The Ely Energy Center was a proposed
coal-fired power plant A coal-fired power station or coal power plant is a thermal power station which burns coal to generate electricity. Worldwide, there are about 8,500 coal-fired power stations totaling over 2,000 gigawatts capacity. They generate about a th ...
that was to be built in
Steptoe Valley The Steptoe Valley is a long basin located in White Pine County, in northeastern Nevada in the western United States. From the historic community of Currie, the valley runs south for approximately 100 miles (160 km). To the west are the h ...
, north of the city of
Ely Ely or ELY may refer to: Places Ireland * Éile, a medieval kingdom commonly anglicised Ely * Ely Place, Dublin, a street United Kingdom * Ely, Cambridgeshire, a cathedral city in Cambridgeshire, England ** Ely Cathedral ** Ely Rural District, a ...
and located in
White Pine County, Nevada White Pine County is a largely rural, mountain county along the central eastern boundary of the U.S. state of Nevada. As of the 2010 census, the population was 10,030. Its county seat is Ely. The name "(Rocky Mountain) white pine" is an o ...
. The plant was proposed by Nevada Power Company and
Sierra Pacific Resources NV Energy is a public utility which generates, transmits and distributes electric service in northern and southern Nevada, including the Las Vegas Valley, and provides natural gas service in the Reno–Sparks metropolitan area of northern Nevad ...
in January 2006. Construction was to begin on a 750-megawatt power unit in 2007, with completion by 2011. A second 750-megawatt unit was to be built within a few years after the first one, with a total cost of $3.8 billion. The companies also planned to ultimately add two 500-megawatt coal
gasification Gasification is a process that converts biomass- or fossil fuel-based carbonaceous materials into gases, including as the largest fractions: nitrogen (N2), carbon monoxide (CO), hydrogen (H2), and carbon dioxide (). This is achieved by react ...
plants to the project as soon as such technology became commercially viable. The total cost, upon full completion, would amount to $5 billion. The Ely Energy Center would have been the largest power plant in Nevada, and the state's largest energy project since the construction of Hoover Dam. The project faced opposition from environmental groups and senator
Harry Reid Harry Mason Reid Jr. (; December 2, 1939 – December 28, 2021) was an American lawyer and politician who served as a United States senator from Nevada from 1987 to 2017. He led the Senate Democratic Caucus from 2005 to 2017 and was the Sena ...
, but was supported by Nevada governor Jim Gibbons, the
Ely Shoshone Tribe The Ely Shoshone Indian Reservation is an Indian reservation for the Ely Shoshone Tribe of Nevada, Shoshone people, in and near the south side of the city of Ely in south-central White Pine County, Nevada. In 2005 it had a population of around 500, ...
, and some Ely city officials. The project was postponed for three and a half years in November 2007, due to delays from the Bureau of Land Management (BLM) in issuing an environmental impact statement (EIS). In February 2009, the project was delayed for approximately 10 years, until the technology to capture and store carbon dioxide pollution would become commercially feasible. The decision was made due to the possibility of the
United States Congress The United States Congress is the legislature of the federal government of the United States. It is bicameral, composed of a lower body, the House of Representatives, and an upper body, the Senate. It meets in the U.S. Capitol in Washi ...
enacting carbon emission tax laws, which would increase the project's cost and make it unfeasible. Rising construction costs were also a factor in delaying the project.


