The Akosombo Dam, also known as the Volta Dam, is a
hydroelectric dam Hydroelectricity, or hydroelectric power, is electricity generated from hydropower (water power). Hydropower supplies one sixth of the world's electricity, almost 4500 TWh in 2020, which is more than all other renewable sources combined an ...
on the
Volta River The Volta River is the main river system in the West African country of Ghana. It flows south into Ghana from the Bobo-Dioulasso highlands of Burkina Faso. The main parts of the river are the Black Volta, the White Volta, and the Red Volta. ...
in southeastern
Ghana Ghana (; tw, Gaana, ee, Gana), officially the Republic of Ghana, is a country in West Africa. It abuts the Gulf of Guinea and the Atlantic Ocean to the south, sharing borders with Ivory Coast in the west, Burkina Faso in the north, and To ...
in the Akosombo gorge and part of the
Volta River Authority The Volta River Authority (VRA) is the main generator and supplier of electricity in Ghana. They are also the responsible for the maintenance of the hydro power supply plant. Establishment The VRA was established by the Volta River Development ...
. The construction of the dam flooded part of the Volta River Basin and led to the subsequent creation of Lake Volta. Lake Volta is the largest man-made lake in the world by surface area. It covers , which is 3.6% of Ghana's land area. With a volume of 148 cubic kilometers, Lake Volta is the world's third largest man-made lake by volume; the largest being
Lake Kariba Lake Kariba is the world's largest artificial lake and reservoir by volume. It lies upstream from the Indian Ocean, along the border between Zambia and Zimbabwe. Lake Kariba was filled between 1958 and 1963 following the completion of the Karib ...
which contains 185 cubic kilometers of water. The primary purpose of the Akosombo Dam was to provide electricity for the
aluminium Aluminium (aluminum in American and Canadian English) is a chemical element with the symbol Al and atomic number 13. Aluminium has a density lower than those of other common metals, at approximately one third that of steel. I ...
industry. The Akosombo Dam was called "the largest single investment in the economic development plans of Ghana." The dam is significant for providing the majority of both
Togo Togo (), officially the Togolese Republic (french: République togolaise), is a country in West Africa. It is bordered by Ghana to the west, Benin to the east and Burkina Faso to the north. It extends south to the Gulf of Guinea, where its c ...
and
Benin Benin ( , ; french: Bénin , ff, Benen), officially the Republic of Benin (french: République du Bénin), and formerly Dahomey, is a country in West Africa. It is bordered by Togo to the west, Nigeria to the east, Burkina Faso to the nort ...
's electricity, although the construction of the Adjarala Dam (on Togo's
Mono River The Mono River is the major river of eastern Togo. Approximately long, and draining a basin of about , it rises between the town of Sokodé and the border with Benin, and flows south. Along the southern portion of the river towards its mouth, ...
) hopes to reduce these countries' reliance on imported electricity. The dam's original electrical output was , which was upgraded to in a retrofit project that was completed in 2006. The flooding that created the Lake Volta reservoir displaced many people and had a significant impact on the local environment, including seismic activity that led to
coastal erosion Coastal erosion is the loss or displacement of land, or the long-term removal of sediment and rocks along the coastline due to the action of waves, currents, tides, wind-driven water, waterborne ice, or other impacts of storms. The landwa ...
; a changed hydrology caused microclimatic changes with less rain and higher temperatures. The soil surrounding the lake is less fertile than the soil under it, and heavy agricultural use has required the use of fertilizers, which in turn has led to
eutrophication Eutrophication is the process by which an entire body of water, or parts of it, becomes progressively enriched with minerals and nutrients, particularly nitrogen and phosphorus. It has also been defined as "nutrient-induced increase in phytopla ...
, which caused, among others, the explosive growth of an invasive weed that renders water navigation and transportation difficult, and form a habitat for the vectors of water-borne illnesses such as
bilharzia Schistosomiasis, also known as snail fever, bilharzia, and Katayama fever, is a disease caused by parasitic flatworms called schistosomes. The urinary tract or the intestines may be infected. Symptoms include abdominal pain, diarrhea, bloody ...
,
river blindness Onchocerciasis, also known as river blindness, is a disease caused by infection with the parasitic worm ''Onchocerca volvulus''. Symptoms include severe itching, bumps under the skin, and blindness. It is the second-most common cause of blindne ...
and
malaria Malaria is a mosquito-borne infectious disease that affects humans and other animals. Malaria causes symptoms that typically include fever, tiredness, vomiting, and headaches. In severe cases, it can cause jaundice, seizures, coma, or death. S ...
. Resettlement of the displaced inhabitants proved complex and in some cases unsuccessful; traditional farming practices disappeared and poverty increased.


