The Rooppur Nuclear Power Plant () is a 2.4 GWe nuclear power plant currently under construction in
Bangladesh Bangladesh, officially the People's Republic of Bangladesh, is a country in South Asia. It is the List of countries and dependencies by population, eighth-most populous country in the world and among the List of countries and dependencies by ...
. It consists of two 1200 MWe
VVER-1200 The water-water energetic reactor (WWER), or VVER (from ) is a series of pressurized water reactor designs originally developed in the Soviet Union, and now Russia, by OKB Gidropress. The idea of such a reactor was proposed at the Kurchatov Insti ...
reactors. The nuclear power plant is being constructed at Rooppur in
Ishwardi Upazila Ishwardi (, ''Ish-shordi'', officially ''Ishurdi'') is an upazila of Pabna District in Rajshahi Division. It is the westernmost upazila of Pabna district. This upazila is a dynamic administrative region with a rich cultural heritage and significan ...
on the bank of the river
Padma The Padma () is a major river in Bangladesh. It is the eastern and main distributary of the Ganges, flowing generally southeast for to its confluence with the Meghna River, near the Bay of Bengal. The city of Rajshahi is situated on the bank ...
, about 160 km northwest of
Dhaka Dhaka ( or ; , ), List of renamed places in Bangladesh, formerly known as Dacca, is the capital city, capital and list of cities and towns in Bangladesh, largest city of Bangladesh. It is one of the list of largest cities, largest and list o ...
. It will be the country's first
nuclear power plant A nuclear power plant (NPP), also known as a nuclear power station (NPS), nuclear generating station (NGS) or atomic power station (APS) is a thermal power station in which the heat source is a nuclear reactor. As is typical of thermal power st ...
, and the first of the two units is expected to become operational in December 2025.


