The Elizabeth River Tunnels Project, a series of transportation projects in the
South Hampton Roads South Hampton Roads is a region located in the extreme southeastern portion of Virginia's Tidewater region in the United States with a total population of 1,177,742 as of 2020. It is part of the Virginia Beach-Norfolk-Newport News, VA-NC MSA ( M ...
region of
Virginia Virginia, officially the Commonwealth of Virginia, is a U.S. state, state in the Southeastern United States, Southeastern and Mid-Atlantic (United States), Mid-Atlantic regions of the United States between the East Coast of the United States ...
, comprises the rehabilitation of the
Downtown ''Downtown'' is a term primarily used in American and Canadian English to refer to a city's sometimes commercial, cultural and often the historical, political, and geographic heart. It is often synonymous with its central business district ( ...
and existing Midtown Tunnels, the construction of a new parallel Midtown Tunnel, and the extension of the MLK Freeway/ U.S. 58 to
I-264 Interstate 264 is the designation for two Interstate Highways in the United States, both of which are related to Interstate 64: *Interstate 264 (Kentucky), a bypass of Louisville, Kentucky *Interstate 264 (Virginia) Interstate 264 (I-264) ...
. Intended to reduce congestion on area surface streets and arterial roads, the project was administered by
Elizabeth River Crossings Elizabeth River Crossings (ERC), officially known as Elizabeth River Crossings OpCo, LLC, is a limited liability company A limited liability company (LLC) is the United States-specific form of a private limited company. It is a busine ...
(ERC) and
Virginia Department of Transportation The Virginia Department of Transportation (VDOT) is the agency of the U.S. state, state government responsible for transportation in the state of Virginia in the United States. VDOT is headquartered at the Virginia Department of Highways Buildin ...
(VDOT) as part of a 58-year public-private partnership. ERC maintains and operates the project ongoing.


History

Transportation around South Hampton Roads is complicated by the various branches of the
Elizabeth River (Virginia) The Elizabeth River is a U.S. Geological Survey. National Hydrography Dataset high-resolution flowline dataThe National Map , accessed April 1, 2011 tidal estuary forming an arm of Hampton Roads harbor at the southern end of Chesapeake Bay in sout ...
, which are crossed by two major highways. The busiest spur route in the area,
I-264 Interstate 264 is the designation for two Interstate Highways in the United States, both of which are related to Interstate 64: *Interstate 264 (Kentucky), a bypass of Louisville, Kentucky *Interstate 264 (Virginia) Interstate 264 (I-264) ...
, crosses the river's Eastern Branch (via the Berkley Bridge) and its Southern Branch (via the
Downtown Tunnel The Downtown Tunnel on Interstate 264 (Virginia), Interstate 264 (I-264) and U.S. Route 460 Alternate (Chesapeake–Norfolk, Virginia), U.S. Route 460 Alternate (US 460 Alt.) crosses the Southern Branch Elizabeth River, Southern B ...
). Built in 1952, the westbound Downtown Tunnel is the oldest tunnel in Hampton Roads; much of it, including its ceiling tiles, has reached or exceeded its designed service life and requires repairs. The eastbound tube, built in 1987, also requires maintenance, as well as several updates to comply with NFPA 502 regulations. The primary alternate route to the Downtown Tunnel is the Midtown Tunnel upstream. Built in 1962 to carry U.S. 58, the Midtown allows direct access to
Portsmouth Portsmouth ( ) is a port city status in the United Kingdom, city and unitary authority in Hampshire, England. Most of Portsmouth is located on Portsea Island, off the south coast of England in the Solent, making Portsmouth the only city in En ...
without passing through Downtown. Built with one lane in both directions, it served nearly 8,400 vehicles per day in its first operating year and nearly 40,000 per day in 2013, making it the "most heavily traveled two-lane road east of the Mississippi", according to the VDOT and ERC. Traffic is projected to rise to nearly 50,000 vehicles per day by 2026. The Martin Luther King Jr. Freeway carries U.S. 58 after the Midtown Tunnel to its surface-street connection on London Boulevard in Portsmouth. As part of the long-term plan, regional leaders and VDOT looked to extend the freeway from its terminus at London Boulevard down to I-264, creating a highway-speed alternate that connected I-264 to the Midtown Tunnel and the new Western Freeway. Efforts to extend the MLK Freeway have been in the works with VDOT as far back as the early 1990s, when the agency completed its initial environmental assessment. The project received a new environmental assessment in 1999, when VDOT began pursuing the parallel Midtown Tunnel.


