HOME

TheInfoList



OR:

The Crystal River Nuclear Plant, also called the Crystal River 3 Nuclear Power Plant, or simply CR-3, is a closed
nuclear power plant A nuclear power plant (NPP), also known as a nuclear power station (NPS), nuclear generating station (NGS) or atomic power station (APS) is a thermal power station in which the heat source is a nuclear reactor. As is typical of thermal power st ...
located in
Crystal River, Florida Crystal River is a city in Citrus County, Florida, Citrus County, Florida, United States. The population was 3,396 in the 2020 census, up from 3,108 at the 2010 census. It is part of the Homosassa Springs, Florida Citrus County, Florida, Metrop ...
. the facility is being decommissioned, a process expected to last 60 years. The power plant was completed and licensed to operate in December 1976, and operated safely for 33 years until shutdown in September 2009. It was the third plant built as part of the
Crystal River Energy Complex The Crystal River Energy Complex consists of seven power-generating plants on a site near the mouth of the Crystal River in Citrus County, Florida. Crystal River 1, 2, 4, and 5 are fossil fuel power plants. Crystal River 3 was previously t ...
(CREC) which contains a single nuclear power plant, while sharing the site with four operational
fossil fuel power plant A fossil fuel power station is a thermal power station that burns fossil fuel, such as coal, oil, or natural gas, to produce electricity. Fossil fuel power stations have machines that convert the heat energy of combustion into mechanical en ...
s. The Crystal River reactor went offline in September 2009 for refueling, OTSG replacement (once through steam generator), and 20% power up-rate outage. In preparing the containment building for making the opening to replace the two OTSG's, tendons in the
containment building A containment building is a reinforced steel, concrete or lead structure enclosing a nuclear reactor. It is designed, in any emergency, to contain the escape of radioactive steam or gas to a maximum pressure in the range of . The containment is ...
wall were detensioned. During the concrete removal in creating the opening workers discovered a large gap in the concrete of the containment building wall. The main cause of the gap, which further engineering analysis determined was a large delamination, was attributed to the scope and sequence of the tendon detensioning. The plant had originally been scheduled to restart in April 2011, but the project encountered a number of delays. Repairs were successful, but additional delamination began to occur in adjacent bays. After several months of analyzing options, Duke Energy senior executives announced in February 2013 that the Crystal River Nuclear Plant would be permanently shut down. The costs were estimated at $1.18 billion over the next 60 years of decommissioning. The coal-fired units are not affected. Crystal River was originally owned by Florida Progress Corporation (and operated by its subsidiary, Florida Power Corporation) but, in 2000, it was bought by Carolina Power & Light to form the new company, Progress Energy. Progress Energy owned 91.8% of the plant; the remainder is owned by nine municipal utilities. Effective July 2, 2012, Duke Energy purchased Progress Energy and made it a wholly owned direct unit of Duke Energy.


Power plant and containment

Crystal River 3 Nuclear Power Plant was an operating 860 MWe, PWR (pressurized water reactor plant). There are three main barriers that protect the public from the radiation hazards associated with nuclear operations. One of those barriers is known as the containment building which houses the fuel, the reactor, and the reactor cooling system. The Crystal River containment building is a steel lined post-tensioned (
prestressed concrete Prestressed concrete is a form of concrete used in construction. It is substantially prestressed (Compression (physics), compressed) during production, in a manner that strengthens it against tensile forces which will exist when in service. Post-t ...
) cylindrical concrete structure approximately in height with an outside diameter of about . The containment has 42-inch thick concrete walls, has a flat foundation mat and a shallow torispherical dome. Post-tensioning is achieved by utilizing an outer array of horizontal tendons immediately adjacent to an inner array of vertical tendons that are embedded in the walls about 15 inches from the outside surface.


