The Celtic Interconnector is a planned 700
MW high-voltage direct current
A high-voltage direct current (HVDC) electric power transmission system (also called a power superhighway or an electrical superhighway) uses direct current (DC) for electric power transmission, in contrast with the more common alternating curre ...
(HVDC)
submarine power cable
A submarine power cable is a transmission cable for carrying electric power below the surface of the water.[EirGrid
EirGrid plc is the state-owned electric power transmission operator in Ireland. It is a public limited company registered under the Companies Acts; its shares are held by the Minister for the Environment, Climate and Communications. It is one of ...]
stated in 2022 that the interconnector was arguably "the most important Irish infrastructure project for this decade".
Route
The cable is due to run between the
Knockraha substation in
County Cork
County Cork ( ga, Contae Chorcaí) is the largest and the southernmost county of Ireland, named after the city of Cork, the state's second-largest city. It is in the province of Munster and the Southern Region. Its largest market towns ar ...
to the La Martyre substation in
Finistère
Finistère (, ; br, Penn-ar-Bed ) is a department of France in the extreme west of Brittany. In 2019, it had a population of 915,090. .
Of its total length of , will pass through Irish, British and French waters of the
Celtic Sea
The Celtic Sea ; cy, Y Môr Celtaidd ; kw, An Mor Keltek ; br, Ar Mor Keltiek ; french: La mer Celtique is the area of the Atlantic Ocean off the southern coast of Ireland bounded to the east by Saint George's Channel; other limits includ ...
.
[
]
Status
On 14 Sept 2022, the UK Marine Management Organisation
The Marine Management Organisation (MMO) is an executive non-departmental public body in the United Kingdom established under the Marine and Coastal Access Act 2009, with responsibility for English waters. The MMO exists to make a significant cont ...
granted a licence for the project to proceed. This was the last major license required before Step 6 construction could start in late 2022.
Project step six, construction and energisation, is scheduled to take place from 2022 to 2026. As of November 2022, the interconnector was "due to be completed and operational by 2026".
Technical specification
The electrical interconnector
An interconnector (also known as a DC tie in the USA) is a structure which enables high voltage DC electricity to flow between electrical grids. An electrical interconnector allows electricity to flow between separate AC networks, or to link sy ...
, which will be the first between the two countries, had an initial expected cost of €1billion and a planned capacity of 700MW.[
The project also includes plans for a direct ]fibre optic
An optical fiber, or optical fibre in Commonwealth English, is a flexible, transparent fiber made by drawing glass (silica) or plastic to a diameter slightly thicker than that of a human hair. Optical fibers are used most often as a means ...
communications link between Ireland and France.
Project promoters
The project is a joint venture between the Irish transmission system operator (TSO) EirGrid
EirGrid plc is the state-owned electric power transmission operator in Ireland. It is a public limited company registered under the Companies Acts; its shares are held by the Minister for the Environment, Climate and Communications. It is one of ...
and French TSO Réseau de Transport d'Électricité (RTE) for the purpose of improving security of supply, reducing consumer electricity costs and supporting the development of renewable energy.
Project economics
, the interconnector was expected to cost €1.6billion.
According to the then Taoiseach, Micheál Martin, "The Celtic Interconnector will bring tangible benefits to the citizens of both France and Ireland by promoting the use of renewable energy, bringing down electricity prices, and helping ensure security of energy supply".
Project history
In July 2016, after completion of a feasibility study
A feasibility study is an assessment of the practicality of a project or system. A feasibility study aims to objectively and rationally uncover the strengths and weaknesses of an existing business or proposed venture, opportunities and threats pr ...
the two countries agreed to proceed with a two-year planning phase.[
This included an economic assessment, environmental considerations and will determine the placement of the cable and onshore stations, while a decision initially due on the project is foreseen for 2020 or 2021. In May 2018, the project was granted a foreshore license to begin marine surveys for the potential landing sites at Ballinwilling, Claycastle and Redbarn beaches, County Cork.
In 2018, the project was given preliminary approval for European Investment Bank funding as part of preparations by Ireland for Brexit, for €530million.
By 2019, the project had been designated a European Project of Common Interest as part of the ]European Super Grid
The European super grid is a possible future super grid that would ultimately interconnect the various European countries and the regions around Europe's borders – including North Africa, Kazakhstan, and Turkey – with a high-voltage ...
.
Three potential landing sites on the Cork coast were identified and six locations (Ballyadam, Leamlara, Knockraha, Pigeon Hill, Kilquane and Ballyvatta) were under consideration for the HVDC converter station.