History


Announcement and overview

On January 10, 2006,
utility As a topic of economics, utility is used to model worth or value. Its usage has evolved significantly over time. The term was introduced initially as a measure of pleasure or happiness as part of the theory of utilitarianism by moral philosoph ...
company
Sierra Pacific Resources NV Energy is a public utility which generates, transmits and distributes electric service in northern and southern Nevada, including the Las Vegas Valley, and provides natural gas service in the Reno–Sparks metropolitan area of northern Nevad ...
– the parent company of Nevada Power Company – announced plans to construct the Ely Energy Center, a $5 billion coal plant, in
White Pine County White Pine County is a largely rural, mountain county along the central eastern boundary of the U.S. state of Nevada. As of the 2010 census, the population was 10,030. Its county seat is Ely. The name "(Rocky Mountain) white pine" is an old ...
's
Steptoe Valley The Steptoe Valley is a long basin located in White Pine County, in northeastern Nevada in the western United States. From the historic community of Currie, the valley runs south for approximately 100 miles (160 km). To the west are the h ...
, north of the city of
Ely Ely or ELY may refer to: Places Ireland * Éile, a medieval kingdom commonly anglicised Ely * Ely Place, Dublin, a street United Kingdom * Ely, Cambridgeshire, a cathedral city in Cambridgeshire, England ** Ely Cathedral ** Ely Rural District, a ...
. The project was to be built on land that was controlled by the Bureau of Land Management (BLM). The project was part of the company's plan to lower its reliance on
natural gas Natural gas (also called fossil gas or simply gas) is a naturally occurring mixture of gaseous hydrocarbons consisting primarily of methane in addition to various smaller amounts of other higher alkanes. Low levels of trace gases like carbon ...
. The Ely Energy Center would be the largest power plant in the state, and the largest energy project in the state since the construction of Hoover Dam. The first power unit, capable of producing 750 megawatts, was to be operational by 2011. A 250-mile
transmission line In electrical engineering, a transmission line is a specialized cable or other structure designed to conduct electromagnetic waves in a contained manner. The term applies when the conductors are long enough that the wave nature of the transmi ...
would accompany the energy center, to bring electricity from the plant to northern and
southern Nevada Southern Nevada (SNV) is a region and the southern portion of the U.S. state of Nevada which includes the Las Vegas Valley. It also includes the areas in and around Pahrump and Pioche. Tonopah and Hawthorne are sometimes also referred to as par ...
. A second 750-megawatt plant would be completed within a few years after the first one. Both units, to be built at a total cost of $3 billion, were to utilize water-conserving technology and "supercritical" technology capable of burning coal efficiently at high temperatures. The company would also use clean coal technology as a way of minimizing environmental effects, while hybrid cooling would be used to reduce the amount of water required to keep the plants cool. Additionally, the company had plans to ultimately build two 500-megawatt coal
gasification Gasification is a process that converts biomass- or fossil fuel-based carbonaceous materials into gases, including as the largest fractions: nitrogen (N2), carbon monoxide (CO), hydrogen (H2), and carbon dioxide (). This is achieved by react ...
plants at the Ely Energy Center, as soon as such technology became commercially viable. The gasification plants would cost $2 billion to construct. The four plants would be capable of producing up to 2,500 megawatts, enough to provide electricity to 1.7 million households. Sierra Pacific Resources had previously declined to be a long-term customer of LS Power's White Pine Energy Station (also proposed for the Steptoe Valley) and Sithe Global's
Toquop Energy Project Toquop Energy Project is a proposed energy facility located in Lincoln County near Mesquite, Nevada. In 2003, the Bureau of Land Management (BLM) issued a rights-of-way for a natural gas-fired plant. In 2004, Toquop Energy applied to amend the R ...
(proposed near
Mesquite, Nevada Mesquite is a city in Clark County, Nevada, United States adjacent to the Arizona state line and northeast of Las Vegas on Interstate 15. As of the 2020 census, the city had a population of 20,471. The city is located in the Virgin River valle ...
) as bond rating agencies perceive long-term power contracts to be a liability for utility companies, while company-owned plants are treated as assets. Sierra Pacific Resources planned to finance the project through stocks and bonds. Construction was expected to begin in 2007. The project would provide up to 2,000 construction jobs, and 300 permanent jobs upon completion. Sierra Pacific Resources stated that the project could make the company an additional $90 million in its first year. Officials of Utah's
Hill Air Force Base Hill Air Force Base is a major U.S. Air Force (USAF) base located in northern Utah, just south of the city of Ogden, and bordering the Cities of Layton, Clearfield, Riverdale, Roy, and Sunset with its largest border immediately adjacent ...
had concerns that the coal plant could interfere with training flights in the Ely area. The project was presented to the White Pine County Commission on March 8, 2006. In May 2006, LS Power stated that consumers of electrical power in Nevada would save $600 million over a three-year period if Nevada Power Company and Sierra Pacific Power would purchase power from the White Pine Energy Station rather than building their own coal plant.