History


Planning

The plan to establish a nuclear power plant in the then
East Pakistan East Pakistan was the eastern province of Pakistan between 1955 and 1971, restructured and renamed from the province of East Bengal and covering the territory of the modern country of Bangladesh. Its land borders were with India and Burma, wit ...
was made in 1961. In 1963, the Rooppur village of the Pabna district was selected for the proposed plant and 260 acres of land was acquired. The plan was to establish a 200MW nuclear power plant on the selected site. The plan to construct a 200 MW power plant was completed in 1969 with the assistance of Belgium. However, in 1969-1971, the project was scrapped by the then
Pakistan government The Government of Pakistan () (abbreviated as GoP), constitutionally known as the Federal Government, commonly known as the Centre, is the national authority of the Islamic Republic of Pakistan, a federal republic located in South Asia, cons ...
. After Bangladesh gained
independence Independence is a condition of a nation, country, or state, in which residents and population, or some portion thereof, exercise self-government, and usually sovereignty, over its territory. The opposite of independence is the status of ...
, the
government of Bangladesh The government of the People's Republic of Bangladesh () is the central government of Bangladesh. The government was constituted by the Constitution of Bangladesh comprising the executive (the president, prime minister and cabinet), the ...
resumed the effort to construct the 200-megawatt nuclear power plant. From 1977–86, the French company MS Sofratom carried out a feasibility study and determined that the Rooppur project was viable. Subsequently, the Executive Committee of the National Economic Council (ECNEC) approved a 125 MW nuclear power plant. However, the project did not materialize. In 1987–88, another feasibility study was conducted by Lahmeyer International and Motor Columbus which proved that the site was technically, economically, and financially viable for a 300-500 MW nuclear power plant. Between 1997 and 2001, the Bangladesh Atomic Energy Commission (BAEC) embarked on a new initiative to develop a nuclear power plant with a capacity of 600 MW. In 2005, Bangladesh signed a nuclear cooperation agreement with China. Two years later, in 2007, the Bangladesh Atomic Energy Commission (BAEC) put forth a proposal for the construction of two 500 MW nuclear reactors in Rooppur, aiming for completion by 2015. In 2008, the Bangladeshi government reaffirmed its commitment to collaborate with China on the construction of the Rooppur Nuclear Power Plant, with China extending an offer of financial support for the project. A year later, on 13 May 2009, BAEC signed a memorandum of understanding (MoU) with
Rosatom State Atomic Energy Corporation Rosatom (commonly referred to as Rosatom rus, Росатом, p=rosˈatəm}), also known as Rosatom State Nuclear Energy Corporation, (), or Rosatom State Corporation, is a Russian State corporation (Russia), sta ...
on "Cooperation in Using Nuclear Energy for Peaceful Purpose". Then, on 21 May 2010, Bangladesh and the Russia signed a framework agreement on "Cooperation in Using Nuclear Energy for Peaceful Purpose". On 10 November 2010, the National Parliament of Bangladesh made the decision to proceed with the immediate implementation of a nuclear power project. In 2011,
International Atomic Energy Agency The International Atomic Energy Agency (IAEA) is an intergovernmental organization that seeks to promote the peaceful use of nuclear technology, nuclear energy and to inhibit its use for any military purpose, including nuclear weapons. It was ...
conducted ''IAEA Integrated Nuclear Infrastructure Review (INIR)'' mission in Bangladesh to understand the state of Bangladesh's nuclear infrastructure. Later on the same year, IAEA examined and offered suggestions for the national nuclear power infrastructure. On 15 January 2013, Bangladesh and Russia established an Intergovernmental Credit Agreement worth US$500 million to fund the preparatory phase activities of the Power Plant, and construction of the first phase of the project was also approved on 2 April of the same year. On 27 June 2013, the Bangladesh Atomic Energy Commission (BAEC) and
Atomstroyexport Atomstroyexport (ASE) JSC () is the Russian Federation's nuclear power equipment and service exporter. It is a fully owned subsidiary of Rosatom. Organization Atomstroyexport, along with Atomenergoprom, is part of Rosatom's ''Engineering Divi ...
signed the first contract, which covered the Feasibility Studies, Engineering Survey, and Environmental Impact Assessment. On 2 October of the same year, a second contract was signed between the same two entities for the development of design documentation, which included first priority working documentation and necessary engineering surveys. Subsequently, a third contract was signed on 5 June 2014, concerning the "Performance of First Priority Works for the Preparatory Stage of Rooppur NPP Construction". In 2015, Rosatom offered to build two units featuring
VVER-1200 The water-water energetic reactor (WWER), or VVER (from ) is a series of pressurized water reactor designs originally developed in the Soviet Union, and now Russia, by OKB Gidropress. The idea of such a reactor was proposed at the Kurchatov Insti ...
reactors which increased the total output to 2400 MW, up from the initial offer of two VVER-1000 reactors with a total capacity of 2000 MW made in 2010.


General contract

On 25 December 2015, representatives of the Bangladesh Atomic Energy Commission and the Russian state nuclear corporation Rosatom signed the general contract for Rooppur nuclear power plant worth US$12.65 billion. The general contract for the construction of two units is an EPC (Engineering, Procurement, and Construction) contract and it includes construction, installation, erection work, the development of working documentation, the supply of equipment and materials, nuclear fuel for initial loading and two reloads, personnel training, and commissioning. Furthermore, the contract includes the delivery of nuclear fuel from Russia as part of the construction work until 2027. This differs from the contract awarded to Rosatom for the
Kudankulam Nuclear Power Plant Kudankulam Nuclear Power Plant (or Kudankulam NPP or KKNPP) is the largest nuclear power station in India, situated in Kudankulam in the Tirunelveli district of the southern Indian state of Tamil Nadu. Construction on the plant began on 31 Ma ...
, which was limited to Engineering and Procurement (EP), with the Indian side responsible for construction and commissioning. Following this development, three days later, '' The Daily Star'' echoed criticism from Germany-based
Transparency International Transparency International e.V. (TI) is a German registered association founded in 1993 by former employees of the World Bank. Based in Berlin, its nonprofit and non-governmental purpose is to take action to combat global corruption with civil s ...
about increased costs, from statements of around US$4 billion made earlier in the same year.


