Babai Irrigation Project (बबई सिचाई आयोजना) is an irrigation project in western
Nepal Nepal, officially the Federal Democratic Republic of Nepal, is a landlocked country in South Asia. It is mainly situated in the Himalayas, but also includes parts of the Indo-Gangetic Plain. It borders the Tibet Autonomous Region of China Ch ...
which aim to irrigate 36,000 ha of land by using water of
Babai River The Babai River () originates in and completely drains Inner Terai Dang Valley of Mid-Western Nepal. Dang is an oval valley between the Mahabharat Range and Siwalik Hills in its eponymous district. Dang was anciently home to indigenous Th ...
. The project has been listed as the
National Pride Projects National Pride Projects are a set of infrastructure projects by the government of Nepal based on the proposal by the National Planning Commission. Projects Irrigation Projects * Babai Irrigation Project * Bheri Babai Diversion Multipurpose Proj ...
of Nepal and is implemented by the
Ministry of Energy, Water Resources and Irrigation (Nepal) The Ministry of Energy, Water Resources and Irrigation () is a governmental body of Nepal that governs the development and implementation of energy including its conservation, regulation and utilization. It furthermore develops operates elect ...
. The project aims to irrigate about 21,000 ha and 15,000 ha in the eastern and western side of the river respectively. The project cost is estimated to be about NPR 17,340,000,000.


Project implementation

(''Years in BS refers to
Bikram Sambat Vikram Samvat (ISO: ''Vikrama Saṁvata''; abbreviated VS), also known as the Vikrami calendar is a Hindu calendar historically used in the Indian subcontinent and still also used in several Indian states and Nepal. It is a lunisolar calendar, ...
'') The master plan study of the project was done in 2024 BS which concluded to irrigate 21,000 ha and 15,000 ha in the eastern and western side of the river respectively.


First stage

In 2035 BS, the first stage of the feasibility study was done to irrigate 13,240 ha in the eastern branch and detail engineering was done for the same in 2040BS. When the world bank in 2046 BS disagreed to fund the project, the district level committee started the work on its own by firstly constructing the highway weir cum bridge over the Babai River. This work was completed in 2049 BS. By 2050 BS 5.5km of the canal was constructed and the traditional canals (''Budhi kulo, Majro Kulo, Raj Kulo and Dhadhawar kulo'') were fed to irrigate about 4000 ha. From 2051 BS to 2058 BS, 28 km of the canal was constructed.


Second stage

The design works of the second stage of the construction were concluded in 2058 BS. As of 2020, this stage is still ongoing. Study of the canal from chainage 28 km to 43 km is being carried out.


See also

* Bheri Babai Diversion Multipurpose Project *
National Pride Projects National Pride Projects are a set of infrastructure projects by the government of Nepal based on the proposal by the National Planning Commission. Projects Irrigation Projects * Babai Irrigation Project * Bheri Babai Diversion Multipurpose Proj ...
*
Ministry of Energy, Water Resources and Irrigation (Nepal) The Ministry of Energy, Water Resources and Irrigation () is a governmental body of Nepal that governs the development and implementation of energy including its conservation, regulation and utilization. It furthermore develops operates elect ...


External links


Official website


References

{{Nepal-stub Irrigation in Nepal National Pride Projects