Contractual Provisions Relating To Time
   HOME

TheInfoList



OR:

Several terms and common clauses are used in
contract A contract is an agreement that specifies certain legally enforceable rights and obligations pertaining to two or more parties. A contract typically involves consent to transfer of goods, services, money, or promise to transfer any of thos ...
s to refer to time, including usage in reference to the time at which, or the length of the period during which, a contracted activity is to be undertaken.


Time is of the essence

"Time is of the essence" is a term used in
contract law A contract is an agreement that specifies certain legally enforceable rights and obligations pertaining to two or more Party (law), parties. A contract typically involves consent to transfer of goods, Service (economics), services, money, or pr ...
in
England and Wales England and Wales () is one of the Law of the United Kingdom#Legal jurisdictions, three legal jurisdictions of the United Kingdom. It covers the constituent countries England and Wales and was formed by the Laws in Wales Acts 1535 and 1542. Th ...
(a legal jurisdiction within the
United Kingdom The United Kingdom of Great Britain and Northern Ireland, commonly known as the United Kingdom (UK) or Britain, is a country in Northwestern Europe, off the coast of European mainland, the continental mainland. It comprises England, Scotlan ...
), Canada, Australia, New Zealand, other Commonwealth countries and the
United States The United States of America (USA), also known as the United States (U.S.) or America, is a country primarily located in North America. It is a federal republic of 50 U.S. state, states and a federal capital district, Washington, D.C. The 48 ...
, expressing the need for timely performance of a contractual obligation, i.e. indicating that one or more parties to the agreement must perform by the time to which the parties have agreed if a delay will cause
material A material is a matter, substance or mixture of substances that constitutes an Physical object, object. Materials can be pure or impure, living or non-living matter. Materials can be classified on the basis of their physical property, physical ...
harm. Were a ''time is of the essence'' clause is included in a contract, a court may nonetheless determine that minor delay did not cause material harm and thus that no
breach of contract Breach of contract is a legal cause of action and a type of civil wrong, in which a binding agreement or bargained-for exchange is not honored by one or more of the parties to the contract by non-performance or interference with the other part ...
occurred. "Time is of the essence" may be contrasted with " reasonable time", where a delay in performing may be justified if it is reasonably required, based upon subjective circumstances such as unexpected weather, and with the phrase ''time at large'', which describes a situation where a party to a contract is relieved from the duty to perform work by a specific deadline due to actions of the principal that prevent timely completion. "Time is of the essence" may also be contrasted with an "express condition", where a specific contract term must be performed to avoid breach, such as in the Court of Appeals of Indiana's decision in ''Dove v. Rose Acre Farms, Inc.'' 434 N.E.2d 931 (Ct. App. Ind. 1982).


Time at large

"Time at large" is a
common law Common law (also known as judicial precedent, judge-made law, or case law) is the body of law primarily developed through judicial decisions rather than statutes. Although common law may incorporate certain statutes, it is largely based on prece ...
principle Bellhouse, J. and Cowan, P.
Common Law “Time at Large” Arguments in a Civil Law Context
''White & Case, LLP'', 2008, accessed 20 December 2022
which is covered by a large body of case law.Linares, T.
Time at Large and Extension of Time Principles
''Project Value Delivery'', published in January 2013, accessed on 11 November 2024
It can arise in four types of situation: *where no time for performance has ever been agreed as part of the contract *where a time which was fixed has ceased to apply, by agreement or an act which prevents its fulfillment, including an employer's act of prevention affecting completion *where the employer has waived the right to insist on completion by the agreed date, or where the contractor is in breach of contract but the employer elects to continue with the contract on a delayed basis, or *where the employer has failed to comply with the certification process, if this prevents the contract being administered correctly.David Atkinson Ltd.
Time at Large
published 2002, updated 8 April 2007, archived 7 April 2008, accessed 9 December 2022
The case of ''Holme v Guppy'' (1838) confirms the "prevention principle", which states that "if the party be prevented by the refusal of the other contracting party from completing the contract within the time limited he is not liable in law for the default". Where time is "at large", there is an implied term obliging the contractor to complete the work within a reasonable time. The facts of the case will determine what is a reasonable time. It is generally agreed that it is not in the interests of either an employer or a contractor to move into time being "at large", and Bellhouse and Cowan note that most forms of contract now have "adequate extension of time procedures", so it has become difficult to argue that an "at large" situation has arisen in most situations. "The principle in Bramall & Ogden" (referring to the case of Bramall & Ogden v Sheffield City Council (1983) 29 BLR 73) established that confused legal drafting can give rise to a situation where time is "at large" due to the absence of agreement on contractual time for performance. In this case, Sheffield had contracted for the construction of 123 houses, which were completed on various dates. The contract provided for liquidated damages applicable on the number of houses incomplete, and stated a date for completion as 6 December 1976. The contract did not provide for sectional completion and the court held that the sectional basis on which the liquidated damages clause was to operate was inconsistent with the single end-date for anticipated completion, meaning that Sheffield were unable to enforce a damages claim for delay. In ''Bruno Zornow (Builders) Ltd v Beechcroft Developments'' (1990), a contract which originally provided for a project's "preliminary works" was later extended to include further works measured against an agreed work programme. The preliminary works had a clear and binding deadline but this was not amended to take account of the further works. The court was required to determine whether "time at large" applied for the further works, subject only to an implied term that it be finished within a reasonable time, or that a contractual date for completion was to be implied. The court held the date which both parties had in mind for the completion of the whole project when the first tender was submitted, as amended by subsequent architect extensions, should apply as the contractual completion date. "Time at large" arguments may also be utilised in a civil law context.


Extension of time

Standard form contracts such as the Joint Contracts Tribunal (JCT) contract and the New Engineering Contract (NEC) family include various mechanisms for extending contracts to account for delay but still retain the need for the works to be completed by an agreed date.Mendelle, J. and Raja, U.
Extension of time - differing approaches under standard form construction contracts
''Sharpe Pritchard'', published 19 January 2017, accessed 28 September 2023


See also

* Date certain * Reasonable time * Laches


References

Contract law {{UK-law-stub