Within
quality management systems (QMS) and
information technology
Information technology (IT) is a set of related fields within information and communications technology (ICT), that encompass computer systems, software, programming languages, data processing, data and information processing, and storage. Inf ...
(IT) systems, change control is a process—either formal or informal
—used to ensure that changes to a product or system are introduced in a controlled and coordinated manner. It reduces the possibility that unnecessary changes will be introduced to a system without forethought, introducing faults into the system or undoing changes made by other users of software. The goals of a change control procedure usually include minimal disruption to services, reduction in back-out activities, and cost-effective utilization of resources involved in implementing change. According to the
Project Management Institute, change control is a "process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected."
Change control is used in various industries, including in IT,
software development,
the pharmaceutical industry,
the medical device industry,
and other engineering/manufacturing industries.
For the IT and software industries, change control is a major aspect of the broader discipline of change management. Typical examples from the
computer
A computer is a machine that can be Computer programming, programmed to automatically Execution (computing), carry out sequences of arithmetic or logical operations (''computation''). Modern digital electronic computers can perform generic set ...
and
network environments are patches to software products, installation of new
operating system
An operating system (OS) is system software that manages computer hardware and software resources, and provides common daemon (computing), services for computer programs.
Time-sharing operating systems scheduler (computing), schedule tasks for ...
s, upgrades to network
routing
Routing is the process of selecting a path for traffic in a Network theory, network or between or across multiple networks. Broadly, routing is performed in many types of networks, including circuit-switched networks, such as the public switched ...
tables, or changes to the
electrical power
Electric power is the rate of transfer of electrical energy within a electric circuit, circuit. Its SI unit is the watt, the general unit of power (physics), power, defined as one joule per second. Standard prefixes apply to watts as with oth ...
systems supporting such
infrastructure
Infrastructure is the set of facilities and systems that serve a country, city, or other area, and encompasses the services and facilities necessary for its economy, households and firms to function. Infrastructure is composed of public and pri ...
.
Certain portions of
ITIL cover change control.
The process
There is considerable overlap and confusion between
change management,
configuration management
Configuration management (CM) is a management process for establishing and maintaining consistency of a product's performance, functional, and physical attributes with its requirements, design, and operational information throughout its life. ...
and change control. The definition below is not yet integrated with definitions of the others.
Change control can be described as a set of six steps:
# Plan / scope
# Assess / analyze
# Review / approval
# Build / test
# Implement
# Close
Plan / scope
Consider the primary and ancillary detail of the proposed change. This should include aspects such as identifying the change, its owner(s), how it will be communicated and executed, how success will be verified, the change's estimate of importance, its added value, its conformity to business and industry standards, and its target date for completion.
Assess / analyze
Impact and risk assessment is the next vital step. When executed, will the proposed plan cause something to go wrong? Will related systems be impacted by the proposed change? Even minor details should be considered during this phase. Afterwards, a risk category should ideally be assigned to the proposed change: high-, moderate-, or low-risk. High-risk change requires many additional steps such as management approval and stakeholder notification, whereas low-risk change may only require project manager approval and minimal documentation.
If not addressed in the plan/scope, the desire for a backout plan should be expressed, particularly for high-risk changes that have significant worst-case scenarios.
Review / approval
Whether it's a change controller,
change control board, steering committee, or project manager, a review and approval process is typically required. The plan/scope and impact/risk assessments are considered in the context of business goals, requirements, and resources. If, for example, the change request is deemed to address a low severity, low impact issue that requires significant resources to correct, the request may be made low priority or shelved altogether. In cases where a high-impact change is requested but without a strong plan, the review/approval entity may request a full
business case
A business case captures the reasoning for initiating a project or task. Many projects, but not all, are initiated by using a business case. It is often presented in a well-structured written document, but may also come in the form of a short ver ...
may be requested for further analysis.
Build / test
If the change control request is approved to move forward, the delivery team will execute the solution through a small-scale development process in test or development environments. This allows the delivery team an opportunity to design and make incremental changes, with
unit and/or
regression testing
Regression testing (rarely, ''non-regression testing'') is re-running functional and non-functional tests to ensure that previously developed and tested software still performs as expected after a change. If not, that would be called a '' regr ...
.
Little in the way of testing and validation may occur for low-risk changes, though major changes will require significant testing before implementation.
They will then seek approval and request a time and date to carry out the implementation phase. In rare cases where the solution can't be tested, special consideration should be made towards the change/implementation window.
Implement
In most cases a special implementation team with the technical expertise to quickly move a change along is used to implement the change. The team should also be implementing the change not only according to the approved plan but also according to organizational standards, industry standards, and quality management standards.
The implementation process may also require additional staff responsibilities outside the implementation team, including stakeholders who may be asked to assist with troubleshooting.
Following implementation, the team may also carry out a post-implementation review, which would take place at another stakeholder meeting or during project closing procedures.
Close
The closing process can be one of the more difficult and important phases of change control.
Three primary tasks at this end phase include determining that the project is actually complete, evaluating "the project plan in the context of project completion", and providing tangible proof of project success.
If despite best efforts something went wrong during the change control process, a post-mortem on what happened will need to be run, with the intent of applying lessons learned to future changes.
Regulatory environment
In a
good manufacturing practice regulated industry, the topic is frequently encountered by its users. Various industrial guidances and commentaries are available for people to comprehend this concept.
As a common practice, the activity is usually directed by one or more
SOPs.
From the
information technology
Information technology (IT) is a set of related fields within information and communications technology (ICT), that encompass computer systems, software, programming languages, data processing, data and information processing, and storage. Inf ...
perspective for
clinical trial
Clinical trials are prospective biomedical or behavioral research studies on human subject research, human participants designed to answer specific questions about biomedical or behavioral interventions, including new treatments (such as novel v ...
s, it has been guided by another U.S.
Food and Drug Administration
The United States Food and Drug Administration (FDA or US FDA) is a List of United States federal agencies, federal agency of the United States Department of Health and Human Services, Department of Health and Human Services. The FDA is respo ...
document.
See also
*
Change request
*
Change order
*
Engineering change order
*
Documentation
Documentation is any communicable material that is used to describe, explain or instruct regarding some attributes of an object, system or procedure, such as its parts, assembly, installation, maintenance, and use. As a form of knowledge managem ...
*
Identifier
An identifier is a name that identifies (that is, labels the identity of) either a unique object or a unique ''class'' of objects, where the "object" or class may be an idea, person, physical countable object (or class thereof), or physical mass ...
*
Version control
Version control (also known as revision control, source control, and source code management) is the software engineering practice of controlling, organizing, and tracking different versions in history of computer files; primarily source code t ...
*
Changelog
*
Living document
*
Specification (technical standard)
A specification often refers to a set of documented requirements to be satisfied by a material, design, product, or service. A specification is often a type of technical standard.
There are different types of technical or engineering specificati ...
*
Standardization
Standardization (American English) or standardisation (British English) is the process of implementing and developing technical standards based on the consensus of different parties that include firms, users, interest groups, standards organiza ...
*
Scope management
Citations
References
*