Technology selection

The Bangladesh Atomic Energy Commission (BAEC) considered building a power plant using VVER-1000 technology or equivalent from other suppliers in 2007, estimating costs between $0.9 billion and $2 billion. By 2009, Russia proposed constructing two units using AES-92 technology, which the government of Bangladesh responded to favorably. In October 2013, Valery Limarenko, president of the United Company NIAEP-Atomstroyexport, said that he expected the Rooppur Nuclear Project to be based on a modified AES-2006 design. This was followed in 2014 by Moscow
Atomenergoprom Atomenergoprom (Atomic Energy Power Corporation, AEP, ) is a 100% state-owned holding company that unifies the Russian civil nuclear industry. It is a part of the Rosatom state corporation. History Atomenergoprom was created by a Presidential Decr ...
's confirmation that it would deliver two units based on the AES-2006 design, with Novovoronezh II designated as the reference plant for the project. As discussions progressed, several Bangladeshi media outlets reported in 2015 that Russia was seeking to supply
VVER-TOI The VVER-TOI or WWER-TOI () is a generation III+ nuclear power reactor based on VVER technology developed by Rosatom. The VVER-TOI design is intended to improve the competitiveness of Russian VVER technology in international markets. It would us ...
reactors. However, in September 2013, Marat Mustasin, general director of Atomenergoproekt, clarified in an interview with Nuclear.Ru that although the geological survey at Rooppur would be conducted under the VVER-TOI project, a decision on which specific reactor design the plant would be adjusted to would be made later.


Construction

On 4 November 2017, the Bangladesh Atomic Energy Commission received, from the Bangladesh Atomic Energy Regulatory Authority, the design and construction license of Unit 1, paving the way for the nuclear island first concrete pour. The
nuclear reactor A nuclear reactor is a device used to initiate and control a Nuclear fission, fission nuclear chain reaction. They are used for Nuclear power, commercial electricity, nuclear marine propulsion, marine propulsion, Weapons-grade plutonium, weapons ...
and critical infrastructure are being built by Russian companies.
Atomenergomash Atomenergomash JSC (AEM Group) (, AEM Holding company) is a Russian power engineering company, a supplier of products for nuclear and thermal power plants, natural gas and petrochemical industry, shipbuilding, and special steel markets. It is the ...
is the engineering division of Russia's state nuclear corporation, Rosatom. This company is the supplier of all the equipment for the reactor compartment of Rooppur Nuclear Power Plant and a significant part of the equipment for the machine room. On 14 July 2018, the first concrete was poured for Unit 2. The following month, Rosatom began installing a 200-tonne core catcher as the first large piece of equipment in the reactor building of Rooppur 1, describing it as "a unique protection system". When the
COVID-19 pandemic The COVID-19 pandemic (also known as the coronavirus pandemic and COVID pandemic), caused by severe acute respiratory syndrome coronavirus 2 (SARS-CoV-2), began with an disease outbreak, outbreak of COVID-19 in Wuhan, China, in December ...
struck Bangladesh in early 2020, many projects such as the
Dhaka Metro Rail The Dhaka Metro Rail () is a rapid transit, mass rapid transit system serving Dhaka (currently from Uttara North to Motijheel), the capital and largest city of Bangladesh. It is operated by the Dhaka Mass Transit Company Limited (DMTCL). Toget ...
were stalled, but the Rooppur Nuclear Power Plant remained on track to be completed by 2023 or 2024. Progress in this period included Rosatom's engineering company
Atommash Atommash () is a multidisciplinary engineering company located in Volgodonsk, Rostov Oblast, Russia. It was established in 1976 as a nuclear engineering corporation. Following Privatization in Russia, privatization and bankruptcy in 1999, the ...
completing hydraulic tests for Rooppur unit 1.
Russia's invasion of Ukraine On 24 February 2022, , starting the largest and deadliest war in Europe since World War II, in a major escalation of the Russo-Ukrainian War, conflict between the two countries which began in 2014. The fighting has caused hundreds of thou ...
in 2022, however, meant international sanctions and restrictions on movement of Russian capital and personnel. By 2022, Russia claimed its work on the plant was unaffected. Concrete work for Unit 2 was completed in January 2024. On 18 December 2018, Rosatom announced that its Engineering Division had successfully completed the construction and installation work at Unit 1 of the Rooppur Nuclear Power Plant.


