History
Cellular manufacturing is derivative of principles of group technology, which were proposed by American industrialist Ralph Flanders in 1925 and adopted in Russia by the scientist Sergei Mitrofanov in 1933 (whose book on the subject was translated into English in 1959). Burbidge actively promoted group technology in the 1970s. "Apparently, Japanese firms began implementing cellular manufacturing sometime in the 1970s," and in the 1980s cells migrated to the United States as an element of just-in-time (JIT) production. One of the first English-language books to discuss cellular manufacturing, that of Hall in 1983, referred to a cell as a “U-line,” for the common, or ideal, U-shaped configuration of a cell—ideal because that shape puts all cell processes and operatives into a cluster, affording high visibility and contact. By 1990 cells had come to be treated as foundation practices in JIT manufacturing, so much so that Harmon and Peterson, in their book, ''Reinventing the Factory'', included a section entitled, "Cell: Fundamental Factory of the Future". Cellular manufacturing was carried forward in the 1990s, when just-in-time was renamed lean manufacturing. Finally, when JIT/lean became widely attractive in the service sector, cellular concepts found their way into that realm; for example, Hyer and Wemmerlöv's final chapter is devoted to office cells.Cell design
Cells are created in a workplace to facilitate flow. This is accomplished by bringing together operations or machines or people involved in a processing sequence of a products natural flow and grouping them close to one another, distinct from other groups. This grouping is called a cell. These cells are used to improve many factors in a manufacturing setting by allowing ''one-piece flow'' to occur. An example of one-piece flow would be in the production of a metallic case part that arrives at the factory from the vendor in separate pieces, requiring assembly. First, the pieces would be moved from storage to the cell, where they would be welded together, then polished, then coated, and finally packaged. All of these steps would be completed in a single cell, so as to minimize various factors (called non-value-added processes/steps) such as time required to transport materials between steps. Some common formats of single cells are: the U-shape (good for communication and quick movement of workers), the straight line, or the L-shape. The number of workers inside these formations depend on current demand and can be modulated to increase or decrease production. For example, if a cell is normally occupied by two workers and demand is doubled, four workers should be placed in the cell. Similarly, if demand halves, one worker will occupy the cell. Since cells have a variety of differing equipment, it is therefore a requirement that any employee is skilled at multiple processes.Implementation process
In order to implement cellular manufacturing, a number of steps must be performed. First, the parts to be made must be grouped by similarity (in design or manufacturing requirements) into families. Then a systematic analysis of each family must be performed; typically in the form of production flow analysis (PFA) for manufacturing families, or in the examination of design/product data for design families. This analysis can be time-consuming and costly, but is important because a cell needs to be created for each family of parts. Clustering of machines and parts is one of the most popular production flow analysis methods. The algorithms for machine part grouping include Rank Order Clustering, Modified Rank Order Clustering, and Similarity coefficients. There are also a number of mathematical models and algorithms to aid in planning a cellular manufacturing center, which take into account a variety of important variables such as, "multiple plant locations, multi-market allocations with production planning and various part mix." Once these variables are determined with a given level of uncertainty, optimizations can be performed to minimize factors such as, "total cost of holding, inter-cell material handling, external transportation, fixed cost for producing each part in each plant, machine and labor salaries."Difficulties in creating flow
The key to creating flow is continuous improvement to production processes. Upon implementation of cellular manufacturing, management commonly "encounters strong resistance from production workers". It will be beneficial to allow the change to cellular manufacturing to happen gradually. In this process. It is also difficult to fight the desire to have someBenefits and costs
