routinely maintained or inspected, though the pipe shifted and distorted because of exposure to abnormal stresses, the report said. * Edison's management made high production a priority over safety. In 1979, Edison disciplined a supervisor for ordering an unauthorized inspection of unrelated pipe welds. "The fear SCE management has instilled in its employees is counterproductive to safety and increases the chances that additional incidents as serious as this one may occur in the future," the report said. The report found no evidence that the accident was caused by a specific action on the day of the pipe failure. The report recommended sweeping changes to Edison's policies, including annual reports to the PUC on the utility's safety training, inspection and maintenance programs. In addition, the report argues that, because the accident was avoidable, the costs should be borne by Edison's shareholders, not its rate-paying customers.Shutdown
The plant was shut down on December 31, 2005, with the possibility it may not reopen. With the shutdown of the plant, the mine supplying the coal was also closed as well. The land where the mine was located is owned by theDismantling
On June 10, 2009, Southern California Edison announced that the Mohave Generating Station would be decommissioned and all generating equipment would be removed from the site. Later, SCE announced that all administrative buildings on site would also be razed. The only structure remaining on the property will be the 500 kV switchyard, which will continue to serve as a switching location for the regional bulk power system as well as provide electricity to a nearby Nevada Power substation supplying the Laughlin area. Dismantling got underway in October 2009 and is expected to take 2 years and cost $30 million. About 300 staff lost their jobs when the plant was closed. On March 11, 2011, the exhaust stack, a longtime landmark of the Laughlin/Bullhead City area, was felled by explosives. In October 2016, the entire site was listed for sale.Owners
* Southern California Edison (56%) *References
{{Energy resource facilities in Nevada 1971 establishments in Nevada 2005 disestablishments in Nevada Coal-fired power stations in Nevada Buildings and structures in Laughlin, Nevada Former coal-fired power stations in the United States Southern California Edison Energy infrastructure completed in 1971 Former power stations in Nevada