Commissioning

On 17 September 2024, the loading of Dummy Fuel Assemblies (DFAs) into the core of Unit 1 started in order to validate reactor hydraulic parameters during circulation flushing, as well as during reactor hot and cold tests.


Expansion

In 2024, Prime Minister
Sheikh Hasina Sheikh Hasina (''née'' Wazed; born 28 September 1947) is a Bangladeshi politician who served as the tenth prime minister of Bangladesh from June 1996 to July 2001 and again from January 2009 to August 2024. Premiership of Sheikh Hasina, Her ...
requested that Rosatom build two additional units upon completion of the first two units.


Safety

The safety of VVER-1200/523 units of the power plant is ensured by emergency core cooling systems, reactor shutdown systems, and heat removal systems. Some of these safety systems are active, while others are passive. All these systems have 2 to 4 times redundancy. The emergency core cooling system of the VVER-1200/523 consists of active and passive systems. Two of the active safety systems that ensure cooling are high pressure injection system (HPIS), and low pressure injection system (LPIS). Both these systems have two independent trains with 100% redundancy. Another active system that ensures cooling is the Emergency and Planned Cooldown System, which comprises the HPIS, LPIS, and the Spent Fuel Pool Cooling System. In contrast, passive cooling of the core is ensured by the four first and eight second stage hydro-accumulator tanks, which are filled with a boric acid solution. Each hydro accumulator tank in the first stage has a capacity of 60 m³, while each tank in the second stage has a capacity of 120 m³. These tanks are designed to automatically inject boric acid solution into the core when the pressure in the Reactor Coolant System falls below a specified threshold. In addition to the safety systems for injecting coolant into the core, there are also systems used for removing heat from the core. One of these systems is the Steam Generator Emergency Cooldown System. It is an entirely closed-loop system. Each train of this system is connected to two steam generators. When the pressure in the steam generator reaches a specific threshold, the valve on the steam lines that lead to the heat exchanger open automatically, allowing the steam to be condensed back into water, after which the water is sent back to the steam generator. Furthermore, the VVER-1200/523 is equipped with a Passive Heat Removal System (PHRS) designed to remove decay heat from the core during a Station Blackout (SBO). This system features four independent trains, each containing two air-cooled heat exchangers. When activated during a loss of AC power, the bypass line of the steam generator opens, directing steam to the air-cooled heat exchangers, which uses atmospheric air to condense the steam and return it to the steam generators. This system requires that 3 out of 4 trains remain operational to ensure effective cooldown and can function indefinitely. The VVER-1200/523 is also equipped with a redundant shutdown system that consists of control rods made of boron carbide and Emergency Boron Injection System (EBIS). In addition to the safety systems for the primary and secondary circuits, the double containment also is equipped with its own safety features designed to prevent radiation release and protect against external events. Among these systems are the Containment Spray System (CSS), Passive Autocatalytic Recombiners (PAR), and the Core Catcher (CC). The Containment Spray System (CSS) lowers pressure and temperature within the containment during a Loss of Coolant Accident (LOCA). The Passive Autocatalytic Recombiners (PAR) remove hydrogen produced from fuel rods during a LOCA by mixing it with oxygen and producing water through a catalytic reaction. The Core Catcher (CC) retains the materials of the molten core, ensures its cooling, and maintains its subcriticality in the event of a meltdown.


Waste


Spent fuel repatriation

The governments of Bangladesh and Russia formalized an inter governmental agreement (IGA) on 30 August 2017, concerning the repatriation of
spent nuclear fuel Spent nuclear fuel, occasionally called used nuclear fuel, is nuclear fuel that has been irradiated in a nuclear reactor (usually at a nuclear power plant). It is no longer useful in sustaining a nuclear reaction in an ordinary thermal reactor and ...
generated by the Rooppur Nuclear Power Plant to Russia. This agreement stipulates the return of the spent nuclear fuel to Russia for purposes of temporary storage, reprocessing, recycling, and the management of the resultant products derived from the reprocessing process.