Design

The dam was conceived in 1915 by geologist Albert Kitson, but no plans were drawn until the 1940s. The development of the
Volta River The Volta River is the main river system in the West African country of Ghana. It flows south into Ghana from the Bobo-Dioulasso highlands of Burkina Faso. The main parts of the river are the Black Volta, the White Volta, and the Red Volta. ...
Basin was proposed in 1949, but because funds were insufficient, the American company
Volta Aluminum Company Volta Aluminum Company, known as VALCO, is an aluminium company based in Tema, Greater Accra Region founded by Kaiser Aluminum and now wholly owned by the government of Ghana. History VALCO was a joint venture with Kaiser Aluminum and ALCOA, ...
(Valco) lent money to Ghana so that the dam could be constructed. President Kwame Nkrumah adopted the Volta River hydropower project. The dam is long and high, comprising a high rock-fill embankment dam. It has a base width of and a structural volume of . The reservoir created by the dam, Lake Volta, has a capacity of and a surface area of . The lake is long. Maximum lake level is and minimum is . On the east side of the dam are two adjacent
spillway A spillway is a structure used to provide the controlled release of water downstream from a dam or levee, typically into the riverbed of the dammed river itself. In the United Kingdom, they may be known as overflow channels. Spillways ensure th ...
s that can discharge about of water. Each spillway contains six -wide and -tall steel
floodgate Floodgates, also called stop gates, are adjustable gates used to control water flow in flood barriers, reservoir, river, stream, or levee systems. They may be designed to set spillway crest heights in dams, to adjust flow rates in sluices a ...
s. The dam's power plant contains six Francis turbines. Each turbine is supplied with water via a long and diameter
penstock A penstock is a sluice or gate or intake structure that controls water flow, or an enclosed pipe that delivers water to hydro turbines and sewerage systems. The term is inherited from the earlier technology of mill ponds and watermills. H ...
with a maximum of of hydraulic head afforded. The final proposal outlined the building of an
aluminum Aluminium (aluminum in American and Canadian English) is a chemical element with the symbol Al and atomic number 13. Aluminium has a density lower than those of other common metals, at approximately one third that of steel. It ha ...
smelter at
Tema Tema is a city on the Bight of Benin and Atlantic coast of Ghana. It is located east of the capital city; Accra, in the region of Greater Accra, and is the capital of the Tema Metropolitan District. As of 2013, Tema is the eleventh most populo ...
, a dam constructed at Akosombo to power the smelter, and a network of power lines installed through southern Ghana. The aluminum smelter was expected to eventually provide the revenue necessary for establishing local
bauxite Bauxite is a sedimentary rock with a relatively high aluminium content. It is the world's main source of aluminium and gallium. Bauxite consists mostly of the aluminium minerals gibbsite (Al(OH)3), boehmite (γ-AlO(OH)) and diaspore (α-AlO ...
mining and refining, which would allow aluminum production without importing foreign alumina. Development of the aluminum industry within Ghana was dependent upon the proposed hydroelectric power. The proposed project's aluminum smelter was overseen by the American company
Kaiser Aluminum Kaiser Aluminum Corporation is an American aluminum producer. It is a spinoff from Kaiser Aluminum and Chemicals Corporation, which came to be when common stock was offered in Permanente Metals Corporation and Permanente Metals Corporation's ...
and is operated by Valco. The smelter received its financial investment from Valco shareholders, with the support of the Export-Import Bank of the United States. However, Valco did not invest without first requiring insurances from Ghana's government, such as company exemptions from taxes on trade and discounted purchases of electricity. The estimated total cost of the project was $258 million.


