Kriegers Flak (wind farm)
   HOME

TheInfoList



OR:

Kriegers Flak is a 600  MW offshore
wind farm A wind farm or wind park, also called a wind power station or wind power plant, is a group of wind turbines in the same location used to produce electricity. Wind farms vary in size from a small number of turbines to several hundred wind turb ...
under construction in the
Baltic Sea The Baltic Sea is an arm of the Atlantic Ocean that is enclosed by Denmark, Estonia, Finland, Germany, Latvia, Lithuania, Poland, Russia, Sweden and the North and Central European Plain. The sea stretches from 53°N to 66°N latitude and ...
on the Danish part of the reef of the same name. It will form part of a new 400 MW
interconnector An interconnector (also known as a DC tie in the USA) is a structure which enables high voltage DC electricity to flow between electrical grids. An electrical interconnector allows electricity to flow between separate AC networks, or to link sy ...
between Denmark and Germany.


Location

In 2010 the
Danish Energy Agency The Danish Energy Agency (Danish: Energistyrelsen) was established in 1976 as an agency of the Danish Ministry of Transport. It was part of the Ministry of Environment and Energy from 1994 to 2001. In 2007 it came under the newly created Danish Min ...
pointed to the site as one of the most attractive for a Danish offshore wind farm. In addition to favorable wind conditions and a depth ranging from 16 m to 25 m, Kriegers Flak will also be located next to the German offshore wind farm ″ EnBW Baltic 2″. Kriegers Flak will take advantage of this and be connected both to the Danish grid as well as to the 288 MW ″EnBW Baltic 2″ which is connected via the 48 MW ″EnBW Baltic 1″ to the German grid. The wind farm will consist of two partitions, a western of 200 MW covering and an eastern of 400 MW covering ; a sand dredging area separates the two areas.


Combined Grid Solution

The Kriegers Flak Combined Grid Solution, a serial connection of offshore wind farms into the power grids of two different countries will be the first of its kind. This has the advantage that up to the capacity of the connection the produced power can be transmitted to the country with the highest demand and price, improving the economy of the wind farms. Secondly, the connection between Denmark and Germany can act as an interconnector, so power can be transmitted from one country to the other, also in absence of power production from the wind farms themselves. This improves the overall reliability of the power grids in both countries and can also reduce the overall price of the electricity. The combined solution was scheduled to be direct current, but the offshore converter turned out to be prohibitively expensive, and
alternating current Alternating current (AC) is an electric current which periodically reverses direction and changes its magnitude continuously with time in contrast to direct current (DC) which flows only in one direction. Alternating current is the form in whic ...
(AC) was chosen instead. Like the 150 kV cables connecting the ″EnBW Baltic 2″, ″Baltic 1″ and Germany, the 170kV cables connecting Kriegers Flak to ″Baltic 2″ and the 220kV to Denmark will be relatively short and thus using AC which is more economical. However, Germany is part of the
synchronous grid of Continental Europe The synchronous grid of Continental Europe (also known as Continental Synchronous Area; formerly known as the UCTE grid) is the largest synchronous electrical grid (by connected power) in the world. It is interconnected as a single phase-locked ...
, while Kriegers Flak will connect to eastern Denmark, which is synchronized with the Nordic grid. As such, the non-synchronous connection requires a paired, back-to-back
HVDC A high-voltage direct current (HVDC) electric power transmission system (also called a power superhighway or an electrical superhighway) uses direct current (DC) for electric power transmission, in contrast with the more common alternating curre ...
converter substation, to be located in
Bentwisch Bentwisch is a municipality in the Rostock district, in Mecklenburg-Vorpommern, Germany, to the east of Rostock. Since its merger with Klein Kussewitz in January 2018, the municipality has 3,174 inhabitants and covers 29.19 square kilometres. Due ...
, Germany, which already hosts the converter substation for the
Kontek The Kontek HVDC is a long, monopolar 400 kV high-voltage direct current cable between Germany and the Danish island Zealand. Its name comes from "continent" and the name of the former Danish power transmission company "Elkraft", which o ...
interconnector. The transmission capacity will be 400 MW, with the converter substation being delivered by
ABB ABB Ltd. is a Swedish- Swiss multinational corporation headquartered in Zürich, Switzerland. The company was formed in 1988 when Sweden's Allmänna Svenska Elektriska Aktiebolaget (ASEA) and Switzerland's Brown, Boveri & Cie merged to crea ...
for around 140M US$. Thus, when Kriegers Flak operates at its full 600 MW capacity at least one third of the produced power must be transmitted to Denmark. The 220 kV cables to Kriegers Flak will be constructed and operated by
Energinet.dk Energinet is the Danish national transmission system operator for electricity and natural gas. It is an independent public enterprise owned by the Danish state under the Ministry of Climate and Energy. Energinet has some 1150 employees, a ...
, with a planned spending of 3.5 billion DKK and planned commissioning by the end of 2018. The cable will reach Denmark at Rødvig on
Zealand Zealand ( da, Sjælland ) at 7,031 km2 is the largest and most populous island in Denmark proper (thus excluding Greenland and Disko Island, which are larger in size). Zealand had a population of 2,319,705 on 1 January 2020. It is the 1 ...
. In June of 2019 NKT stated that they had successfully commissioned the 170 kV AC cable between Kriegers Flak and Baltic 2 and that the remaining 220 kV AC cable between Kriegers Flak and Denmark would become operational later in 2019. In November 2020, the European Union allowed the connection to transmit available wind power to shore rather than conform to the 70% market transmission rule.


