The Silicon Valley BART extension is an ongoing effort to expand service by
Bay Area Rapid Transit Bay Area Rapid Transit (BART) is a rapid transit system serving the San Francisco Bay Area in California. BART serves 50 stations along six routes on of rapid transit lines, including a spur line in eastern Contra Costa County which u ...
(BART) into
Santa Clara County Santa Clara County, officially the County of Santa Clara, is the sixth-most populous county in the U.S. state of California, with a population of 1,936,259, as of the 2020 census. Santa Clara County and neighboring San Benito County together ...
via the
East Bay The East Bay is the eastern region of the San Francisco Bay Area and includes cities along the eastern shores of the San Francisco Bay and San Pablo Bay. The region has grown to include inland communities in Alameda and Contra Costa counties ...
from its former terminus at the
Fremont station Fremont station (also known as Fremont–Centerville station) is a train station located in the Centerville area of Fremont, California, United States. The station is served by Amtrak ''Capitol Corridor'' commuter rail/intercity rail service a ...
in Alameda County. Planned since at least 1981, the project has seven stations in three sequential phases. The first phase was the Warm Springs BART extension, built by BART at a cost of $790 million, terminating at the new Warm Springs/South Fremont station. Construction began in 2009, and the extension and new station opened in 2017. The $2.3-billion second phase, known as phase I of Silicon Valley BART extension or the Berryessa extension, includes two new stations, the
Milpitas Milpitas (Spanish for "little milpas") is a city in Santa Clara County, California, in Silicon Valley. As of the 2020 census, the city population was 80,273. The city's origins lie in Rancho Milpitas, granted to Californio ranchero José Mar� ...
and Berryessa/North San Jose stations. Construction began in 2012, and the extension and its two new stations were inaugurated on June 12, 2020, while service for the public began on the next day. Many credited the former Mayor of San Jose,
Ron Gonzales Ronald R. Gonzales (born 1951) is an American politician and member of the Democratic Party, who served as the 63rd Mayor of San Jose, California. Gonzales was the first Hispanic to serve as Mayor of San Jose since 1845. Early life Gonzales ...
, with bringing this project to fruition. The $5.6-billion third phase to downtown San Jose remains unfunded. Targeted for completion in 2029–2030, it would add three new subway stations south of Berryessa: Alum Rock/28th Street,
Downtown San Jose Downtown San Jose is the central business district of San Jose, California. Downtown is one of the largest tech clusters in Silicon Valley, as well as the cultural and political center of San Jose. History The town was first settled in 1777. T ...
, Diridon, and a surface station in Santa Clara. Initial testing and preliminary construction activities began in January 2019. The
Santa Clara Valley Transportation Authority The Santa Clara Valley Transportation Authority, more commonly known simply as the Valley Transportation Authority (VTA), is a Special district (United States), special district responsible for public transit services, Congestion management agenc ...
(VTA) built the Berryessa extension, and intends to build the final downtown San Jose extension, but BART operates and maintains the completed portion of the extension and will also do so for the final phase when completed.