Construction

In May 1960, the Ghana government called for tenders for construction of the hydroelectric dam. In 1961, an Italian consortium,
Impregilo Webuild SpA (formerly Salini Impregilo SpA) () is an Italian industrial group specialised in the construction and civil engineering business headquartered in Milan. The company was formally founded in 2014 as the result of the merger by incorporat ...
which had just completed the Kariba Dam, won the contract. In 1961, the
Volta River Authority The Volta River Authority (VRA) is the main generator and supplier of electricity in Ghana. They are also the responsible for the maintenance of the hydro power supply plant. Establishment The VRA was established by the Volta River Development ...
(VRA) was established by Ghana's Parliament through the passage of the Volta River Development Act. The VRA's fundamental operations were structured by six Board members and Nkrumah as chairman. The VRA's primary task is to manage the development of the Volta River Basin, which included the construction and supervision of the dam, the power station and the power transmission network. The VRA is responsible for the reservoir impounded by the dam, fishing within the lake, lake transportation and communication, and the welfare of those surrounding the lake. The dam was built between 1961 and 1965. Its development was undertaken by the Ghanaian government and funded 25% by the International Bank for Reconstruction and Development of the
World Bank The World Bank is an international financial institution that provides loans and grants to the governments of low- and middle-income countries for the purpose of pursuing capital projects. The World Bank is the collective name for the Inte ...
, the United States, and the United Kingdom. Impreglio carried out the dredging of the river bed and dewatering of the channel, and completed the dam a month earlier than scheduled despite flooding of the Volta River in 1963 which delayed work over three months. Between 1961 and 1966, 28 workers of Impregilo died during the construction of the dam. Memorials in Akosombo township and St. Barbara Catholic Church have been put up in their honor. The construction of the Akosombo Dam resulted in the flooding of part of the Volta River Basin and its upstream fields, and in the creation of Lake Volta which covers 3.6% of Ghana's total land area. Lake Volta was formed between 1962 and 1966 and necessitated the relocation of about 80,000 people, who represented 1% of the population. People of 700 villages were relocated into 52 resettlement villages two years prior to the dam's completion; the resettlement program was under the direction of the VRA. Two percent of the resettlement population were riparian fishers, and most were subsistence farmers. The Eastern Region of Ghana and the populations incorporated within its districts were most subject to the project's effects.


