Jakarta LRT
   HOME

TheInfoList



OR:

The Jakarta Light Rapid Transit or Jakarta LRT (, lit. "Jakarta Integrated Rail Line") is one of the
light rapid transit A medium-capacity system (MCS), also known as light rapid transit or light metro, is a rail transport system with a capacity greater than light rail, but less than typical heavy-rail rapid transit. MCS trains are usually 1 to 4 cars. Most medi ...
systems in
Jakarta Jakarta (; , Betawi language, Betawi: ''Jakartè''), officially the Special Capital Region of Jakarta (; ''DKI Jakarta'') and formerly known as Batavia, Dutch East Indies, Batavia until 1949, is the capital and largest city of Indonesia and ...
, the capital city of
Indonesia Indonesia, officially the Republic of Indonesia, is a country in Southeast Asia and Oceania, between the Indian Ocean, Indian and Pacific Ocean, Pacific oceans. Comprising over List of islands of Indonesia, 17,000 islands, including Sumatra, ...
. It is conceived and built by the Jakarta provincial government. The first phase of the LRT, from to , began commercial operations on 1 December 2019. Jakarta LRT is operated by PT LRT Jakarta, a subsidiary of municipally-owned property and infrastructure company PT Jakarta Propertindo (Jakpro).


History


Background

The proposed LRT system in Jakarta was initially conceived as an alternative to the suspended
Jakarta Monorail The Jakarta Monorail ( JET Monorail) was a cancelled monorail network project in Jakarta, Indonesia. If completed, it would have comprised two lines, totalling up to . The project had a tumultuous history. First awarded in 2003, the contract ch ...
construction project. The suspension of the
monorail A monorail is a Rail transport, railway in which the track consists of a single rail or beam. Colloquially, the term "monorail" is often used to describe any form of elevated rail or people mover. More accurately, the term refers to the style ...
project was due to the objection of the
Governor of Jakarta } The Jakarta Special Region is administratively equal to a Provinces of Indonesia, province with special status as the largest city of Indonesia. Instead of a mayor, the executive head of Jakarta is a governor. The Governor of Jakarta is an elect ...
, Basuki Tjahaja Purnama, to the construction of the monorail depot above the Setiabudi Reservoir. This decision was made to avoid a recurrence of the 2013 Jakarta flood incident that occurred due to the collapse of the Latuharhari Embankment. The monorail project was ultimately cancelled as the investors failed to meet the advanced requirements set by the Jakarta Provincial Government. Consequently, the LRT project became the priority, with Governor Basuki Tjahaja Purnama expressing his hope for greater consistency and fewer setbacks compared to the discontinued monorail project. The plan for the construction of the Jakarta LRT refers to Presidential Regulation Number 99 of 2015 concerning the Acceleration of the Implementation of Public Transportation on the Special Capital Region of Jakarta Province. As part of the preparation for the
2018 Asian Games The 2018 Asian Games ( or ''Asian Games 2018''), officially known as the 18th Asian Games (), and also known as Jakarta-Palembang 2018 or Indonesia 2018, were a Asia, continental multi-sport event that was held from 18 August to 2 September 201 ...
, the Jakarta LRT was designated as a complementary public transportation system, and to facilitate its construction, the Governor of Jakarta directly appointed PT Jakarta Propertindo and PT Pembangunan Jaya for the project.


Phase 1

The groundbreaking of the Jakarta LRT was previously planned to be held in conjunction with the Greater Jakarta LRT groundbreaking in September 2015. The Jakarta LRT groundbreaking was held on 22 June 2016, coinciding with the 489th Anniversary of the City of Jakarta. In December 2016, PT Wijaya Karya was appointed as the contractor for the LRT construction project worth Rp5.29 trillion (around US$347.6 million). The construction itself only started in early 2017 after the land preparation process had been completed. The Jakarta LRT project seeks to address the issue of heavy traffic congestion on the city's roads. The rolling stock comes from
Hyundai Rotem Hyundai Rotem Company, often referred to as Hyundai Rotem (), is a South Korean manufacturer of railway rolling stock, railway signalling, defense products and plant equipment. It is a member of Hyundai Motor Group and has presence in more than ...
from South Korea which was first arrived from the Tanjung Priok Port on April 13, 2018. Each trainset consists of two cars and will be able to carry 270 to 278 passengers. There will be a total of 16 cars.
Platform screen doors Platform screen doors (PSDs), also known as platform edge doors (PEDs), are used at some train, rapid transit and people mover stations to separate the platform from train tracks, as well as on some bus rapid transit, tram and light rail ...
by ST Engineering Electronics will be installed at all stations. To build the site, BCA had disbursed 2.78 trillion rupiahs of their syndicated loans. The completion target of the Jakarta LRT construction before the 2018 Asian Games was not met, resulting in the limited operation of the LRT during the competition as a trial run. The limited trial run was carried out starting August 15, 2018. A full public trial run began on 11 June 2019 between Boulevard Utara and Velodrome stations, with free admission to registered ticket holders. Since commercial operation began in December 2019, the "flagging" system has seen falling ridership, with an average of 4,364 passengers per day.