Funding

Santa Clara County Santa Clara County, officially the County of Santa Clara, is the sixth-most populous county in the U.S. state of California, with a population of 1,936,259, as of the 2020 census. Santa Clara County and neighboring San Benito County together ...
was originally planned to be part of the BART system, but local governments did not approve. Minor service at
Palo Alto Palo Alto (; Spanish for "tall stick") is a charter city in the northwestern corner of Santa Clara County, California, United States, in the San Francisco Bay Area, named after a coastal redwood tree known as El Palo Alto. The city was es ...
near San Mateo County had also been planned originally. In 2000, Santa Clara County voters approved a 30-year half-cent sales tax increase to fund BART, which took effect in April 2006. To make up for a shortfall in projected federal funding, an increase in the sales tax by 0.125 percent was proposed if additional federal funding were secured. In the process of obtaining the federal funding necessary to build the BART extension, the
Federal Transit Administration The Federal Transit Administration (FTA) is an agency within the United States Department of Transportation (DOT) that provides financial and technical assistance to local public transportation systems. The FTA is one of ten modal administratio ...
issued a "Not Recommended" rating in January 2004. The FTA was concerned about the ability of VTA to operate BART and other bus services at the same time. VTA continued to design BART and prepare the required environmental documents. In 2006, the Santa Clara County Board of Supervisors placed a half-cent general
sales tax A sales tax is a tax paid to a governing body for the sales of certain goods and services. Usually laws allow the seller to collect funds for the tax from the consumer at the point of purchase. When a tax on goods or services is paid to a gove ...
increase for unspecified transportation projects along with other county services. It was advocated by supporters of the BART Silicon Valley extension and labor groups. The measure would have funded improvements to local hospitals, clinics, and transportation. On June 6, 2006, voters defeated the measure by a margin of 58% to 42%. In December 2006, the VTA board authorized $135 million in contract amendments to continue engineering work and environmental clearance on the extension, with a proposal to bring a tax increase to operate the BART extension in 2008. By a two-thirds majority, Santa Clara County voters approved Measure B in November 2008, implementing a 30-year, 1/8-cent local sales tax dedicated solely to funding the operating and maintenance costs associated with the BART Silicon Valley extension. The 2008 Measure B sales tax took effect in July 2012. The economy worsened in 2009, and the 2000 sales tax was projected to generate $7 billion—short of the originally expected $11 billion. As a consequence, the number of planned stations was reduced. In addition, the line from Berryessa to downtown San Jose was delayed until 2026, pushed back from 2025. VTA awarded $770 million to Skanska-Shimmick-Herzog in 2011 for the first phase of the Berryessa Extension (
Milpitas Milpitas (Spanish for "little milpas") is a city in Santa Clara County, California, in Silicon Valley. As of the 2020 census, the city population was 80,273. The city's origins lie in Rancho Milpitas, granted to Californio ranchero José Mar� ...
and Berryessa/North San Jose Stations), and the federal government granted $900 million for the project in 2012. Construction began the same year. It was scheduled to open in 2016. For phase II, VTA sought funding from the federal New Starts program in 2016. A half-cent 30-year sales tax passed in the
2016 elections The following elections occurred in the year 2016. Africa Benin Republic * 2016 Beninese presidential election 6 March 2016 Cape Verde * 2016 Cape Verdean presidential election 2 October 2016 Chad * 2016 Chadian presidential election 10 ...
, to raise $6.0 to $6.5 billion with up to 25% of this (or $1.6 billion) for BART. VTA also sought $1.5 billion from New Starts, and $750 million from the California Cap and Trade program. In 2018, VTA was awarded $2.6 billion for the project from the state's Transit and Intercity Rail Capital Program funded by the 2017 gas tax bill. VTA anticipates receiving a Full Funding Agreement from the FTA in late 2021. In August 2019, the VTA received $125 million from the FTA under a new accelerated funding program. $140 million was included in the version of the
American Rescue Plan Act of 2021 The American Rescue Plan Act of 2021, also called the COVID-19 Stimulus Package or American Rescue Plan, is a economic stimulus bill passed by the 117th United States Congress and signed into law by President Joe Biden on March 11, 2021, to s ...
passed by the House of Representatives, but was dropped in the Senate.


Phases

The project is broken into three phases. ;Notes


Warm Springs extension

The extension to Warm Springs was constructed by BART south from the existing Fremont station (opened in 1972) to the new Warm Springs/South Fremont station; revenue service began in March 2017. The original estimate was $890 million, but the cost of the subway segment under Lake Elizabeth was reduced by 45% from the original estimate of $249 million to $136 million, bringing the total cost to $790 million. The Warm Springs/South Fremont station opened on March 25, 2017. The extension broke ground in 2009, and was originally scheduled for completion in 2014. Construction of the station began in 2011, and was expected to take three and a half years. However, the opening was delayed repeatedly, and ultimately pushed back to spring 2017. The Berryessa Extension extends south from the Warm Springs/South Fremont station.