Progress

In September 2006, environmental groups testified that the companies should delay the Ely Energy Center for a year to conduct further research, as the current version of the plant would produce large amounts of
carbon dioxide Carbon dioxide ( chemical formula ) is a chemical compound made up of molecules that each have one carbon atom covalently double bonded to two oxygen atoms. It is found in the gas state at room temperature. In the air, carbon dioxide is t ...
. In November 2006, the
Public Utilities Commission In the United States, it is a governing body of a utility. In Canada, it is a utility, not a regulatory body. Canada In Canada, a public utilities commission (PUC) is a public utility owned and operated by a municipal or local government under t ...
gave the companies permission to spend $300 million to begin developing the transmission line and the $3.7 billion Ely Energy Center. Nevada Power Company was to pay 80 percent of the cost for the 1,500-megawatt energy center, while Sierra Pacific Resources would pay the remainder. Later that month, the companies applied for an air permit with the Nevada Division of Environmental Protection. In March 2007, Sierra Pacific Resources agreed to help the city of Ely purchase the
Nevada Northern Railway The Nevada Northern Railway was a railroad in the U.S. state of Nevada, built primarily to reach a major copper producing area in White Pine County, Nevada. The railway, constructed in 1905–06, extended northward about from Ely to connections ...
by providing a $375,000 loan. The company intended to use the railroad to transport coal to the energy center from Montana and from Wyoming's
Powder River Basin The Powder River Basin is a geologic structural basin in southeast Montana and northeast Wyoming, about east to west and north to south, known for its extensive coal reserves. The former hunting grounds of the Oglala Lakota, the area is very ...
. The company planned to spend $40 million of a $3.8 billion budget to rebuild 100 miles of the railway so it could connect with an existing
Union Pacific The Union Pacific Railroad , legally Union Pacific Railroad Company and often called simply Union Pacific, is a freight-hauling railroad that operates 8,300 locomotives over routes in 23 U.S. states west of Chicago and New Orleans. Union Pac ...
rail line. LS Power, which also helped cover the cost to purchase the railway, also planned to use it for transporting coal to its White Pine Energy Station. By April 2007, analysts believed that only one coal plant would be built in White Pine County, with the Ely Energy Center being considered as more likely to proceed. In June 2007, a spokesman for the companies said they did not expect to receive opposition from the
National Park Service The National Park Service (NPS) is an List of federal agencies in the United States, agency of the Federal government of the United States, United States federal government within the United States Department of the Interior, U.S. Department of ...
, which had recently voiced opposition to the White Pine Energy Station for its possible environmental effects on the nearby
Great Basin National Park Great Basin National Park is an American national park located in White Pine County in east-central Nevada, near the Utah border, established in 1986. The park is most commonly entered by way of Nevada State Route 488, which is connected to U ...
. David Sims, project director of development for the Ely Energy Center, said the project would use superior air quality controls that would result in significantly lower sulfur dioxide emissions compared to the White Pine Energy Station.