By 2019, due to the potential impact of Brexit
Brexit (; a portmanteau of "British exit") was the withdrawal of the United Kingdom (UK) from the European Union (EU) at 23:00 GMT on 31 January 2020 (00:00 1 February 2020 CET).The UK also left the European Atomic Energy Community (EAE ...
on electricity trading over the existing Ireland UK HVDC interconnectors, planning for the Celtic Interconnector had accelerated.
In December 2020, EirGrid and RTE signed a €520million European Commission
The European Commission (EC) is the executive of the European Union (EU). It operates as a cabinet government, with 27 members of the Commission (informally known as "Commissioners") headed by a President. It includes an administrative body ...
funding agreement for the Celtic Interconnector.
As of 2021, the cable was expected to be operational by 2026.[ In August 2021, the project was at step five in the planning process and was expected to continue until 2022.]
In May 2022, An Bord Pleanala granted permission for the onshore portion of the project while in August 2022, the Department for Housing Local Government and Heritage granted the project a foreshore licence, an important permit for the undersea work involved.
In November 2022, final construction and finance agreements were signed off by the Irish and French governments at the Irish embassy in Paris.
See also
* Energy in Ireland
Ireland is a net energy importer. Ireland's import dependency decreased to 85% in 2014 (from 89% in 2013).
The cost of all energy imports to Ireland was approximately €5.7 billion, down from €6.5 billion (revised) in 2013 due mainly to f ...
* Energy in France
* Electricity sector in Ireland
The electricity sectors of the Republic of Ireland and Northern Ireland are integrated and supply 2.5 million customers from a combination of coal, peat, natural gas, wind and hydropower. In 2018 natural gas produced 51.8%, while wind turbines gene ...
* Electricity sector in France
* Greenlink
Greenlink is a high-voltage direct current (HVDC) submarine power cable under construction between County Wexford in Ireland and Pembrokeshire in Wales.
Project status
As of May 2022, the project has reached financial close, and construction ha ...
, cable project to connect Ireland
Ireland ( ; ga, Éire ; Ulster Scots dialect, Ulster-Scots: ) is an island in the Atlantic Ocean, North Atlantic Ocean, in Northwestern Europe, north-western Europe. It is separated from Great Britain to its east by the North Channel (Grea ...
and the United Kingdom
The United Kingdom of Great Britain and Northern Ireland, commonly known as the United Kingdom (UK) or Britain, is a country in Europe, off the north-western coast of the European mainland, continental mainland. It comprises England, Scotlan ...
* NordLink
NordLink is a subsea 1,400 megawatt (MW) HVDC power cable between Norway and Germany, opened in May 2021. The over long cable operates at a voltage of 500 kV DC.
The cable enables Deutsche Bahn to buy the full production from M� ...
, cable project to connect Norway
Norway, officially the Kingdom of Norway, is a Nordic country in Northern Europe, the mainland territory of which comprises the western and northernmost portion of the Scandinavian Peninsula. The remote Arctic island of Jan Mayen and t ...
and Germany
Germany, officially the Federal Republic of Germany (FRG),, is a country in Central Europe. It is the most populous member state of the European Union. Germany lies between the Baltic and North Sea to the north and the Alps to the sou ...
* NorGer, cable project to connect Norway
Norway, officially the Kingdom of Norway, is a Nordic country in Northern Europe, the mainland territory of which comprises the western and northernmost portion of the Scandinavian Peninsula. The remote Arctic island of Jan Mayen and t ...
and Germany
Germany, officially the Federal Republic of Germany (FRG),, is a country in Central Europe. It is the most populous member state of the European Union. Germany lies between the Baltic and North Sea to the north and the Alps to the sou ...
* NorNed
NorNed is a long high-voltage direct current submarine power cable between Feda in Norway and the seaport of Eemshaven in the Netherlands, which interconnects both countries' electrical grids. It was once the longest submarine power cable in the ...
, cable project to connect Norway
Norway, officially the Kingdom of Norway, is a Nordic country in Northern Europe, the mainland territory of which comprises the western and northernmost portion of the Scandinavian Peninsula. The remote Arctic island of Jan Mayen and t ...
and Netherlands
)
, anthem = ( en, "William of Nassau")
, image_map =
, map_caption =
, subdivision_type = Sovereign state
, subdivision_name = Kingdom of the Netherlands
, established_title = Before independence
, established_date = Spanish Netherl ...
References
External links
*{{Official, https://www.celticinterconnector.eu/ga/
Map with power line and tentative substation locations
Poste Electrique De La Martyre, Unnamed Road, 29800 La Martyre, France (map)
RTE video clip
Electrical interconnectors to and from the island of Ireland
Electrical interconnectors to and from the Synchronous Grid of Continental Europe
HVDC transmission lines
Proposed electric power infrastructure in the Republic of Ireland
Proposed electric power infrastructure in France
Proposed electric power transmission systems