Berryessa extension

The Berryessa extension to north San Jose encompasses the Milpitas station and the Berryessa station. A proposed infill station at Calaveras Boulevard in downtown Milpitas has been deferred until the city secures funding. Milpitas Station connects to VTA's Milpitas light rail station (formerly known as Montague station) near the
Great Mall of the Bay Area The Great Mall of the Bay Area (often simply called The Great Mall) is a large indoor outlet shopping mall in Milpitas, California built by Ford Motor Land Development and Petrie Dierman Kughn in 1994. It was acquired by Mills Corporation in 200 ...
via a pedestrian bridge. Originally the entire Silicon Valley Extension from Fremont to Santa Clara was proposed as one megaproject, but lower than expected federal funding and sales tax revenue eliminated some stations from the original project and caused the division into two phases. Phase 1 extends to Berryessa, and Phase 2 will extend through downtown San Jose to Santa Clara. The Phase 1 scope was set by what VTA could afford. A local industrial park sued in 2011, without success, on environmental grounds claiming that the extension would reduce vehicular access. The project saw numerous delays, and completion was pushed back many times from the originally-planned 2016.
Milpitas Milpitas (Spanish for "little milpas") is a city in Santa Clara County, California, in Silicon Valley. As of the 2020 census, the city population was 80,273. The city's origins lie in Rancho Milpitas, granted to Californio ranchero José Mar� ...
and Berryessa/North San José stations opened on June 13, 2020.