Liquid radioactive waste management

In July 2022, a contract was signed between the general contractor of Rooppur Nuclear Power Plant,
Atomstroyexport Atomstroyexport (ASE) JSC () is the Russian Federation's nuclear power equipment and service exporter. It is a fully owned subsidiary of Rosatom. Organization Atomstroyexport, along with Atomenergoprom, is part of Rosatom's ''Engineering Divi ...
, and Sverdniikhimmash, a subsidiary of
AtomEnergoMash Atomenergomash JSC (AEM Group) (, AEM Holding company) is a Russian power engineering company, a supplier of products for nuclear and thermal power plants, natural gas and petrochemical industry, shipbuilding, and special steel markets. It is the ...
, for the design, manufacture, and supply of equipment for the management of liquid radioactive waste at the Rooppur Nuclear Power Plant.


Economics


Cost and funding

The project, which is estimated to cost $12.65 billion, is being financed mainly through Russian export credit amounting to $11.38 billion. The interest rate for the Russian loan is set at the 6-month LIBOR rate plus 1.75%, with a maximum limit of 4% per year. The Russian export credit has a 7-year utilization period from 2017 to 2024, with a 10-year grace period and 30-year repayment period. However, during a meeting on February 26, 2025, between Chief Advisor
Muhammad Yunus Muhammad Yunus (born 28 June 1940) is a Bangladeshi economist, entrepreneur, and civil society leader who has been serving as the Chief Adviser of Bangladesh, Chief Adviser of the Interim government of Muhammad Yunus, interim Yunus ministry, g ...
and Rosatom Director General Alexey Likhachev, the utilization period was extended until the end of 2026. An official from the
Ministry of Finance A ministry of finance is a ministry or other government agency in charge of government finance, fiscal policy, and financial regulation. It is headed by a finance minister, an executive or cabinet position . A ministry of finance's portfoli ...
informed The Daily Star that this agreement has not been amended yet because the payment issue remains unresolved. According to the Planning Division's Revised Annual Development Programme for 2024-2025, as of June 2024, BDT 73,746.06 crore has been spent on the project. Additionally, the
Economic Relations Division The Economic Relations Division (ERD) is one of the four divisions of the Ministry of Finance A ministry of finance is a ministry or other government agency in charge of government finance, fiscal policy, and financial regulation. It is head ...
's Annual Report 2023-2024 reports that a total of $7.30 billion had been disbursed to Bangladesh as of the fiscal year 2023-24. The Russian Embassy in Dhaka stated that only the amounts of state export credits that have been used are the debt that the foreign state borrower owes to Russia.


Levelized cost of electricity (LCOE)

A report from the government of Bangladesh estimated the
levelized cost of electricity The levelized cost of electricity (LCOE) is a measure of the average net present cost of electricity generation for a generator over its lifetime. It is used for investment planning and to compare different methods of electricity generation on a ...
(LCOE) at $56.73/MWh. However, a research paper published in 2020 found the LCOE to be between $43.8/MWh and $82.5/MWh, using the Financial Analysis of Electric Sector Expansion Plans (FINPLAN) for nine different postulated scenarios.


Planned nuclear power reactors


Economic justification

Reducing dependence on electricity generated from oil and gas is crucial for Bangladesh due to the depletion of these resources and their adverse effects on the environment. Experts believe that the Rooppur Nuclear Power Plant will play a crucial role in ensuring energy security and reducing CO2 emissions at a low cost. Additionally, a research article published in 2020 indicates that the levelized cost of electricity (LCOE) of the Rooppur NPP is competitive with those of coal, oil, and renewable energy sources. The research article also points out that the LCOE of the Rooppur NPP is currently higher than that of gas-based power plants in Bangladesh. However, this situation may change as the country becomes more reliant on liquefied natural gas (LNG) imported from the international market.


Corruption


Rooppur Pillow Scandal

The Rooppur pillow scandal involved corruption by engineers tasked with furnishing 966 flats for plant workers. This included inflated prices for domestic products, such as pillows that were priced at BDT 5957.