Power generation

The dam provides electricity to Ghana and its neighboring West African countries, including
Togo Togo (), officially the Togolese Republic (french: République togolaise), is a country in West Africa. It is bordered by Ghana to the west, Benin to the east and Burkina Faso to the north. It extends south to the Gulf of Guinea, where its c ...
and
Benin Benin ( , ; french: Bénin , ff, Benen), officially the Republic of Benin (french: République du Bénin), and formerly Dahomey, is a country in West Africa. It is bordered by Togo to the west, Nigeria to the east, Burkina Faso to the nort ...
. Initially 20% of Akosombo Dam's electric output (serving 70% of national demand) was provided to Ghanaians in the form of electricity, the remaining 80% was generated for Valco. The Ghana government was compelled, by contract, to pay for over 50% of the cost of Akosombo's construction, but the country was allowed only 20% of the power generated. Some commentators are concerned that this is an example of
neocolonialism Neocolonialism is the continuation or reimposition of imperialist rule by a state (usually, a former colonial power) over another nominally independent state (usually, a former colony). Neocolonialism takes the form of economic imperialism, ...
. In recent years the production from the Valco plant has declined with the vast majority of additional capacity in Akosombo used to service growing domestic demand. Initially, the dam's power production capabilities greatly overreached the actual demand; while, the demand since the dam's inception has resulted in the doubling of hydropower production. Ghana's industrial and economic expansion triggered a higher demand for power, beyond the Akosombo's power plant capabilities. By 1981, a smaller dam was built at
Kpong Kpong is a town in the Lower Manya Krobo District of the Eastern Region of Ghana and particularly noted for the Kpong Dam The Kpong Dam, also known as the Akuse Dam, is a hydroelectric power generating dam on the lower Volta River near Akuse i ...
, downstream from Akosombo, and further upgrades to Akosombo have become necessary for maintaining hydropower output. Increasing demands for power exceed what can be provided by the current infrastructure. Power demands, along with unforeseen environmental trends, have resulted in rolling blackouts and major power outages. An overall trend of lower lake levels has been observed, sometimes below the requirement for operation of the dam. In the beginning of 2007, concerns were expressed over the electricity supply from the dam because of low water levels in the Lake Volta reservoir. During the latter half of 2007, much of this concern was abated when heavy rain fell in the catchment area of Volta River. In 2010, the highest-ever water level was recorded at the dam. This necessitated the opening of the flood gates at a reservoir elevation of , and for several weeks, water was spilled from the lake, causing some flooding downstream.


Impacts

The Akosombo Dam benefited some industrial and economic activities from the addition of lake transportation, increased fishing, new farming activities along the shoreline, and tourism.


Biological habitat

In the time following the construction of the dam, there has been a steady decline in agricultural productivity along the lake and the associated tributaries. The land surrounding Lake Volta is not nearly as fertile as the formerly cultivated land residing underneath the lake, and heavy agricultural activity has since exhausted the already inadequate soils. Downstream agricultural systems are losing soil fertility without the periodic floods that brought nutrients to the soil before the natural river flow was halted by the dam. The growth of commercially intensive agriculture has produced a rise in fertilizer run-off into the river. This, along with run-off from nearby cattle stocks and sewage pollution, has caused
eutrophication Eutrophication is the process by which an entire body of water, or parts of it, becomes progressively enriched with minerals and nutrients, particularly nitrogen and phosphorus. It has also been defined as "nutrient-induced increase in phytopla ...
of the river waters. The nutrient enrichment, in combination with the low water movement, has allowed for the invasion of aquatic weeds (''
Ceratophyllum ''Ceratophyllum'' is a cosmopolitan genus of flowering plants including four accepted living species in 2016, commonly found in ponds, marshes, and quiet streams in tropical and in temperate regions. It is the only extant genus in the family Ce ...
''). These weeds have become a formidable challenge to water navigation and transportation.


Human welfare

The presence of aquatic weed along the lake and within the tributaries has resulted in even greater detriment to local human health. The weeds provide the necessary habitat for black-fly, mosquitoes and snails, which are the vectors of water-borne illnesses such as
bilharzia Schistosomiasis, also known as snail fever, bilharzia, and Katayama fever, is a disease caused by parasitic flatworms called schistosomes. The urinary tract or the intestines may be infected. Symptoms include abdominal pain, diarrhea, bloody ...
,
river blindness Onchocerciasis, also known as river blindness, is a disease caused by infection with the parasitic worm ''Onchocerca volvulus''. Symptoms include severe itching, bumps under the skin, and blindness. It is the second-most common cause of blindne ...
and
malaria Malaria is a mosquito-borne infectious disease that affects humans and other animals. Malaria causes symptoms that typically include fever, tiredness, vomiting, and headaches. In severe cases, it can cause jaundice, seizures, coma, or death. S ...
. Since the installation of the dam, these diseases have increased remarkably. In particular, resettlement villages have shown an increase in disease prevalence since the establishment of Lake Volta, and a village's likelihood of infection corresponds to its proximity to the lake. Children and fishermen have been especially hard hit by this rise of disease prevalence. Additionally, the degradation of aquatic habitat has resulted in the decline of shrimp and clam populations. The physical health of local communities has been diminished from this loss of shellfish populations, as they provided an essential source of dietary protein. Likewise, the rural and industrial economies have experienced the financial losses associated with the decimation of river aquaculture. Increased human migration within the area has been driven by poverty and unfavorable resettlement conditions. This migration enabled the contraction of
HIV The human immunodeficiency viruses (HIV) are two species of ''Lentivirus'' (a subgroup of retrovirus) that infect humans. Over time, they cause acquired immunodeficiency syndrome (AIDS), a condition in which progressive failure of the immune ...
and has since led to its heightened prevalence within Volta Basin communities. The districts of Manya Krobo and Yilo Krobo, which lie within the southwest portion of the Volta Basin, are predominantly indigenous communities that have attained a disproportionate prevalence of HIV. The situation underlines the strength of the local factors upon these districts. Commercial sex work was established in response to the thousands of male workers that were in the area for building the dam. Ten percent of the child-bearing females from these two districts migrated out of their districts during this time. In 1986, "90% of AIDS victims in Ghana were women, and 96% of them had recently lived outside the country".