Financing studies and public funding attempts

In June 2004, the Hampton Roads Planning District Commission wanted to add the parallel Midtown Tunnel and the extension of the Martin Luther King Freeway (along with several other congestion-relieving projects) to the 2026 Regional Transportation Plan (RTP). The construction cost was estimated at $686 million. However, the Commission removed the project from the RTP after concluding that state funding would be insufficient, and because VDOT determined that "reliance on a regional gas tax asnot a reasonably foreseeable source of revenue" for the plan. In 2006, the Hampton Roads Metropolitan Planning Organization (MPO) (formerly a subcommittee of the HRPDC, now known as the Transportation Planning Organization) concluded that new tolls could help secure funding for transportation projects that were removed from the 2026 RTP, including the Midtown Tunnel and MLK Extension. This would include tolling the parallel Downtown Tunnel to create a congestion-management plan to prevent the diversion of potential Midtown Tunnel traffic to a competing free facility. Both tunnels were initially tolled (25 cents, both ways) to pay off their construction bonds; both were made free in the late 1980s after the opening of the second (eastbound) Downtown Tunnel. Options included adding a 58-cent toll to the Midtown Tunnel (and a 19-cent toll to the MLK Extension), which could raise $427 million for the project; or adding a $2.05 peak/$1.50 off-peak toll for the Midtown, and a $2.20 peak/$1.60 off-peak for the Downtown Tunnel, which could raise nearly $4.8 billion. Based on this study, the MPO added the projects to the regions 2030 RTP, now estimated to cost around $779 million— if the
Virginia General Assembly The Virginia General Assembly is the legislative body of the Commonwealth of Virginia, the oldest continuous law-making body in the Western Hemisphere, and the first elected legislative assembly in the New World. It was established on July 30, ...
approved the new tolls and several tax increases. After receiving the proposal, the General Assembly enacted House Bill 3202 introduced by State Delegate William J. Howell, which allowed the region to enact tolling on the project by creating the Hampton Roads Transportation Authority, as well as authorizing tax increases requested by the MPO to finance the other major projects in the region's plan, including the controversial civil remedial fees, a plan that would have allowed the HRTA to raise nearly $169 million in taxes in its first year. However, the authority's taxing authority was short-lived. On February 28, 2008, the
State Supreme Court In the United States, a state supreme court (known by other names in some states) is the highest court in the state judiciary of a U.S. state. On matters of state law, the judgment of a state supreme court is considered final and binding in ...
ruled in ''
Marshall Marshall may refer to: Places Australia *Marshall, Victoria, a suburb of Geelong, Victoria ** Marshall railway station Canada * Marshall, Saskatchewan * The Marshall, a mountain in British Columbia Liberia * Marshall, Liberia Marshall Is ...
v.
Northern Virginia Transportation Authority The Northern Virginia Transportation Authority (NVTA) is a regional governmental entity established to plan, prioritize and fund regional transportation programs. The NVTA covers Arlington, Fairfax, Loudoun and Prince William counties and the ci ...
'' that the taxation authority granted to these non-elected bodies violated the
Constitution of Virginia The Constitution of the Commonwealth of Virginia is the document that defines and limits the powers of the state government and the basic rights of the citizens of the Commonwealth of Virginia. Like all other state constitutions, it is supreme ...
:
The General Assembly also may not accomplish through Chapter 896 B 3202 indirectly, that which it is not empowered to do directly, namely, impose taxes on the citizenry in the absence of an affirmative, recorded vote of a majority of all members elected to each body of the General Assembly. Thus, by enacting Chapter 896 B 3202 the General Assembly has failed to adhere to the mandates of accountability and transparency that the Constitution requires when the General Assembly exercises the legislative taxing authority permitted by the Constitution. If payment of the regional taxes and fees is to be required by a general law, it is the prerogative and the function of the General Assembly, as provided by Article IV, Section 1 of the Constitution, to make that decision, in a manner which complies with the requirements of Article IV, Section 11 of the Constitution.
The opinion did not find the existence of the HRTA (or the NVTA for that matter) to be unconstitutional, nor did it strike the authority of the regional authorities to impose tolling on the roadways.


