The Barakah nuclear power plant ( ar, محطة براكة للطاقة النووية) is the
United Arab Emirates The United Arab Emirates (UAE; ar, اَلْإِمَارَات الْعَرَبِيَة الْمُتَحِدَة ), or simply the Emirates ( ar, الِْإمَارَات ), is a country in Western Asia (Middle East, The Middle East). It is ...
' first
nuclear power Nuclear power is the use of nuclear reactions to produce electricity. Nuclear power can be obtained from nuclear fission, nuclear decay and nuclear fusion reactions. Presently, the vast majority of electricity from nuclear power is produced ...
station, the first nuclear power station in the
Arabian Peninsula The Arabian Peninsula, (; ar, شِبْهُ الْجَزِيرَةِ الْعَرَبِيَّة, , "Arabian Peninsula" or , , "Island of the Arabs") or Arabia, is a peninsula of Western Asia, situated northeast of Africa on the Arabian Plate. ...
, the second in the Persian Gulf region and the first commercial nuclear power station in the
Arab World The Arab world ( ar, اَلْعَالَمُ الْعَرَبِيُّ '), formally the Arab homeland ( '), also known as the Arab nation ( '), the Arabsphere, or the Arab states, refers to a vast group of countries, mainly located in Western As ...
. It consists of four APR-1400 nuclear reactors (three operating, one undergoing post-construction testing). Total
nameplate capacity Nameplate capacity, also known as the rated capacity, nominal capacity, installed capacity, or maximum effect, is the intended full-load sustained output of a facility such as a power station,
is 5380 MW which is intended to supply up to 25% of UAE's electricity needs. The site is in the Gharbiya region of
Abu Dhabi Abu Dhabi (, ; ar, أَبُو ظَبْيٍ ' ) is the Capital city, capital and List of cities in the United Arab Emirates, second-most populous city (after Dubai) of the United Arab Emirates. It is also the capital of the Emirate of Abu Dha ...
, on the coastline between the
Persian Gulf The Persian Gulf ( fa, خلیج فارس, translit=xalij-e fârs, lit=Gulf of Fars, ), sometimes called the ( ar, اَلْخَلِيْجُ ٱلْعَرَبِيُّ, Al-Khalīj al-ˁArabī), is a mediterranean sea in Western Asia. The body ...
and the E11 highway, 50 km west of
Ruwais ''Ar-Ruwais'' ( ar, ٱلـرُّوَيْـس, lit=The Small head) is a city located some west of Abu Dhabi City, in the Western Region of the Emirate of Abu Dhabi. "Al Ruwais" is largely dropped in relation to the Ruwais Refinery and other i ...
.


History


Contracting

In December 2009,
Emirates Nuclear Energy Corporation The Emirates Nuclear Energy Corporation (ENEC, مؤسسة الإمارات للطاقة النووية) is the entity responsible for the deployment and ownership of nuclear energy plants in the United Arab Emirates (UAE). ENEC was established by ...
(ENEC) awarded a coalition led by
Korea Electric Power Corporation Korea Electric Power Corporation, better known as KEPCO (Hangul: 켑코) or Hanjeon (Hangul: 한전), is the largest electric utility in South Korea, responsible for the generation, transmission and distribution of electricity and the developme ...
(KEPCO) a $20 billion bid to build the first nuclear power plant in the UAE.
Barakah In Islam, ''Barakah'' or ''Baraka'' ( ar, بركة "blessing") is a blessing power, a kind of continuity of spiritual presence and revelation that begins with God and flows through that and those closest to God. Baraka can be found within physic ...
was chosen as the site to build four APR-1400 nuclear reactors successively, with the first scheduled to start supplying electricity in 2017. In 2011,
Bloomberg Bloomberg may refer to: People * Daniel J. Bloomberg (1905–1984), audio engineer * Georgina Bloomberg (born 1983), professional equestrian * Michael Bloomberg (born 1942), American businessman and founder of Bloomberg L.P.; politician and ...
reported that following detailed finance agreements, the build cost was put at $30 billion and financed with $10 billion equity, $10 billion export-credit agency debt, and $10 billion from bank and sovereign debt. South Korea may earn a further $20 billion from operation, maintenance and fuel supply contracts. A later Bloomberg report indicates the price as $25 billion. As of 22 March 2018, the project's total cost was refined to $24.4 billion to complete. Startup of Unit 1 was delayed to late 2018.