Socioeconomics

The loss of land experienced by the 80,000 people forcibly relocated meant the loss of their primary economic activities from fishing and agriculture, loss of their homes, loss of their family grave sites, loss of community stability, and the eventual loss of important social values. The resettlement program demonstrated the social complexities involved in establishing "socially cohesive and integrated" communities. Insufficient planning resulted in the relocation of communities into areas that were not capable of providing for their former livelihoods and traditions. The loss of the naturally fertile soils beneath Lake Volta essentially led to the loss of traditional farming practices. The poor living conditions provided within the resettlement villages has been demonstrated by population reductions since resettlement. One resettlement village in particular experienced a greater than 50% population reduction in the 23 years following relocation. Increased economic risks and experiences of poverty are associated with those communities most impacted by the Volta River's development. The extensive human migration and degradation of natural resources within the Volta-basin area, are the products of poverty in conjunction with population pressure.


Physical environment

Reservoir-induced seismicity Induced seismicity is typically minor earthquakes and tremors that are caused by human activity that alters the stresses and strains on Earth's crust. Most induced seismicity is of a low magnitude. A few sites regularly have larger quakes, such ...
has been recorded because of the crustal re-adjustments from the added weight of the water within Lake Volta. There is an eastward shift of the river's mouth from the changes to the river's delta, and this has led to continuing coastal erosion. The changes in the river hydrology have altered the local heat budget which has caused microclimatic changes such as decreasing rain and higher mean monthly temperatures. All of these larger scale environmental impacts will all further compound the problems surrounding disruptions to local economic activities and associated, difficult human welfare conditions. A case study by the International Federation of Surveyors has indicated that the dam has had a significant impact on the shoreline erosion of the barrier separating the Keta Lagoon from the sea. Dr. Isaac Boateng has calculated the reduction of fluvial sediment as being from 71 million cubic metres per year to as little as 7 million cubic metres per year.


See also

*
Adomi Bridge The Adomi Bridge (originally the Volta Bridge) is a latticed steel arch suspension bridge crossing the Volta River at Atimpoku in Ghana in West Africa. It is the first permanent bridge to span the Volta River, which drains south into the Gulf of G ...
*
Bui Dam The Bui Dam is a hydroelectric project in Ghana. It is built on the Black Volta river at the ''Bui Gorge'', at the southern end of Bui National Park. The project is a collaboration between the government of Ghana and Sino Hydro, a Chinese constru ...


Notes


References

* * * * *


External links


Video documentary on the history of the dam. Published by the Volta River Authority (2013)

Ghana Web – History of The Dam



University of Ghana

History of Akosombo dam


{{Authority control Dams in Ghana Lake Volta Dams on the Volta River Volta River Authority Dams completed in 1965 1965 establishments in Ghana Eastern Region (Ghana)