Allegations of embezzlement

On 17 August 2024, Global Defense Corp alleged that former prime minister
Sheikh Hasina Sheikh Hasina (''née'' Wazed; born 28 September 1947) is a Bangladeshi politician who served as the tenth prime minister of Bangladesh from June 1996 to July 2001 and again from January 2009 to August 2024. Premiership of Sheikh Hasina, Her ...
and her family members embezzled over $5 billion in kickbacks for the purchase of two VVER-1200 reactors from Rosatom. However, the website did not provide any sources to support this claim. According to The Bangla Outlook, the website neither provided any sources nor reference any documents to support its claims. In response to allegations of embezzlement, the Russian Embassy in Dhaka issued a press release on 11 September 2024, clarifying that as of 3 September 2024, approximately US$7.3 billion of the US$11.38 billion export credit (set to expire on 31 December 2024) and US$491.3 million out of the US$500 million export credit (which expired in 2017) provided by Russia for the Rooppur Nuclear Power Plant project in Bangladesh has been utilized, and only the utilized portions of state export credits are deemed as the debt of the foreign state borrower. The press release further stated that the absence of any corruption on the Rooppur Nuclear Power Project can be proven by the fact that Russian law does not allow direct transfer of funds of export credits to the sovereign borrower.


Investigation into allegations of embezzlement

On 3 September 2024, the chairman of the National Democratic Movement, Bobby Hajjaj, submitted a petition to the High Court asking the Anti-Corruption Commission (ACC) to investigate allegations of $5 billion in embezzlement from the Rooppur Nuclear Power Plant Project by Sheikh Hasina and her family members. Following this, on 17 December 2024, the ACC announced to reporters that it had initiated an investigation against Sheikh Hasina and her family members, including British MP
Tulip Siddiq Tulip Rizwana Siddiq (born 16 September 1982) is a British Bangladeshi politician who has been the Member of Parliament (MP) for Hampstead and Highgate, previously Hampstead and Kilburn, since 2015. She served as Economic Secretary to the T ...
, regarding allegations of embezzlement amounting to Tk80,000 crore, which includes more than $5 billion (Tk59,000 crore) from the Rooppur Nuclear Power Plant Project.
The Daily Telegraph ''The Daily Telegraph'', known online and elsewhere as ''The Telegraph'', is a British daily broadsheet conservative newspaper published in London by Telegraph Media Group and distributed in the United Kingdom and internationally. It was found ...
reported on February 4, 2025, that the ACC received claims indicating that a luxury flat in London, now valued at £700,000, that had been given to Tulip Siddiq was allegedly purchased with embezzled funds from the Rooppur Nuclear Power Plant project. However, Labour sources clarified that the flat, gifted to Tulip Siddiq by a businessman associated with her aunt, Sheikh Hasina, had been given to her in 2004, suggesting it is not related to the nuclear agreement signed in 2013.


Criticism

Many experts have expressed concerns over the high cost of Rooppur Nuclear Power Plant, arguing that it costs higher than similar projects worldwide. However, a research paper published in 2020 suggests that the Levelized Cost of Electricity (LCOE) for the Rooppur Nuclear Power Plant is expected to be lower than the global average of US 9.59 cents/kWh. The research paper also indicates that the LCOE for Rooppur Nuclear Plant is estimated at US 9.48 cents/kWh, which is similar to the Ostrovets Nuclear Power Plant in Belarus at US 8.03 cents/kWh and the Paks II Nuclear Power Plant under construction in Hungary at US 8.56 cents/kWh, as calculated using the INPRO model. All three projects utilize two VVER-1200 reactors with similar electrical power output.


See also

* Nuclear energy in Bangladesh * Mymensingh Power Station *
List of megaprojects in Bangladesh This is a list of megaprojects of Bangladesh, i.e. projects characterized by large investment commitment, vast complexity (especially in organizational terms), and long-lasting impact on the economy, the Biophysical environment, environment, and s ...


References

{{Electricity generation in Bangladesh Nuclear power in Bangladesh Nuclear power stations with reactors under construction Proposed power stations in Bangladesh Bangladesh–Russia relations