Public–private partnership

As early as 2004 while the political wrangling continued, VDOT had determined that in order to fund the project, it would need to be a public-private venture, sending out an informal
request for information A request for information (RFI) is a common business process whose purpose is to collect written information about the capabilities of various suppliers. Normally it follows a format that can be used for comparative purposes. An RFI is primarily ...
for private entities interested in pursuing such a project. Three companies expressed an interest in the project, including Skanska. Both Skanska and one of the other interested parties stated that tolling on the Downtown Tunnel and the Midtown Tunnel would bring about the best financial outcome for completing the project. Following that, VDOT began the process to solicit bids from private companies to partner with the state in executing the Elizabeth River Tunnels Project (which now included the rehabilitation of the Downtown Tunnel) through Virginia's Public Private Transportation Act. Transportation Secretary Pierce R. Homer said that "It desperately needs upgrading." and that "it's a very expensive project and we have no public‐sector resources to pay for it.", which was underscored in the solicitation request, which stated that "user tolls will ultimately pay for the work". Ultimately, although three companies expressed an interest, only one actually submitted a proposal, which was what is now Elizabeth River Crossings. After the lengthy review process required under the PPTA, then-Governor
Bob McDonnell Robert Francis McDonnell (born June 15, 1954) is an American politician, attorney, businessman, academic administrator, and former military officer who served as the 71st governor of Virginia from 2010 to 2014. He is a member of the Republica ...
and VDOT executed the Comprehensive Agreement with ERC on December 5, 2011. Under the agreement, VDOT retains ownership and oversight of the tunnels, while ERC finances, builds, operates and maintains the facilities for a 58-year concession period. Funding is expected from tolls, private equity, contributions from the Commonwealth and a low-interest
Federal Highway Administration The Federal Highway Administration (FHWA) is a division of the United States Department of Transportation that specializes in highway transportation. The agency's major activities are grouped into two programs, the Federal-aid Highway Program a ...
loan. ERC is responsible for paying back all debt on the project, as well as assumes the entire risk of a decrease in toll revenue if traffic counts do not meet projections. However, if traffic exceeds projections and increases revenue, VDOT will receive a portion of the excess revenue, after all other costs and debt service has been paid for the period. The deal reached financial close on April 13, 2012. The cost of the project, at financial close was $2.1 billion. ERC eventually received $300 million from VDOT, $663.75 mil from the Virginia Small Business Financing Authority and $422 million from the
U.S. Department of Transportation The United States Department of Transportation (USDOT or DOT) is one of the executive departments of the U.S. federal government. It is headed by the secretary of transportation, who reports directly to the president of the United States a ...
, all of which went to pay down the toll rate. The 58-year concession period will end on April 13, 2070.


Tolling

The agreement gave ERC the authority to impose tolling on the roadway in order to recoup the private parties the money they put into the project. Initially, ERC estimated the toll rate to be between $2–3 (for cars), however the Comprehensive Agreement scheduled the tolls to begin at rates of $1.59/non-peak hours and $1.84/peak for cars and $4.77/non-peak and $7.34/peak for heavy vehicles after the infusion of VDOT and FHWA money and the extra eight years added to the concession. However, after public outcry at the rates, the incoming governor,
Terry McAuliffe Terence Richard McAuliffe (born February 9, 1957) is an American businessman and politician who served as the List of governors of Virginia, 72nd governor of Virginia from 2014 to 2018. A member of the Democratic Party (United States), Democrat ...
announced a further, $82.5 million buydown of the tolls through the completion of the construction. This buydown reduced tolls to 75-cents/off peak and $1.00/peak for the light vehicles, and $2.25 during non-peak or $4.00 during peak hours for heavy vehicles. Under Gov. McAuliffe's plan, toll rates would increase by 25-cents each year until January 2017 or until the new Midtown Tunnel is completed, at which point they would return to the rates set in the Comprehensive Agreement. After 2017, rates increase annually by a factor equal to the greater of changes to Consumer Price Index or 3.5 percent.


Project description

Each level of the project was laid out in detail in the Comprehensive Agreement as four separate projects/services, along with the dates that construction on them must be substantially completed to avoid the contract penalties.


Downtown Tunnel and Midtown Tunnel rehabilitation work

The Downtown & Midtown Tunnel Rehabilitation Project consisted of 15 projects to bring the tunnels up to NFPA 502 standards, plus: * Removing the suspended ceiling of the eastbound tunnel. (The westbound tunnel tiles were removed in 2011 for safety.) * Replacing old lights with energy-efficient LEDs. * Adding seven sets of jet ventilation fans (14 per tunnel). * Removing police booths and other cosmetic rehab work. Rehabilitation work on the westbound Downtown Tunnel (Norfolk to Portsmouth) began on August 9, 2013. The plan initially called for closing the tunnel on about 25 consecutive weekends from 8 p.m. Friday to 5 a.m. Monday, with traffic to be primarily detoured to the High Rise Bridge using I-464. One-lane closures were not feasible because most of this work required overhead work (such as installing the fireproofing on the ceiling), or work that would cross the centerline. But after several weekends of closures, public outcry from businesses and citizens of Portsmouth forced VDOT and ERC to reconsider the plan. Portsmouth City Council asked VDOT to look at turning the eastbound tunnel into a two-way tunnel during the weekend closures, an idea VDOT and ERC had initially ruled out, insisting that "maintaining two lanes of eastbound traffic in the eastbound Downtown Tunnel while directing westbound traffic towards one of the four alternative routes (with the I-64 High Rise Bridge as the primary detour) is the best course of action, both for the Project and the traveling public." Eventually, ERC changed the plan from full weekend closures to nightly closures from 8 p.m. to 5 a.m. Rehabilitation work on the eastbound tunnel began on July 25, 2014. ERC scheduled full weekend closures on the eastbound tunnel and little to no resistance was felt from city leaders or residents. To minimize delays, work on the Midtown Tunnel will begin after the completion of the new Midtown Tunnel. The Downtown Tunnel rehabilitation work ended August 16, 2016.