Refueling outage, containment repairs and closure

CR-3 went offline in September 2009 for RFO-16. While the reactor was down, the old steam generators were to be replaced. There are 426 steel tendons within the concrete walls of the reactor containment dome which reinforce the dome. Plan developer Sargent & Lundy specified that 97 tendons be loosened. Progress rejected that number as excessive. The next proposal was to loosen 74 tendons, which was typical of other nuclear plants doing the procedure. According to a Progress employee, "de-tensioning the tendons is a very expensive and time-consuming effort", so the number was further reduced to 65. Progress engaged
Bechtel Bechtel Corporation () is an American engineering, procurement, construction, and project management company founded in San Francisco, California in 1898, and headquartered in Reston, Virginia in the Washington metropolitan area. , the '' E ...
to provide a 3rd party review, which agreed that 65 was appropriate. However, when the work was performed, only 27 tendons were loosened, and a foreman and supervisor sent emails questioning the way the tendons were loosened. When workers began to cut the access hole for the steam generators, a crack formed. That crack was repaired, but more cracks appeared. Engineers noticed that parts of the concrete had delaminated. This was repaired, and the concrete re-tensioned, but the same problem was found in other areas. The plant had originally been due to restart in April 2011 following the uprate, but in June 2011 Progress Energy said that it did not expect it to restart until 2014. Preliminary cost estimates for the repairs was put at between $900 million and $1.3 billion, but this estimate was later called into question by Duke Energy. In October 2012 an independent review estimated the repair cost at $1.5 billion, with a worst-case scenario of $3.4 billion. In February 2013 Duke Energy announced that Crystal River would be permanently shut down and that they will recover $850 million in insurance claims. A Duke spokesperson stated, "The company sought input from numerous engineering experts — internally and externally — and used proven industry-accepted practices when determining how to replace the steam generators. Analysis has shown that the 2009 delamination (cracking) could not have been predicted. The U.S. Nuclear Regulatory Commission confirmed these findings."
Gregory Jaczko Gregory B. Jaczko (; born October 29, 1970, Norristown, Pennsylvania) is a physicist who is the 13th and former chairman of the Nuclear Regulatory Commission, U.S. Nuclear Regulatory Commission (NRC) from 2009 to 2012.Nuclear Regulatory Commission The United States Nuclear Regulatory Commission (NRC) is an independent agency of the United States government tasked with protecting public health and safety related to nuclear energy. Established by the Energy Reorganization Act of 1974, the ...
, stated, "That's a multi-billion dollar asset that had to be shut down because of improper work planning, improper understanding of how to properly do this containment retrofit".


Surrounding population

The NRC defines two emergency planning zones around nuclear power plants: a plume exposure pathway zone with a radius of , concerned primarily with exposure to, and inhalation of, airborne
radioactive contamination Radioactive contamination, also called radiological pollution, is the deposition of, or presence of Radioactive decay, radioactive substances on surfaces or within solids, liquids, or gases (including the human body), where their presence is uni ...
, and an ingestion pathway zone of about , concerned primarily with ingestion of food and liquid contaminated by radioactivity. The 2010 U.S. population within of Crystal River was 20,695, an increase of 50.9 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within was 1,046,741, an increase of 32.4 percent since 2000. Cities within 50 miles include
Ocala Ocala ( ) is a city in and the county seat of Marion County, Florida, United States. Located in North Central Florida, the city's population was 63,591 as of the 2020 census, up from 56,315 at the 2010 census and making it the 43rd-most popul ...
, ( to city center) and Spring Hill ( to city center).


Seismic risk

On September 10, 2006, a magnitude 5.8 earthquake occurred 300 miles southwest of the nuclear plant, no damage occurred to the Crystal River Nuclear Power Plant from the rare quake. The odds of such a quake happening again in the near-term around Florida are low. The NRC's estimate of the risk each year of an earthquake intense enough to cause core damage to the reactor at Crystal River was 1 in 45,455, according to an NRC study published in August 2010.


Electricity production


See also

*
Progress Energy Inc Progress Energy was a power generation and distribution company. Prior to its merger with Duke Energy, it was a Fortune 500 energy company with more than 21,000 megawatts of generation capacity and $9 billion in annual revenues. Headquartered in ...
*
Levy County Nuclear Power Plant The Levy County Nuclear Power Plant was a proposed nuclear power plant in Levy County, Florida. Progress Energy, Inc., Progress Energy Florida originally estimated that the reactors would cost $5 billion and would commence operation in 2016. It ...


References


External links

* *
NukeWorker
{{U.S. nuclear plants Towers in Florida Buildings and structures in Citrus County, Florida Energy infrastructure completed in 1977 Former nuclear power stations in the United States Crystal River, Florida 1977 establishments in Florida Former power stations in Florida Energy infrastructure closed in the 2000s 2009 disestablishments in Florida