Timeline

The plant's ground-breaking ceremony was held on 14 March 2011, including Korean President Lee Myung-bak. It has four units. Construction of the first unit was begun in the afternoon of 18 July 2012, ahead of its scheduled date in late 2012. This happened despite delays being mooted in the wake of the
Fukushima Daiichi nuclear disaster The was a nuclear accident in 2011 at the Fukushima Daiichi Nuclear Power Plant in Ōkuma, Fukushima, Japan. The proximate cause of the disaster was the 2011 Tōhoku earthquake and tsunami, which occurred on the afternoon of 11 March 2011 and ...
. In May 2013, construction started on the second unit, which was then expected to take five years. The first safety-related concrete was poured for Unit 3 in September 2014. Unit 4 started construction in September 2015. In 2014, the Barakah 1 reactor vessel was delivered onsite and site preparation works for Barakah 3 and 4 started. Meanwhile, the concrete-and-steel reactor containment building for Barakah 1 was completed in January 2015. In March 2015, ENEC applied to
Federal Authority for Nuclear Regulation The United Arab Emirates is installing nuclear-powered plants to meet their electricity demand, which is estimated to increase from 15 GWe to over 40 GWe in 2020. In December 2009, the USA and UAE signed a Section 123 Agreement for peaceful n ...
(FANR) for operating licences for Units 1 and 2. In September 2015, first concrete was poured for Unit 4. More than 18,000 staff were then working on the construction of all 4 units. In December 2017, the rebel
Houthis The Houthi movement (; ar, ٱلْحُوثِيُّون ''al-Ḥūthīyūn'' ), officially called Ansar Allah (' ''Partisans of God'' or ''Supporters of God'') and colloquially simply Houthis, is an Islamist political and armed movement that ...
group claimed to have fired a cruise missile in the direction of the Barakah plant, but the Emirati authorities said that no missiles had actually reached the UAE. In December 2018, it was reported that voids were found in the concrete containment buildings for units 2 & 3. Grease was found to have leaked through the unit 3 containment, which may have been due to a crack in the concrete. Unit 1 was declared complete in 2018. However it was not expected to begin operations until late 2019 or early 2020. In January 2020 it was announced that fuel loading would commence that quarter, about 2.5 years later than the original planned date of August 2017. FANR had raised 400 adverse findings in a review requiring rectification of various technical, organisational and management issues. In March 2020, ENEC announced the completion of the fuel assemblies loading into the Unit 1 reactor. The reactor started generating electricity in August 2020 and entered commercial operation in 2021.


Completion

*Unit 1 is 100% complete as of December 2018. It entered commercial service in April 2021. *Unit 2 is 100% complete as of April 2021. It entered commercial service in March 2022. *Unit 3 is 100% complete as of November 2021. It started producing electricity in October 2022, with commercial operation expected a few months later. *Unit 4 is 89% complete as of April 2021. Overall construction completion rate for the entire plant is at 96%, as of November 2021.


Criticism

In March 2019,
Qatar Qatar (, ; ar, قطر, Qaṭar ; local vernacular pronunciation: ), officially the State of Qatar,) is a country in Western Asia. It occupies the Qatar Peninsula on the northeastern coast of the Arabian Peninsula in the Middle East; it s ...
lodged a letter of complaint to the
International Atomic Energy Agency The International Atomic Energy Agency (IAEA) is an intergovernmental organization that seeks to promote the peaceful use of nuclear energy and to inhibit its use for any military purpose, including nuclear weapons. It was established in 195 ...
(IAEA) regarding the Barakah nuclear power plant, stating concerns about its safety and lack of co-operation with regional states on the project as well as that it poses a serious threat to regional stability and the environment. The UAE denied that there are safety issues with the plant stating that Barakah adheres to the highest standards of nuclear safety and security.


See also

*
Nuclear power in the United Arab Emirates The United Arab Emirates is installing nuclear-powered plants to meet their electricity demand, which is estimated to increase from 15 GWe to over 40 GWe in 2020. In December 2009, the USA and UAE signed a Section 123 Agreement for peaceful n ...
* List of nuclear reactors#United Arab Emirates *
Energy in the United Arab Emirates Energy in the United Arab Emirates describes energy and electricity production, consumption and import in the United Arab Emirates (UAE). UAE has 7% of global proved oil reserves, about 100 billion barrels.Construction photo album
Nuclear power stations in the United Arab Emirates Nuclear power stations with reactors under construction Nuclear power stations using pressurized water reactors Buildings and structures in the United Arab Emirates