Parallel Midtown Tunnel construction

The Midtown Tunnel Construction consists of the fabrication and installation of the new, parallel Midtown Tunnel, as well as upgrading & replacing the Brambleton Ave/ Hampton Boulevard interchange, which leads directly to the tunnel. Fabrication of the tunnel's 11 concrete elements began in November 2012 in
Sparrows Point, Maryland Sparrows Point is an industrial area in unincorporated Baltimore County, Maryland, United States, adjacent to Edgemere. Named after Thomas Sparrow, landowner, it was the site of a very large industrial complex owned by Bethlehem Steel, known ...
and are towed down the Chesapeake Bay to the Project site in Portsmouth for immersion and placement under the Elizabeth River. As of March 2015, the first six elements are in place and production of the remaining five tunnel elements is in progress. Upon completion of construction, traffic in the existing Midtown Tunnel will be converted to one-way eastbound from Portsmouth to Norfolk and the new 2-lane tunnel will carry westbound traffic from Norfolk to Portsmouth. The scheduled completion date of the new Midtown Tunnel is December 24, 2016. ERC will face the steepest penalty of all the projects -- $21,000 a day—if this project is not completed by its completion date. For the rehabilitation work on the Midtown Tunnel, ERC will face the same penalty as for the work on the Downtown tunnel ($7,000/day), if the work is not completed by May 11, 2018. ERC completed the new tunnel a half year ahead of schedule, and opened the new, westbound tunnel to traffic at 1:40pm EST on June 17, 2016. Rehabilitation work on the Midtown was completed early as well, by mid-2017.


Martin Luther King Expressway

The Martin Luther King Freeway Project consists of extending the freeway from U.S. 58/London Boulevard to an interchange with
I-264 Interstate 264 is the designation for two Interstate Highways in the United States, both of which are related to Interstate 64: *Interstate 264 (Kentucky), a bypass of Louisville, Kentucky *Interstate 264 (Virginia) Interstate 264 (I-264) ...
with an interchange at High Street (which carries U.S. 17 to the east of its interchange with U.S. 58). This requires the permanent closure of two I-264 ramps: eastbound to Des Moines Ave, and Westbound to South Street, in accordance with the projects FHWA approval of the VDOT proposal. Construction on the extension began in November 2014 and was completed in 2016.


Maintenance and operations

Operational control of the tunnel system was turned over to ERC on July 12, 2012. Under the agreement's turnover plan, ERC is responsible for all maintaining and operating: * I-264 from the west end of the Berkley Bridge, through the Downtown Tunnel to the west end of the MLK Freeway ramps in Portsmouth, * from the Brambleton Ave/Hampton Blvd interchange in Norfolk, up to the West Norfolk Bridge, and * from the West Norfolk Bridge along the Martin Luther King Freeway. The boundaries for incident management, which includes removal of disabled/wrecked vehicles as well as snow removal, extends the above limits: * from the
West Norfolk Bridge State Route 164 (SR 164) is a primary state highway in the U.S. state of Virginia that connects the northern parts of Suffolk and Portsmouth with Newport News and Hampton via Interstate 664 (I-664) with Downtown Portsmouth and Norfolk through ...
westbound to the eastern end of the W. Norfolk Road overpass on the Western Freeway in Portsmouth (not including the offramps), * from the Waterside Drive/City Hall Avenue/
Tidewater Drive State Route 168 is a primary state highway in the South Hampton Roads region of the U.S. state of Virginia. It runs from the border with North Carolina (where it continues as North Carolina Highway 168 towards the Outer Banks) through the in ...
interchange westbound across the Berkley Bridge in Norfolk continuing to the western end of the future MLK Freeway ramps in Portsmouth , and * all of the MLK Expressway itself.


See also

* Public-private partnerships in the United States


Notes


References

{{Reflist, 30em Transportation in Hampton Roads Roads in Virginia Road construction Public–private partnership projects in the United States