Phase 1B

The groundbreaking for phase 1B was held on 30 October 2023. PT Waskita Karya was appointed as the constructor for phase 1B. The project would serve as an extension to the already operational Phase 1 line from to . The plan is to build 6.4 km of new tracks and five new stations; ''Pemuda Rawamangun'', ''Pramuka BPKP'', ''Pasar Pramuka'', ''Matraman'', and ''Manggarai''. Phase 1B cost an estimated Rp5.5 trillion, all were to be funded via
Jakarta Jakarta (; , Betawi language, Betawi: ''Jakartè''), officially the Special Capital Region of Jakarta (; ''DKI Jakarta'') and formerly known as Batavia, Dutch East Indies, Batavia until 1949, is the capital and largest city of Indonesia and ...
's own provincial budget. The Acting Governor of
DKI Jakarta Jakarta (; , Betawi language, Betawi: ''Jakartè''), officially the Special Capital Region of Jakarta (; ''DKI Jakarta'') and formerly known as Batavia, Dutch East Indies, Batavia until 1949, is the capital and largest city of Indonesia and ...
, Heru Budi Hartono, said that Phase 1B will run from 2024 to 2026, with construction from Rawamangun to Pramuka stations finishing in September 2024 and the rest following in 2026.


System network

The Jakarta LRT is expected to stretch across over , including for the South line (from Pengansaan Dua to Pesing), for the North line (from Pesing to JIS), and for the South East line (from Velodrome to Halim).


Southern Line


Operational

* Phase 1 - Pegangsaan Dua - Velodrome, along 5.8 km


Under construction

* Phase 1B - Velodrome - Manggarai, along 6.4 km Construction of Route 1 started on 22 June 2016. The first six kilometers of the route connecting the Kelapa Gading Depot to Velodrome Station was 29.61% complete by 26 June 2017. It was expected to be operational before the
2018 Asian Games The 2018 Asian Games ( or ''Asian Games 2018''), officially known as the 18th Asian Games (), and also known as Jakarta-Palembang 2018 or Indonesia 2018, were a Asia, continental multi-sport event that was held from 18 August to 2 September 201 ...
. However, this did not happen as construction is not yet finished and the Indonesia Asian Games Organizing Committee (INASGOC) considered that buses would be more effective in transporting the athletes. The test run for the LRT was initially scheduled for 10 August, however was delayed to 15 August 2018. Phase 1 was planned to begin operation in February, 2019. After several delays, the line opened for free public trial run from July to late November 2019. Commercial operations began on 1 December 2019.


Northern Line (Planned)


Future development


Pembangunan Jaya LRT (LRT KPDBU)

Apart from the North and South Line plans, the Jakarta Provincial Government is also planning the construction of the Pulogebang-Joglo LRT route for 32.15 km (19.98 mi). This line procurement is carried out under the Regional Government and Business Entity Cooperation scheme between the Jakarta Provincial Government and PT Pembangunan Jaya.


Ticket and fare

LRT Jakarta begun collecting fares from 1 December 2019. On the entire system, passengers pay a flat fare of Rp 5.000. LRT Jakarta accept both cash and cashless payment. Cash payment are accepted to pay single trip tickets. Passengers must deposit of Rp 15.000 in addition to journey fare, which could be refunded within 7 days after last tapping out at exit gate. Cashless payment methods accepted are prepaid cards and electronic wallet. Prepaid cards accepted include e-money (
Bank Mandiri PT Bank Mandiri (Persero) Tbk or Bank Mandiri, headquartered in Jakarta, is the largest bank in Indonesia in terms of assets, loans and deposits. Total assets as of 2022, were 1.992 Trillion rupiah (around US$133 Billion). As of 2022, Bank Man ...
), Flazz ( Bank BCA), TapCash ( Bank BNI), Brizzi ( Bank BRI) Jakcard ( Bank DKI), and Multi Trip Card (KAI Commuter). LRT Jakarta also accepts Jak Lingko-branded payment cards provided by Bank DKI, Bank Mandiri, Bank BRI, and Bank BNI. Fares are deducted from these prepaid cards upon exiting. From 3 August 2020, LRT Jakarta accepts payment from electronic wallet. To date it only accepts wallets provided by LinkAja. Passengers only need to scan QR code at the entry gate to pay directly from their LinkAja e-wallet.


See also

* Greater Jakarta Integrated Mass Transit System * Transport in Indonesia * Transport in Jakarta *
Rail transport in Indonesia The majority of Indonesia's railways are on Java, used for both passenger and freight transport. There are three noncontinuous railway networks in Sumatra (Aceh and North Sumatra; West Sumatra; South Sumatra and Lampung) and Trans-Sulawesi Rail ...
* Jabodebek LRT * Jakarta MRT *
KRL Commuterline KRL Commuterline, commonly known as Greater Jakarta Commuter rail, Jakarta Commuter rail, and KRL Commuter Line Jabodetabek is a commuter rail system for Jabodetabek, Greater Jakarta in Indonesia. It was previously known as KRL Jabodetabek. It ...
*
TransJakarta Transjakarta (stylised in all-lowercase, often erroneously called Busway, sometimes shortened as TJ and branded as TiJe) or Jakarta BRT is a bus rapid transit (BRT) system in Jakarta, Indonesia. The first BRT system in Southeast Asia, it commenc ...


References


External links


Jakarta LRT Progress video per May 2018
{{Rapid transit in Asia Rapid transit in Indonesia Rail transport in Jakarta Rail infrastructure in Indonesia Passenger rail transport in Indonesia Railway companies of Indonesia Regionally-owned companies of Indonesia Railway lines opened in 2019 2019 establishments in Indonesia Standard-gauge railways in Indonesia 750 V DC railway electrification