project management Project management is the process of supervising the work of a Project team, team to achieve all project goals within the given constraints. This information is usually described in project initiation documentation, project documentation, crea ...
, float or slack is the amount of time that a task in a
project network A project network diagram, also known an activity network diagram (AND) is a information graphics, graph that displays the order in which a project’s activities are to be completed. Derived from the work breakdown structure, the Work breakdown ...
can be delayed without causing a delay to: * subsequent tasks ("''free float''") * project completion date ("''total float''"). ''Total float'' is associated with the path. If a project network chart/diagram has 4 non-critical paths, then that
project A project is a type of assignment, typically involving research or design, that is carefully planned to achieve a specific objective. An alternative view sees a project managerially as a sequence of events: a "set of interrelated tasks to be ...
would have 4 ''total float'' values. The ''total float'' of a path is the combined ''free float'' values of all activities in a path. The ''total float'' represents the schedule flexibility and can also be measured by subtracting early start dates from late start dates of path completion. Float is core to
critical path method The critical path method (CPM), or critical path analysis (CPA), is an algorithm for schedule (project management), scheduling a set of project activities. A critical path is determined by identifying the longest stretch of dependent activiti ...
, with the total floats of noncritical activities key to computing the
critical path drag Critical path drag is a project management metric developed by Stephen Devaux as part of the Total Project Control (TPC) approach to schedule analysis and compression in the critical path method of scheduling. Critical path drag is the amount of ...
of an activity, i.e., the amount of time it is adding to the project's duration.*


Example

Consider the process of replacing a broken pane of glass in the window of your home. There are various component activities involved in the project as a whole; obtaining the glass and putty, installing the new glass, choosing the paint, obtaining a tin once it has set, wiping the new glass free of finger smears etc. Some of these activities can run concurrently e.g. obtaining the glass, obtaining the putty, choosing the paint etc., while others are consecutive e.g. the paint cannot be bought until it has been chosen, the new window cannot be painted until the window is installed and the new putty has set. Delaying the acquisition of the glass is likely to delay the entire project - this activity will be on the critical path and have no float, of any sort, attached to it and hence it is a 'critical activity'. A relatively short delay in the purchase of the paint may not automatically hold up the entire project as there is still some waiting time for the new putty to dry before it can be painted anyway - there will be some 'free float' attached to the activity of purchasing the paint and hence it is not a critical activity. However, a delay in choosing the paint, in turn, inevitably delays buying the paint which, although it may not subsequently mean any delay to the entire project, does mean that choosing the paint has no 'free float' attached to it - despite having no free float of its own, the choosing of the paint is involved with a path through the network which does have 'total float'.


See also

*
Critical path method The critical path method (CPM), or critical path analysis (CPA), is an algorithm for schedule (project management), scheduling a set of project activities. A critical path is determined by identifying the longest stretch of dependent activiti ...
*
Glossary of project management A glossary of terms relating to Project Management, project management and consulting. A * Agile software development is a set of fundamental principles about how software should be developed based on an agile way of working in contrast to p ...
*
List of project management topics The following outline is provided as an overview of and topical guide to project management: Project management – discipline of planning, organizing, securing, managing, leading, and controlling resources to achieve specific goals. A proje ...


References


Further reading

* * * {{cite book , last = Sanghera, first = Paul , year = 2019, title=PMP in Depth , edition = Third , publisher = Apress , isbn = 978-1-4842-3910-0 , doi=10.1007/978-1-4842-3910-0 , language=en-US Schedule (project management)