Environmental opposition and delay

In July 2007,
Harry Reid Harry Mason Reid Jr. (; December 2, 1939 – December 28, 2021) was an American lawyer and politician who served as a United States senator from Nevada from 1987 to 2017. He led the Senate Democratic Caucus from 2005 to 2017 and was the Sena ...
said he would fight the development of the two coal projects. Ely city officials expressed disappointment with Reid's position. Nevada governor Jim Gibbons, a supporter of the two coal plants, reaffirmed his support for the projects after Reid's comment. At the end of the month, seven groups submitted a petition to the Nevada Environmental Commission requesting that permits for the two coal plants be delayed until the commission enacted new limits on the amount of pollution allowed by such plants. A hearing on the matter was set for September 7, 2007. On November 28, 2007, Nevada Power announced that the project would be delayed for three and a half years because of regulatory review, while Sierra Pacific Resources planned to build a new natural gas-fired power plant near Las Vegas to keep up with demand in southern Nevada. Sierra Pacific Resources attributed the delay to the BLM, which had yet to issue an environmental impact statement (EIS). The BLM had expected to issue the EIS by summer 2008, but no longer expected to meet the deadline as it was also busy reviewing other projects. The company no longer expected to complete the first 750-megawatt unit by 2011, and did not set a new deadline for its completion. Reid praised the decision to delay construction of the project. In January 2008, the National Park Service stated that plans to build the energy center near Ely were "unacceptable" as it would harm the quality of the air and water at Great Basin National Park, as well as disrupt scenic views. That month, the
Ely Shoshone Tribe The Ely Shoshone Indian Reservation is an Indian reservation for the Ely Shoshone Tribe of Nevada, Shoshone people, in and near the south side of the city of Ely in south-central White Pine County, Nevada. In 2005 it had a population of around 500, ...
announced support for both coal plants, considering them to be an economic necessity. In February 2008, the companies were expected to delay their application for the project for two years. In May 2008, the
National Parks Conservation Association The National Parks Conservation Association (NPCA) is the only independent, nonpartisan membership organization devoted exclusively to advocacy on behalf of the National Parks System. Its mission is "to protect and enhance America's National Park ...
stated that the two coal plants would cause Great Basin National Park to suffer from acid rain pollution over time, ultimately harming the park's plants, fish, and other wildlife. The association also stated that the coal plants would affect air quality at the nearby
Zion National Park Zion National Park is an American national park located in southwestern Utah near the town of Springdale. Located at the junction of the Colorado Plateau, Great Basin, and Mojave Desert regions, the park has a unique geography and a variety o ...
in Utah. In August 2008, analysts for an environmental group, as well as the Public Utilities Commission staff and the attorney general's Bureau of Consumer Protection, recommended that Nevada Power and Sierra Pacific Resources end development of the project, which had increased in cost from $3.8 billion to $5 billion. In September 2008, the attorney general and Nevadans for a Clean, Affordable, Reliable Energy, an environmental group, believed that Nevada Power should do a complete review of project and study other possible power alternatives. Nevada Power suggested waiting until 2010 to do a full study, as new laws regarding carbon dioxide pollution were expected to be enacted by then. In November 2008, Reid requested that Gibbons "join with me in putting Nevada quickly on a cleaner plat toward a renewable energy and efficiency driven economy and safer future." In December 2008, the BLM issued a draft EIS for the project, while
NV Energy NV Energy is a public utility which generates, transmits and distributes electric service in northern and southern Nevada, including the Las Vegas Valley, and provides natural gas service in the Reno–Sparks metropolitan area of northern Nevada ...
suspected that a final decision from the BLM was another year away. The project was also still awaiting a final air permit from the Nevada Division of Environmental Protection. The first power unit was expected to become operational by 2015, followed by the second unit a year later. On February 3, 2009, NV Energy
chief executive officer A chief executive officer (CEO), also known as a central executive officer (CEO), chief administrator officer (CAO) or just chief executive (CE), is one of a number of corporate executives charged with the management of an organization especial ...
Michael Yackira said the project "is going to be very difficult to build." On February 9, 2009, NV Energy announced that the project would be postponed for approximately 10 years, until the technology to capture and store carbon dioxide pollution would become commercially feasible. Yackira said the decision was due to rising construction costs and the possibility of the
United States Congress The United States Congress is the legislature of the federal government of the United States. It is bicameral, composed of a lower body, the House of Representatives, and an upper body, the Senate. It meets in the U.S. Capitol in Washi ...
enacting carbon emission tax laws, which would increase the project's cost and make it unfeasible. The company planned to continue building the One Nevada transmission line, which was expected to be operational by late 2012 but became operational in 2014. Reid said, "I applaud NV Energy's decision to speed up the development of an important transmission line and to postpone construction of its Ely Energy Center coal plant." A July 2009 report from the Government Accountability Office confirmed that air quality and visibility at Great Basin National Park would be affected if either of the coal plants were built.


References


External links


Draft Environmental Impact Statement (2009)
published by the Bureau of Land Management {{coord missing, Nevada Proposed coal-fired power stations in the United States White Pine County, Nevada