Tender

The result of a call for tenders for the construction of the wind farm was expected to be published by the end of 2016. By November 2015 seven companies and consortia had been prequalified to bid on the project; an unusually high number of bidders. The tender was won by Vattenfall in November 2016 at a fixed-price of €49.90/MWh ($/MWh) with no adjustment for inflation, for 30 TWh (corresponding to 50,000 full-load hours for 600 MW, or about 11 years), without the cost of the unusual transmission project. , it is the lowest price for offshore wind. The price is 58% lower than the cap price of €0.12 (90 øre) per kWh set in 2012. Build cost is estimated at €1.1bn-€1.3bn ($1.19bn-$1.4bn). The turbines will be delivered by Siemens Gamesa, each yielding 8.4 MW. The low price was achieved by optimizing several aspects of the process, including the long-standing policy of authorities to prepare
shovel ready In politics, a shovel ready construction project (usually larger-scale infrastructure) is where planning and engineering is advanced enough that—with sufficient funding—construction can begin within a very short time. The term was popularized ...
projects with all necessary permissions. This method was also used in the previous low price record at
Borssele Borssele is a village in the Dutch province of Zeeland. It is a part of the municipality of Borsele, and lies about 12 km east of Vlissingen. Note that the municipality name is spelled with a single ''s'' while the name of the town is spelled ...
where the price is €72.70/MWh (€87/MWh with transmission). The method contrasts with the British way of tender, where applicants must perform preparatory work.


Construction

May 2018 saw installation of the three offshore converter stations that will transmit the electricity from the wind turbines to the onshore substations in Denmark and Germany and in November 2018 its dual electric connection to the offshore station of ''EnBW Baltic 2'' was successfully tested. While the construction at the Danish substation site was underway by August 2018, the construction of the similar German station in Bentwisch has been delayed by "a few months" so as of January 2019 the launch of the interconnector is planned for Q3 of 2019. Monopile foundations were being constructed in early 2019. Turbines are prepared at the port of
Rønne Rønne ( sv, Rönne) is the largest town on the Danish island of Bornholm in the Baltic Sea. It has a population of 13,807 (1 January 2022). It was a municipality in its own right from 1970 until 2002, when Bornholm was a county ( Danish: ''Born ...
on Bornholm and put 4 at a time on a wind turbine installation vessel, then sailed to the site and erected. By April 2021, 36 turbines (half of the total 72) had been installed. The wind farm is expected to be operational by the end of 2021.


See also

*
Renewable energy in Denmark Denmark is a leading country in wind energy production and wind turbine production. Wind power alone produced 47% of Denmark's electricity consumption in 2017, and is expected to increase its production by nearly 80% in the years to 2024. Denma ...
*
List of offshore wind farms in Denmark This is a list of operational, offshore wind farms in Denmark (within the national maritime boundaries). Denmark's wind power generation is the highest in the world as a fraction of domestic consumption, reaching 47% in 2019. Data is primarily ...
*
List of offshore wind farms This article lists the largest offshore wind farms that are currently operational rated by nameplate capacity. It also lists the largest offshore wind farms currently under construction, the largest proposed offshore wind farms, and offshore w ...
*
Baltic 1 Offshore Wind Farm EnBW Baltic 1 is the first commercial offshore wind farm of Germany in the Baltic Sea. Siemens supplied 21 SWT 2.3-93 wind turbines for the 48.3 megawatt wind farm. EnBW Baltic 1 is located about north of the Darss-Zingst Pen ...
*
Kontek The Kontek HVDC is a long, monopolar 400 kV high-voltage direct current cable between Germany and the Danish island Zealand. Its name comes from "continent" and the name of the former Danish power transmission company "Elkraft", which o ...


References

{{Reflist


External links


Important documents and links
Energistyrelsen
Technical Project Description
October 2015
Energinet project page
(in Danish) Electrical interconnectors to and from the Nordic grid Electrical interconnectors to and from the Synchronous Grid of Continental Europe Offshore wind farms in the Baltic Sea Wind farms in Denmark 2018 establishments in Denmark Energy infrastructure completed in 2018