Downtown San Jose/Santa Clara extension

The final Downtown San Jose/Santa Clara leg has been planned through downtown San Jose to Santa Clara at an estimated cost of $6.8 billion. This third phase, long, is largely underground, featuring a tunnel. It would continue south from Berryessa, entering a tunnel to cross the
Bayshore Freeway The Bayshore Freeway is a part of U.S. Route 101 (US 101) in the San Francisco Bay Area of the U.S. state of California. It runs along the west shore of the San Francisco Bay, connecting San Jose with San Francisco. Within the city of San Fran ...
before continuing to a
28th Street/Little Portugal station 28th Street/Little Portugal station is a proposed underground Bay Area Rapid Transit station in the Little Portugal neighborhood of San Jose, California. It would be located north of East Santa Clara Street between North 28th Street and U.S. Rou ...
on the city's "east side". From there, the tunnel would continue west under Santa Clara Street to a Downtown San Jose subway station, which would be an
interchange station An interchange station or a transfer station is a train station for more than one railway route in a public transport system that allows passengers to change from one route to another, often without having to leave a station or pay an additio ...
to VTA light rail lines on the surface at Santa Clara. The original proposal had additional subway stations between Alum Rock and Downtown at Civic Plaza/
SJSU San José State University (San Jose State or SJSU) is a public university in San Jose, California. Established in 1857, SJSU is the List of oldest schools in California, oldest public university on the West Coast of the United States, West Coas ...
and
Plaza de César Chávez The Plaza de César Chávez is an urban plaza and park in Downtown San Jose, California. The plaza's origins date to 1797 as the ''plaza mayor'' of the Alta California, Spanish ''Pueblo de San José de Guadalupe'', making it the oldest public sp ...
, but these were consolidated into a single station to cut costs. The line would continue underground to the
San Jose Diridon station San Jose Diridon station is the central passenger rail depot for San Jose, California. It also serves as a major intermodal transit center for Santa Clara County and Silicon Valley. The station is named after former Santa Clara County Supervisor ...
, a transfer point to Amtrak, Caltrain,
Altamont Corridor Express The Altamont Corridor Express (also known as ACE, formerly Altamont Commuter Express) is a commuter rail service in California, connecting Stockton and San Jose during peak hours only. ACE is named for the Altamont Pass, through which it ru ...
,
VTA light rail VTA Light Rail is a light rail system in San Jose and nearby cities in Santa Clara County, California. It is operated by the Santa Clara Valley Transportation Authority, or VTA, and consists of of network comprising three main lines on stand ...
and bus, and the planned
California High-Speed Rail California High-Speed Rail (also known as CAHSR or CHSR) is a publicly funded high-speed rail system currently under construction in California in the United States. Planning for the project began in 1996, when the California Legislature and Gover ...
system. The proposed BART subway station would be named "Diridon" to match. The extension would then surface and continue to the site of the current Santa Clara Caltrain Station. A BART maintenance yard would also be created at Newhall as part of this phase, using land just south of Santa Clara station that was purchased by VTA from Union Pacific. Like the Berryessa Extension, it would be built by VTA, but operated by BART. After funding was secured for Berryessa (the first phase of the Silicon Valley Extension) in March 2012, VTA began looking for additional funding to complete the $6.8 billion second phase. Completion is expected in 2029–2030. In late 2017, a disagreement arose between VTA and BART over whether the tunnel should have a single bore or dual bores. VTA favored a single bore, configured as a double-deck stack, with one track on the upper level and one on the lower level. VTA preferred a single bore to shorten the construction schedule and avoid
cut and cover A tunnel is an underground passageway, dug through surrounding soil, earth or rock, and enclosed except for the entrance and exit, commonly at each end. A pipeline is not a tunnel, though some recent tunnels have used immersed tube cons ...
construction in Santa Clara Street for station sites. City officials believed cut and cover construction would be disruptive to streets and businesses, citing the construction of the Market Street Subway as evidence. The single-bore design is newer, but less tested in the United States. However, BART preferred dual bores, as used elsewhere in its system, to cut construction cost and standardize the procedure for emergency evacuations. The twin bores would each be wide, and separated horizontally. Local businesses, cities and VTA were lobbying for a single bore in 2018. The design decision was postponed for three months; in March, BART and VTA reached agreement on a single bore. The $125 million contract for engineering the single bore tunnel was awarded to a
joint venture A joint venture (JV) is a business entity created by two or more parties, generally characterized by shared ownership, shared returns and risks, and shared governance. Companies typically pursue joint ventures for one of four reasons: to acces ...
bid placed by
London London is the capital and List of urban areas in the United Kingdom, largest city of England and the United Kingdom, with a population of just under 9 million. It stands on the River Thames in south-east England at the head of a estuary dow ...
-based Mott MacDonald and San Francisco-based PGH Wong Engineering. Initial construction and soil sampling began in January 2019. In September, it was announced that the project would be delayed three to four years, with revenue service to begin in 2029–2030. On October 15, 2021, VTA announced that it would award construction contracts for this phase's stations in summer 2022. In May 2022, the first major contract for the Downtown San Jose/Santa Clara extension was approved.


See also

*
Bay Area Rapid Transit expansion Throughout the history of Bay Area Rapid Transit, there have been plans to extend service to other areas. History The initial 1962 BART maps approved by voters included several lines beyond the core system marked as ''Possible Future Extensio ...
*
List of Bay Area Rapid Transit stations Bay Area Rapid Transit (BART) is a heavy rail rapid transit system in the San Francisco Bay Area in California, United States. With average weekday ridership around passengers in , BART is the fifth busiest rapid transit system in the United Sta ...


References


External links


VTA.org: BART extension webpage

San Jose Mercury News: BART news section

MTC.gov report on extension
{{coord missing, California Bay Area Rapid Transit Proposed public transportation in the San Francisco Bay Area Public transportation in Alameda County, California Public transportation in Santa Clara County, California Transportation in San Jose, California Milpitas, California Santa Clara, California Silicon Valley Proposed railway lines in California Railway lines opened in 2020 2029 in rail transport