Falsework consists of temporary structures used in construction to support a permanent structure until its construction is sufficiently advanced to support itself. For arches, this is specifically called
centering Centring, centre, centering"Centering 2, Centring 2" def. 1. Whitney, William Dwight, and Benjamin E. Smith. ''The Century dictionary and cyclopedia''. vol. 2. New York: Century Co., 1901. p. 885., or center is a type of formwork: the temporary str ...
. Falsework includes temporary support structures for formwork used to mold concreteHardie G.M. (1995) Building Construction: Principles, Practices, and Materials. New Jersey: Prentice Hall. (Pg 116, paragraph 1) in the construction of buildings, bridges, and elevated roadways. The
British Standards British Standards (BS) are the standards produced by the BSI Group which is incorporated under a royal charter and which is formally designated as the national standards body (NSB) for the UK. The BSI Group produces British Standards under the ...
of practice for falsework, BS 5975:2008, defines falsework as "Any temporary structure used to support a permanent structure while it is not self-supporting."


History

Falsework has been employed in bridge and viaduct construction since ancient times. The Romans were renowned for its use, as at the
Limyra Bridge The Bridge near Limyra (in tr, Kırkgöz Kemeri, "Bridge of the Forty Arches") is a late Roman bridge in Lycia, in modern south-west Turkey, and one of the oldest segmented arch bridges in the world. Located near the ancient city of Limyra, ...
in Turkey. Until the turn of the 20th century almost all falsework was constructed from timber. To compensate for timber shortages in different regions and to rationalize labor and material usage, new systems were developed.Burrows B.G (198X) Thesis. (University of Warwick) The major developments include the design of connection devices (coupler), transitions to other spanning beams such as steel pipes or profiles or reusable timber beams, and adjustable steel props. In 1935 W.A. de Vigier designed an adjustable steel prop which revolutionized many aspects of the construction industry including to support slab formwork, wall formwork, trench sheeting and falsework. Materials from which falsework systems are manufactured have also diversified from traditional steel and timber to aluminium components. In the UK, BS 5975 gives recommendations for the design and use of falsework on construction sites. It was first introduced by the
British Standards Institute The British Standards Institution (BSI) is the national standards body of the United Kingdom. BSI produces technical standards on a wide range of products and services and also supplies certification and standards-related services to business ...
in March 1982 and the third version was published in 2008 with Amendment 1 in 2011. The new revisions bring the code up to date with methodology developed in the new CDM 2007 regulations and also the requirements of the new European codes EN 12811-1:2003 Temporary works equipment - Part 1: Scaffolds, and EN 12812:2004, Falsework - Performance requirements and general design.


In modern roadway construction

File:SFOBBSAS-YBIFalseworkFabrication 1485.JPG, Fabrication File:SFOBSAS-YBIFalseworkErection_1471.JPG, Erection file:SFOBSAS-YBIFalseworkPlacementIMG_1482.JPG, Placement file:SFOBB-YBITS-Falsework_1582Skew.jpg, Completed falsework :Fabrication: Metalworkers fabricate a falsework section from pipe and beams. :Erection: A section is lifted to a vertical position with the assistance of two forklift operators. :Placement: The section is guided into position by a ground crew. :Completed Falsework: Decking and some formwork has been added. Here we see the use of modern pipe-column falsework, used to support the formwork for a post-tensioned reinforced concrete flyover connector for the eastern span replacement of the San Francisco-Oakland Bay Bridge. When the supports are complete, wood beams and plywood or reusable metal forms will be placed, reinforcing and tenon conduits added, and concrete poured. After curing and any tenon tensioning, wedges will be removed and forms and falsework disassembled.


In bridge construction

A certain type of bridge, the self-anchored suspension bridge, ''must'' be supported during construction, either by the use of cantilever or suspension methods or by support from below. Support from below was used in the construction of the main span of the eastern span replacement of the San Francisco–Oakland Bay Bridge, using parallel prefabricated truss spans. Cast in place concrete bridges must also be supported during construction. The Sixth Street Viaduct in Los Angeles, California will be cast on falsework and then hung on its network tied arch cables. The release of the falsework will coincide with the tensioning of the arch cables.


Typical falsework components

Soffit: Plywood sheeting for walking platform and surface to pour bridge against, typically on top of 4x4 lumber at specified spacing of 12". Camber: Plywood strips that compensate for beam deflection Stringer: Steel beam that ties caps together Top Cap: Steel Beam Post: Steel Pipe or 12x12 lumber. Bottom Cap: Steel Beam Wedge Pack: 4x4 lumber cut into wedges for falsework adjustment, various lumber sizes include 2x6s and plywood Corbel: Distribute load to pads. Typical material is 12x12 lumber and steel beams Pad: Distribute load to ground. Most commonly 6x16 lumber.


See also

*
Arch bridge An arch bridge is a bridge with abutments at each end shaped as a curved arch. Arch bridges work by transferring the weight of the bridge and its loads partially into a horizontal thrust restrained by the abutments at either side. A viaduct (a ...
for the use of falsework in bridge construction. *
List of construction methods The list of construction methods covers the processes and techniques used in the construction process. The construction method is essential for civil engineers; utilizing it appropriately can help to achieve the desired results. The term ''building ...
*
Scaffolding Scaffolding, also called scaffold or staging, is a temporary structure used to support a work crew and materials to aid in the construction, maintenance and repair of buildings, bridges and all other man-made structures. Scaffolds are widely used ...


References

{{Authority control Building engineering Structural system