Cellular manufacturing brings scattered processes together to form short, focused paths in concentrated physical space. So constructed, by logic a cell reduces flow time, flow distance, floor space, inventory, handling, scheduling transactions, and scrap and rework (the latter because of quick discovery of nonconformities). Moreover, cells lead to simplified, higher validity costing, since the costs of producing items are contained within the cell rather than scattered in distance and the passage of reporting time. Cellular manufacturing facilitates both production and quality control. Cells that are underperforming in either volume or quality can be easily isolated and targeted for improvement. The segmentation of the production process allows problems to be easily located and it is more clear which parts are affected by the problem. There are also a number of benefits for employees working in cellular manufacturing. The small cell structure improves group cohesiveness and scales the manufacturing process down to a more manageable level for the workers. Workers can more easily see problems or possible improvements within their own cells and tend to be more self-motivated to propose changes. Additionally, these improvements that are instigated by the workers themselves cause less and less need for management, so over time overhead costs can be reduced. Furthermore, the workers often are able to rotate between tasks within their cell, which offers variety in their work. This can further increase efficiency because work monotony has been linked to absenteeism and reduced production quality. Case studies in just-in-time and lean manufacturing are replete with impressive quantitative measures along those lines. For example, BAE Systems, Platform Solutions (Fort Wayne, Ind.), producing aircraft engine monitors and controls, implemented cells for 80 percent of production, reducing customer lead time 90 percent, work-in-process inventory 70 percent, space for one product family from 6,000 square feet to 1,200 square feet, while increasing product reliability 300 percent, multi-skilling the union-shop work force, and being designated an ''Industry Week'' Best Plant for the year 2000. By five years later, rework and scrap had been cut 50 percent, new product introduction cycles 60 percent, and transactions 90 percent, while also increasing inventory turns three-fold and service turn times 30 percent, and being awarded a Shingo Prize for the year 2005. It appears to be difficult to isolate how much of those benefits accrue from cellular organization itself; among many case studies researched for this article few include attempts at isolating the benefits. One exception is the contention, at Steward, Inc. (Chattanooga, Tenn.), producing nickel zinc ferrite parts for electromagnetic interference suppression. According to case study authors, cells resulted in reductions of cycle time from 14 to 2 days, work-in-process inventories by 80 percent, finished inventories by 60 percent, lateness by 96 percent, and space by 56 percent. Another cellular case study includes quantitative estimates of the extent to which cells contributed to overall benefits. At Hughes Ground Systems Group (Fullerton, Calif.), producing circuit cards for defense equipment, the first cell, which began as a pilot project with 15 volunteers, was launched in 1987. One month later a second cell began, and by 1992 all production employees, numbering about 150, had been integrated into seven cells. Prior to cells, circuit card cycle time, from kit release to shipment to the customer, had been 38 weeks. After the cells had taken over the full production sequence (mechanical assembly, wave solder, thermal cycle, and conformal coat), cycle time had fallen to 30.5 weeks, of which production manager John Reiss attributed 20 weeks to use of a "WIP chart system" by the cell teams and the other 10.5 weeks to the cellular organization itself. Later, when it seemed that the cells were overly large and cumbersome, cell sizes were shrunk by two-thirds, resulting in “micro cells” that cut cycle time by another 1.5 weeks. Finally, by adopting certain other improvements, cycle times had decreased to four weeks. Other improvements included reducing work-in-process inventory from 6 or 7 days to one day and percent defective from 0.04 to 0.01 Switching from a functional (job-shop) layout to cells often costs has a minus net cost, inasmuch as the cell reduces costs of transport, work-in-process and finished inventory, transactions, and rework. When large, heavy, expensive pieces of equipment (sometimes called “monuments” in lean lingo) must be moved, however, the initial costs can be high to the point where cells are not feasible.1. Hyer, Nancy, and Urban Wemmerlöv. 2002. op cit., pp 519-521 There are a number of possible limitations to implementing cellular manufacturing. Some argue that cellular manufacturing can lead to a decrease in production flexibility. Cells are typically designed to maintain a specific flow volume of parts being produced. Should the demand or necessary quantity decrease, the cells may have to be realigned to match the new requirements, which is a costly operation, and one not typically required in other manufacturing setups.See also